Lead Opinion
This appeal involves the applicability of the doctrine of laches to bar a Title VII employment discrimination claim. 42 U.S. C. § 2000e-2. Specifically, we are asked to decide whether a claimant who awaits the outcome of the Equal Employment Opportunity Commission’s (EEOC) administrative proceedings for a period of ten years before filing suit has caused inexcusable delay sufficient to justify the application of the doctrine of laches. The district court found the delay to have been inexcusable and, since it also found that the delay resulted in prejudice, it granted defendant’s motion for summary judgment. We affirm.
I.
The facts are essentially uncontroverted. On April 12, 1972, the Cleveland Newspaper Guild (Guild), on behalf of its female members, filed a charge with the EEOC alleging sex discrimination in merit pay, promotions, assignments, and other terms and conditions of employment at The Plain Dealer Publishing Company. On May 8, 1972, defendant was sent a form notice of the charge of employment discrimination. The notice did not name the person or persons bringing the charge; however, it did state that “[sjection 1602.14 of the Commission’s Regulations requires the preservation of all relevant personnel records until this charge is resolved.” Additionally, the notice asked that defendant withhold any questions about the complaint until the investigation commenced. The form stated that it was uncertain when defendant would be contacted in connection with the investigation due to the EEOC’s “heavy backlog of pending work.”
On April 12, 1974, the EEOC sent the Guild a form notice entitled “Charging Party Follow-up.” It stated that the EEOC had not been able to process the charge and could not predict when it would begin to do so. Therefore, it asked the Guild to choose one of three courses of action: (1) keep the charge open and have it processed when the EEOC could attend to it, (2) sue the Plain Dealer in federal court, or (3) close the charge without further action. In a letter dated September 4, 1974, Jack Weir, then Executive Secretary of the Guild, indicated the Guild’s decision to have the EEOC continue to process the charge.
The EEOC’s investigation began in May of 1976. On May 19, 1976, counsel for the Plain Dealer was given a copy of Charge No. 1613 filed by the Guild on April 12, 1972. This is the first time that the Plain Dealer became aware of who had filed the charge and why. On June 22, 1976, the Plain Dealer requested that the EEOC dismiss the charge and cease its investigation, asserting that the four-year delay had substantially impaired the Plain Dealer’s ability to respond to the charge. On June 24, 1976, the EEOC notified the Plain Dealer that it would not dismiss the charge, and it requested documents and information regarding Guild employees for the previous six years. The Plain Dealer refused to submit the requested information.
On August 25, 1976, the EEOC issued a subpoena demanding production of the documents previously requested. The Plain Dealer then filed, on September 1, 1976, a petition to revoke and/or modify the subpoena. Over one year later, in September of 1977, the EEOC denied revocation and directed the Plain Dealer to appear at the EEOC for production of the documents. On October 17,1977, counsel for defendant wrote the EEOC that it would not appear in the offices of the EEOC as ordered. Nothing further occurred in this case until July 30, 1979, when Guild Secretary J. Stephens Hatch wrote to the EEOC concern
On July 3, 1980, the Plain Dealer submitted a position paper in response to the Guild’s charge. It stated that because of the lapse of time, management personnel and documents relevant to the charge were no longer available. On October 10, 1980, the EEOC issued a finding of reasonable cause and thereafter attempted to commence conciliation efforts. The attempt proved fruitless and, on May 21, 1982, the EEOC issued a right to sue notice to the Guild. The Guild then filed this suit in the district court on August 18, 1982. The defendant filed a motion for summary judgment based on the affirmative defense of laches, and the district court granted the motion.
The trial court determined that plaintiffs had failed to provide sufficient explanation for the ten-year delay in bringing suit. The trial court also found prejudice to the defendant in the form of unavailable witnesses, destruction of documentary evidence, and erosion of available witnesses’ memories. As to the EEOC’s notice to defendant to retain personnel records, the court found it too ambiguous to serve as a valid command. Accordingly, the court entered judgment for defendant.
On appeal, plaintiffs contend that the defense of laches will not lie to effect dismissal of a Title VII complaint brought by claimants who choose to await completion of the EEOC’s administrative process before filing suit. Assuming that the doctrine of laches may be invoked, however, plaintiffs contend that they acted reasonably and did not inexcusably delay the proceedings. Plaintiffs also argue that defendant is barred from asserting the laches defense based on the doctrine of unclean hands.
II.
A Title VII claimant must file a claim with the EEOC (in a nondeferral state) within 180 days after the allegedly discriminatory act. 42 U.S.C. § 2000e-5(c). Once EEOC proceedings have terminated and the agency issues its right to sue notice, the claimant has 90 days to file suit in federal court. Id. at § 2000e-5(f)(l). If, however, the EEOC proceedings are still in progress, a claimant may request a right to sue letter 180 days after filing of the charge. Id. This 180-day provision is not a statute of limitations. Occidental Life Ins. Co. v. EEOC,
A.
Equitable considerations have influenced the Supreme Court in the context of Title VII. In Albemarle Paper Co. v. Moody,
In Occidental Life Ins. Co. v. EEOC,
B.
Against the backdrop of these cases, the courts of appeals have disagreed as to whether the application of equitable principles to Title VII cases permits a dismissal based on laches when, as here, a claimant chooses to await the termination of EEOC proceedings.
In Bernard v. Gulf Oil Co.,
The Ninth Circuit has also held that lach-es may be used as a defense to a Title VII action. Boone v. Mechanical Specialties,
In Rozen v. District of Columbia,
In contrast is Jeffries v. Chicago Transit Authority,
The Third Circuit, in Waddell v. Small Tube Products, Inc.,
The state agency failed to notify the EEOC when it dismissed Waddell’s charge, as it was obliged to do. In fact, the agency did not send the EEOC any such notification until November 30, 1981, more than four and one-half years later. In the meantime, Waddell wrote two letters to the EEOC about his case. When the EEOC finally was notified of the state agency’s closing of the case, it conducted an investigation and determined that there was no reasonable basis to believe Waddell had
After reviewing the cases discussed above, the Third Circuit concluded that, although plaintiffs have some obligation to monitor the progress of their charge and do not have the absolute right to await termination of EEOC proceedings where it would appear to a reasonable person that no administrative resolution will be forthcoming, whether the circumstances warrant the delay in a particular case must be decided on an ad hoc basis.
Finally, in Whitfield v. Anheuser-Busch, Inc.,
In sum, each court to have considered the question agrees, at least in theory, that the doctrine of laches can bar a Title VII action. These cases also illustrate the fact-dependent nature of the inquiry, as well as the necessity for the reasoned exercise of discretion on the part of trial courts.
III.
The defense of laches “requires proof of (1) lack of diligence by the party against whom the defense is asserted, and (2) prejudice to the party asserting the defense.” Costello v. United States,
Those cases that appear to allow claimants an unqualified right to await indefinitely termination of the administrative process often speak to the fact that claimants cannot be held responsible for the delays occasioned by the EEOC. But whether another party contributes to the delay is only one factor in assessing the reasonableness of a plaintiff’s actions. The question is not purely one of assigning fault. As stated in Pomeroy’s treatise: “A court of equity, which is never active in relief against conscience or public convenience, has always refused its aid to stale demands, where the party has slept upon his rights, and acquiesced for a great length of time. Nothing can call forth ... [the] court into activity but conscience, good faith and reasonable diligence.” J. Pomeroy, II Equity Jurisprudence, § 419 at
IV.
The district court found that both elements of the laches defense had been satisfied; that is, that plaintiffs’ lack of diligence had prejudiced the defendant. As to lack of diligence by plaintiffs, the court indicated that because of the fact the Guild was a labor union, with specific knowledge and responsibility in equal employment opportunity matters, it could not reasonably account for its continued inaction during the extended period that the charge was pending. It was undisputed that the Guild knew of its ability to obtain a right to sue notice and institute a civil action. And while the district court did not fault the Guild for initially refusing the first offer of a right to sue letter, the court was justifiably troubled by the lack of activity over the next eight years. The court also specifically referred to the lack of Guild contacts with the EEOC during that period.
Likewise, as noted by the district court, there was little EEOC activity during this time which could explain plaintiffs’ failure to act. The EEOC did not take enforcement action on the subpoena issued to discover relevant information. Moreover, no conciliation ever occurred. In other words, there was nothing ongoing which the Guild could point to in order to justify its inaction.
The Guild now argues that it was defendant who delayed the administrative process, by refusing to cooperate with the EEOC. This argument ignores, however, the prejudice resulting from the four-year delay that occurred before defendant received a copy of the charge and, further, it erroneously presupposes that defendant’s assertion of prejudice at that point was somehow wrongful. In short, this contention does not persuade us that the court erred in finding inexcusable delay.
No one seriously disputes the district court’s finding that defendant has suffered prejudice in the form of lost witnesses and documentary evidence. Affidavits submitted in the district court detail those witnesses who are no longer available to defendant and their specific knowledge as to the underlying dispute. The Guild argues, however, that defendant was informed that a sex discrimination charge had been filed and was ordered to retain all records, and, therefore, if defendant suffered prejudice, it was of its own making.
The district court found that the EEOC’s notice to defendant to retain personnel records was too ambiguous to serve as a valid command. Under the specific circumstances of this case, we agree. It must be kept in mind that the defendant was not initially informed of any of the details of the charge. It was EEOC policy at that time not to send an actual copy of the charge. Accordingly, all defendant knew was that a charge of employment discrimination based on sex had been filed against it. It was not until four years after the filing of the charge that the defendant received an actual copy of it. In the meantime, it was, of course, impossible to determine which personnel records were “relevant” to the unknown charge. In any event, retention of records would still not alleviate the problem of witnesses who have become unavailable or whose memories have faded.
We find no error in the district court’s application of the doctrine of laches under these circumstances.
V.
We must also reject plaintiffs’ argument that defendant is barred from eq
While the defendant clearly refused to cooperate with the EEOC’s administrative process, it asserted that by the time that process began, four years after the charge had been filed, it had already suffered prejudice. Defendant consistently maintained that position. There was no indication that this position was advanced in bad faith. Moreover, we have found no authority for the proposition that one resisting an administrative process by asserting a legal defense can be found to have unclean hands. Consequently, we do not believe that the doctrine of unclean hands operates here to deny defendant relief.
VI.
We affirm the district court’s holding because we believe that the court’s power to “locate a just result” includes the possibility that a case may be dismissed on the basis of laches. We find no abuse of discretion in the court’s dismissal of this case, nor clear error in its findings of lack of diligence on the part of the plaintiffs and prejudice to the defendant. We emphasize, however, that dismissal of a plaintiff’s claim is an extreme result, and should be accomplished only when the prejudice to the defendant can be avoided in no other way. Accordingly, the judgment of the district court is AFFIRMED.
Notes
. On appeal, the Guild has asserted that part of the reason it delayed bringing suit was because it was monitoring a parallel charge against the Cleveland Press, which it believed would, when concluded, establish a precedent for the resolution of the charge filed against the Plain Dealer. This argument was not raised below and is not properly before us. Consequently, we do not consider it. We note in passing, however, that the argument is not helpful to the Guild’s position. The fact that the Guild felt it was in its interest to wait does little to offset as an equitable consideration the prejudice being suffered by the defendant.
Concurrence Opinion
concurring.
I agree with the Court’s laches argument in this en banc case if no statute of limitations is applicable.
It seems to me, however, that the Court ignores the fact that there is a statute of limitations written into the statute in question. Subsection (f)(1), 42 U.S.C. § 2000e-5(f)(l), says: “If a charge is filed with the commission” and “if within one hundred and eighty days from the filing of such charge ... the commission has not filed a civil action under this section ... or the commission has not entered into a conciliation agreement to which the person aggrieved is a party, the commission ... shall so notify the person aggrieved and within ninety days after the giving of such notice a civil action may be brought
The mandatory language of this section requires the EEOC either to bring an action itself or enter into a conciliation agreement, failing which the commission “shall so notify” the charging party within 180 days. Here the commission failed to give any notice for two years. It seems to me that Congress plainly intended by enacting the ninety day filing requirement and the sixty day stay provision to require both the EEOC and the courts not to allow disputes under this section to fester and drag on indefinitely. I would therefore interpret this section to provide a 180 day EEOC conciliation period, at the end of which the employer can require the EEOC to send the contemplated notice. The court can then allow another period of “not more than sixty days” for conciliation; the judicial proceedings must then go forward. That is what the plain language of the statute contemplates, and that is the way it should be enforced.
The Second Circuit in DeMatteis v. Eastman Kodak Co.,
Here the EEOC did not give the required notice at the end of the 180 day period, and the employer did not insist on it. In such cases, the 90 day period is not triggered until the EEOC affirmatively notifies the charging party that it “has not entered into a conciliation agreement,” thereby extending the 180 day period until EEOC notice is given. That notice was plainly given on April 12, 1974, two years after the charge was filed. The notice further advised the charging parties that they could sue in federal court since the EEOC had not been able to process the case. The 90 day period began to run at that time, and it would have run long before this suit was brought.
We should not permit the EEOC to alter the clear language of the statute by regulation. The regulations set up a procedural regime which is inconsistent with the procedure contemplated by 42 U.S.C. § 2000e-5(f)(l). The regulations provide that an aggrieved party may request notice of right to sue and the EEOC shall issue such notice “at any time after the expiration” of 180 days from the date of filing of the charge. 29 C.F.R. § 1601.28(a)(1) (1987). The regulations further purport to authorize aggrieved persons to bring a civil action within 90 days from the receipt of the notice of right to sue. 29 C.F.R. § 1601.28(e)(1) (1987). The statute, however, clearly states that if within 180 days from the filing of the charge, the commission has not filed a civil action or entered into a conciliation agreement, the commission must notify the aggrieved person and “within ninety days after the giving of such notice a civil action may be brought....” 42 U.S.C. § 2000e-5(f)(l). This language clearly contemplates that the notice from the EEOC be timely and that the 90 day statute of limitations run from that notice. In this case, the Guild received the notice contemplated by the statute in 1974, thus triggering the 90 day statute of limitations.
It seems to me that this 90 day period should be used as the period of limitations in light of the words of the statute. In view of the conflicts in the circuits and the confusion with respect to the applicability of the 90 day statute of limitations, I would apply this rule prospectively as did the Second Circuit in the DeMatteis case, not retroactively. See DeMatteis v. Eastman Kodak Co.,
. Subject to rebuttal, the laches period should presumptively be the same 90 day period as provided for in the statute. See Tandy Corp. v. Malone & Hyde, Inc.,
Dissenting Opinion
dissenting.
Because I believe section 706(f)(1) of Title VII of the Civil Rights Act of 1964, as amended, 42 U.S.C. § 2000e-5(f)(l), and the policies it reflects preclude invocation of the equitable doctrine of laches where the charging party elects to await completion of the EEOC’s processing of the charge and issuance of a right-to-sue notice prior to filing suit, and because I believe
I.
Where, as here, an action arises under a statute enacted by Congress, the doctrine of separation of powers requires that courts be “circumspect in adopting principles of equity,” including the doctrine of laches, in order not to “risk frustrating the will of the Legislature.” County of Oneida v. Oneida Indian Nation,
Section 706(f)(1) expresses “the decision of Congress to delay judicial action while the EEOC performs its administrative responsibilities.”
If a charge filed with the [EEOC] ... is dismissed ... or if within one hundred and eighty days from the filing of such charge ... the [EEOC] has not filed a civil action ..., or ... entered into a conciliation agreement ..., the [EEOC] shall so notify the person aggrieved and within ninety days ... a civil action may be brought ... by the person claiming to be aggrieved....
Regulations promulgated by the EEOC provide that the charging party may request a right-to-sue notice after 180 days from the filing of the charge, see 29 C.F.R. § 1601.28(a), but nothing in section 706(f)(1) or the regulations require that a request be made within a certain time or at all. Kamberos,
Section 706(f)(1) provides “only an alternative method for a plaintiff to obtain relief from discrimination” and the charging party “cannot be penalized for choosing to forego this alternative and electing instead
The literal language of section 706(f)(1) leads inexorably to the conclusion that after 180 days have elapsed “the [charging party] may either file a private action within 90 days after EEOC notification or continue to leave the ultimate resolution of his charge to the efforts of the EEOC.” Occidental Life Insurance,
The EEOC interprets section 706(f)(1) as authorizing the charging party to await the outcome of the EEOC’s efforts to resolve the charge, prior to filing suit unless the charging party intentionally delays the proceedings. Brief of EEOC as amicus curiae at 10. It is well-settled that courts must show “ ‘great deference to the interpretation given the statute by the officers or agency charged with its administration.’” Environmental Protection Agency v. National Crushed Stone Association,
Section 706(f)(1) not only authorizes the charging party to await completion of the EEOC proceedings prior to filing suit, but also provides that a suit is timely if filed within ninety days after the charging party receives notice of the EEOC’s decision not to take action itself. See, e.g., Ringgold v. National Maintenance Corp.,
II.
Assuming arguendo that section 706(f)(1) does not authorize the charging party to await termination of EEOC proceedings before filing suit, a proper application of the doctrine of laches would permit plaintiff to proceed with its claim. To establish the affirmative defense of laches, a defendant has the burden to show both an inexcusable delay by the plaintiff and prejudice to the defendant. Gardner v. Panama R.R.,
The court in Jeffries declined to decide whether the charging party must “necessarily demand” a right-to-sue notice, but instead held that the plaintiff’s failure to demonstrate “some interest” in prosecuting his claim supported a finding of inexcusable delay. The plaintiff in Jeffries filed his charge of discrimination in November 1974, but initiated no further contact with the EEOC until January 1984, when the EEOC issued the right-to-sue notice. The court concluded that the plaintiff “should at least have reached the agency” and that the plaintiff's failure to write or call the EEOC for at least nine years was inexcusable.
The facts of Jeffries are in sharp contrast to those of the present case. Two years after filing the charge, plaintiff inquired about the status of the charge and requested that the EEOC proceed with its investigation as soon as possible. Further, plaintiff again contacted the EEOC in July
On the other hand, the court in Waddell held that the charging party has an absolute right to await termination of EEOC proceedings unless it would appear to a reasonable person that no administrative resolution would be forthcoming. The court emphasized that “plaintiffs may reasonably delay while the EEOC is actively engaged in the administrative process” and that courts must not “undermine the EEOC’s capacity to investigate charges of discrimination ... nor undercut congressional policy of favoring reliance by plaintiffs ‘on the administrative process of the EEOC.’ ”
The court did, however, cite with approval the decision in Bernard where the court characterized EEOC proceedings of nine years as both “active” and “continuing.”
Once the EEOC’s investigation began in the present case, it was both “active” and “continuing” until issuance of the right-to-sue notice. Between 1976 and 1980 the EEOC’s efforts were directed at securing evidence which defendant refused to provide even in the face of an EEOC subpoena. The EEOC made a reasonable cause determination in 1980 and commenced conciliation efforts which continued until 1982 when the right-to-sue notice was issued.
The prejudice prong of the laches analysis requires a showing that the defendant’s chances of success have been diminished by loss of evidence or unavailability of witnesses. Gull Airborne Instruments, Inc. v. Weinberger,
The fact that certain individuals who had been responsible for personnel matters are no longer employed by defendant is insufficient to establish prejudice because defendant made no showing that these witnesses were unavailable. “The fact that there have been personnel changes or that employees have retired is irrelevant unless those employees are unavailable.” Bernard,
Defendant’s assertion of laches is precluded not only by its failure to establish prejudice and inexcusable delay, but also because the delay in the present case was caused in substantial part by defendant’s refusal to cooperate with the EEOC. “If the party which advances the defense of laches is responsible for the delay or contributes substantially to it he cannot take advantage of it.” Potash Co. v. International Minerals & Chemical Corp.,
More than three years of the delay in the present case was caused by defendant’s refusal to produce records voluntarily and to comply with an EEOC subpoena. Defendant urges that we ignore this fact because it had a legal right to refuse to comply with the EEOC subpoena. However, the right to challenge an EEOC subpoena is limited to the assertion that the evidence subpoenaed is not relevant to any matter under investigation or that the subpoena does not describe with sufficient particularity the evidence to be produced. 42 U.S.C. § 2000e-9; 29 U.S.C. § 161(1). Defendant’s challenge to the subpoena was based on its belief that the EEOC had waited too long in commencing its investigation. This is not a sufficient basis to refuse compliance with an EEOC subpoena.
III.
Accordingly, I would REVERSE the district court’s entry of summary judgment and REMAND for further proceedings.
. The district court's opinion does not contain any discussion of section 706(f)(1) and the policies it reflects.
. The Fifth Circuit granted a petition for rehearing en banc on September 27, 1979. See
. The Ninth Circuit held in Boone v. Mechanical Specialties Co.,
. In the present case, the district court made no inquiry or findings in regard to whether the EEOC’s investigation was active.
. The district court made no inquiry about whether a reasonable person in plaintiffs position would have realized that an administrative resolution would not be forthcoming. The district court inexplicably focused its analysis on whether there was any excuse for the EEOC’s delay. Whether the EEOC’s delay was justified is wholly irrelevant in determining whether plaintiffs delay was inexcusable.
Dissenting Opinion
dissenting.
I concur in Judge Milbum’s thoughtful dissenting opinion, and write separately only to stress two points of particular concern. First, even if one were to concede that the doctrine of laches could be applied in such a situation, it is inconceivable to me that any court could conclude that the behavior of this defendant would not preclude the exercise of the court’s equitable power on its behalf. When, as in the present case, the prevailing party on appeal destroys relevant records despite having received notice of a pending claim, and baldly refuses to comply with an EEOC subpoena while citing spurious grounds for its refusal, it is not only unjustifiable but unconscionable for a court to aid the party’s contempt for the administrative process through the granting of equitable relief.
Furthermore, it strikes me as ironic that plaintiff is being penalized for fully exhausting its administrative remedies — pursuant to a complex and comprehensive statutory scheme — rather than resorting to the courts for relief, while this Court, as well as the courts of most other jurisdictions, have been consistently unsympathetic to plaintiffs who seek judicial relief prior to exhaustion even as a reaction to demonstrably lengthy and time-consuming administrative procedures. Indeed, the requirement that one exhaust all administrative remedies has been intoned with such frequency, despite the hardship for plaintiffs which can result, as to have become liturgically axiomatic. Although I am not so naive as to anticipate that this will be the case, I would hope that the delay that the exhaustion requirement creates in some cases would be recognized as prejudicial to future plaintiffs as well as defendants, and
Concurrence Opinion
concurring specially in Circuit Judge MILBURN’s dissent.
In my view of this case the majority opinion simply amends the statute to provide a time limitation not adopted by Congress and not justified in equity. Here defendant Plain Dealer had received notice to “preserve all personnel records relevant to the charge or action until final disposition of the charge or action.” Thus the Plain Dealer Publishing Company clearly had notice of the pending claim but in spite thereof proceeded to destroy essential records. Since in this case we sit in equity
Concurrence Opinion
concurring.
I concur fully in Judge Guy’s opinion for the court and write separately merely to emphasize the fact that this court will treat defenses of laches in Title VII actions on a case-by-case basis. As this court and others have noted in requiring a liberal construction of Title VII, actions under this statute are often “filed by lay complainants who are unfamiliar with the niceties of pleading and are acting without assistance of counsel.” Tipler v. E.I. duPont deNemours & Co.,
We review application of the equitable doctrine of laches under an abuse of discretion standard, Jeffries v. Chicago Transit Authority,
Concurrence Opinion
concurring.
I concur fully in the court’s opinion, except insofar as the first paragraph of Part II might lend itself to the interpretation that we are saying the EEOC is automatically foreclosed from taking any further action once it has started the 90-day clock running, under 42 U.S.C. § 2000e-5(f)(l), by giving notice that the government has neither filed a civil action nor entered into a conciliation agreement. If, as Judge Merritt believes, the notice given by the EEOC in April of 1974 was such a notice
In light of Zipes v. Trans World Airlines, Inc.,
I agree with Judge Edwards that the case before us is essentially a suit in equity. Accordingly, I see nothing novel in applying the equitable defense of laches here. Cf. Occidental Life Insurance Co. v. EEOC,
In holding that the district court did nof abuse its discretion in applying the doctrin¿ of laches under the particular facts of this case, we are not deciding, I take it, whether the notice issued by the EEOC in April of 1974 started the running of a 90-day limitations period that the Plain Dealer could have raised as an affirmative defense in its answer to the complaint. The answer contains no such defense, so the issue is not before us.
. Cf. New York Gaslight Club, Inc. v. Carey,
Dissenting Opinion
dissenting.
While I wholeheartedly agree with the compelling dissenting opinion of Judge Mil-bum, I add this separate point of emphasis.
The 1972 Amendments to the Title VII of the 1964 Civil Rights Act “represents in some respects a compromise from the original proposals. However, the final product provides the Equal Employment Opportunities Commission ... the tools needed to implement an effective enforcement program to secure equal employment opportunity for all our citizens.” Senate Subcommittee on Labor of the Committee on Labor and Public Welfare, 92d Cong., 2d Sess., Legislative History of the Equal Employment Opportunity Act, Forward (Comm. Print 922).
The legislative history of these amendments makes clear that Congress wanted to be certain that bona fide claims would not be lost on mere technicalities involving filing deadlines or because of a lack of diligence or discernment on the part of the agencies, including the EEOC, designated to enforce the law. Speaking of the 1972 Amendments’ changes in the filing time requirements, Senator Harrison Williams, and Senator Jacob Javits, after noting that aggrieved persons are often lay persons, said:
[W]ide latitude should be given individuals in such cases to avoid any prejudice to their rights as a result of government inadvertence, delay or error.
118 Cong.Rec. 1846 (daily ed. Feb. 14, 1972).
The majority opinion can have the likely effect of forcing into already overcrowded courts complaints initially filed and referred to the agency for conciliation efforts. This is what Congress was seeking to avoid through the compromise. Senator Roman Hruska was particularly concerned at the possibility of employers being required to fend off lawsuits before a number of separate forums. In response, Senators Williams and Javits declared that: “[i]t is hoped that recourse to the private lawsuit will be the exception and not the rule, and that the vast majority of complaints will be handled through the offices of [the] EEOC or the Attorney General, as appropriate. However, as the individual's rights are paramount under provision of Title VII it is necessary that all avenues be left open for quick and effective relief.” 118 Cong. Rec. 3462 (daily ed. Mar. 6, 1972).
With these amendments the jurisdiction of Title VII was expanded to embrace complaints of discrimination in federal, state and local government employment as well as gender discrimination. EEOC Act, 42 U.S.C. § 2000e et seq. (Supp. II 1972); 42 U.S.C. § 2000e-5 (Supp. II 1972). This expanded jurisdiction opened a floodgate of complaints of discrimination in that the public awareness of the remedy was heightened. This avalanche of cases was piled atop the caseload in 1972 that numbered 16,348, whereas the Commission was able to complete investigation of only 5,090 of them. See 188 Cong.Rec. 1650 (daily ed. Feb. 14, 1972). In my view, the majority opinion penalizes victims of discrimination for the pervasiveness of discrimination.
I conclude by noting this deep irony: the aggrieved filed their complaints with the EEOC in a timely manner. By engrafting a laches defense onto the statute this court majority is doing the opposite of what Congress intended. Therefore, I must and do dissent.
