135 F. 895 | W.D.N.Y. | 1905
This is a libel in rem, .based upon the statutes ■ of the state of Michigan, to recover the sum of $20,255, balance due for rebuilding, repairing, docking, and equipping the schooner Mary N. Bourlce, owned by George Nester and others, between May 7 and September 20, 1902. The reasonable value of such work performed and materials furnished is alleged to be $25,-255, on account of which respondents paid on August 4, 1902, the sum of $5,000. The libelants are copartners owning and operating a
The necessity for extensive repairs to the Bourke is conceded, for on April 26, 1902, while on a voyage from Duluth, Minn., to Tonawanda, N. Y., loaded with lumber, she collided with the schooner George Nester and stranded off Marquette, Mich. The injured vessel was taken to libelants’ dry dock, at Bay City, for repairs. Upon her arrival a survey was made, in behalf of the owners and the underwriters, to determine the loss. The surveyors estimated that the cost of repair and equipment would amount to $13,405. A supplementary report was made by them, showing the necessity for replacing the mast, which was not included in the original survey. The answer further alleges that respondents relied upon the survey, and that libelants stated that the repairs would not cost near as much as had been anticipated. The evidence, however, does not show that the libelants were parties to such survey, and the court does not understand that respondents claim the libelants were bound thereby. The only significance attaching to this testimony is that it may be considered to show the nature and extent of the injuries to the barge, as well as the repairs which were necessary to put her in seaworthy condition. The bill of particulars specifies the items of work and materials furnished by libelants, and the charges therefor. Neither the extent nor the making of the repairs, other than those specified in the written contract, is disputed. That they were skillfully made is conceded, and no fault is found with the materials used. What was the reasonable value of the repairs and materials furnished ? Was the work upon the vessel unreasonably delayed, and did the claimants suffer loss by such detention?
Giving due weight to the evidence of respondents’ witnesses who testified to the character of the repairs, the timber required, and the labor employed, I conclude that a reasonable deduction must be made upon the various items hereafter enumerated. The evidence on the part of claimants shows that the master of the Bourke, Capt. Hanley, who, in the capacity of their superintendent, was present on the vessel while the repairs were being made, kept a daily record of the work performed, together with the lumber and materials used. Uibelants challenge the detailed statements of this witness on the ground that some of the materials were furnished and a portion of the work performed before he began to keep his tallies or records, and, further, that his measurements of timber were not made at West Bay City, the place of shipment. It is claimed that
Libelants make a charge for timber and planking as follows:
36,023 feet of oak, at $45 per M......... $1,621 04
34,935 “ “ Norway, 40 to 60 ft., at $45 1,572 08
32,093 “ “ pine, 40 to 60 ft., at $45____ 1,444 19
8,830 “ “ docking, at $40............. 353 20
$4,990 51
Respondent insists that the testimony of the witnesses Hanley and Williams shows that only 73,591 feet of timber was used; but, as-already intimated, the tallies of Hanley are not entitled to outweigh libelants’ evidence upon this point, nor, indeed, can the testimony of the witness Williams be given the importance contended for. His estimate of the lumber furnished and work performed is based entirely upon the survey hereinbefore mentioned, and an inspection of the barge after the work was entirely completed. Such opinion-evidence, in my judgment, does not merit the weight that must be-given to the libelants’ witnesses, who were actually present during; the progress of the work, and kept record of the details thereof.
The measurements of the timber are allowed as charged, except that a deduction is made from the oak of 4,212 feet on account of contract work; the evidence not being clear that any deduction was made for lumber furnished for that purpose. There is evidence
30,759 feet of oak, at $40 per M.................................. $1,230 36
34,935 “ “ Norway, at $40 per M.............................. 1,397 40
32,092 “ “ pine, at $40 per M.................................. 1,283 50
8,830 “ “ docking, at $35 per. M.............................. 309 05
$4,220 31
Delay in the work occurred at different times, and the expense for the lay days must accordingly be reduced. The evidence does not indicate that there was an agreement, as claimed by respondents, that the work should be completed in three or four weeks, or within any specified time; nor was the delay of such a nature as to warrant the inference that the vessel was detained because of the carelessness or negligence of libelants. Complaints of delay were frequent, and some evidence was given tending to show that an insufficient number of workmen were employed at different times in completing the repairs. The estimate of respondents’ witnesses that there was an unreasonable delay of 50 days is not persuasive, although the work of repairing the barge might have been hurried. Giving consideration to all the evidence upon this point a deduction of 20 lay days would seem proper and just. This would reduce libelants’ charge for lay days from $4,416 to $3,312.
The amount charged for labor, including - gains and profits, is $9,882.82; the actual cost thereof, according to libelants’ testimony, being $7,552.93. I think a profit of 20 per cent, is reasonable and just, and therefore the amount charged for labor is reduced from $9,882.82 to $9,063.51.
Respondents claim that the profit and gain charged on an expenditure of $1,149.60 for certain materials, tools, etc., furnished, amounting to $556.20, is excessive and unreasonable. The proofs show that the libelant James Davidson sold the articles mentioned to the firm. There is no substantial reason for denying a reasonable profit to the seller of these materials, as well as to the libelants, who used them in making the repairs. The libelant James Davidson, on cross-examination, testifies that a profit of 15 per cent, would not be excessive, and that he stood ready to accept such an estimate of profit. Undoubtedly he had in mind a clear net gain of 15 per cent, over and above all expenditures. In estimating an allowance of gains and profits, regard must be had for the general expense of maintaining the dry dock. I think $200 a proper deduction from the estimate of gains and profits on these materials, making the allowance therefor the sum of $1,505.80. The amount of $50 is allowed for- rigging bands, instead of $60, as charged, and $12 for pitch, instead of $20, as charged. The items enumerated in subdivision 2d of respondents’ brief, consisting of wedges, files, etc., charged at $Í44.85, are disallowed, as is also the charge of $15.53 for hoisting line. The charges of $27.31 for connecting pony engine, and $60 for jig sawing, are disallowed. The item of round
The counterclaim of respondents remains to be briefly considered. The evidence falls short of establishing that there was an actual loss of earning capacity of the barge, nor does it sufficiently appear what her net earnings during the detention would probably have been. The Conqueror, 166 U. S. 133,17 Sup. Ct. 510, 41 L. Ed. 937. Hence no offset as a result of detention is allowed. The charges for the various other items not mentioned herein are allowed.
A summation of the evidence warrants the conclusion that the libelants are entitled to recover the sum of $16,936.77, with interest from April 1, 1904, the time when the briefs herein should have been filed with the court, together with the costs of the action.