The Cessna Aircraft Company (“Cessna”) appeals from March 12, 1993 decision of
*1444
Armed Services Board of Contract Appeals (“Board”) on cross-motions for partial summary judgment in
Cessna Aircraft Co.,
ASBCA No. 43196,
BACKGROUND
I.
This appeal arises out of Contract No. N00019-83-C-0090, awarded to Cessna by Navy, under which Cessna was required to provide training, and related technical and maintenance support, for undergraduate naval flight officers at U.S. Naval Air Station in Pensacola, Florida.
See Cessna I,
The contract called for Cessna to provide flight training services during five program years, commencing August 1, 1984, and ending September 30, 1988.
Cessna I,
Pursuant to “Option to Extend Services” clause, option for three years will be exercised, if at all, in writing by a unilateral modification to this contract issued by Contracting Officer, Naval Air Systems Command, not later than 1 October 1988.
Id.
Each option year ran from October 1 to September 30; that is, first option year ran from October 1, 1988 to September 30, 1989, second option year ran from October 1, 1989 to September 30, 1990, and third option year ran from October 1, 1990 to September 30, 1991.
Cessna
I,
The timing of this notification was addressed by section H-8 of contract Schedule, entitled “Multiyear Procurement,” which stated that:
If three year option is exercised, date within which contracting officer ... will notify Contractor of availability of funds sufficient for performance of requirements for the
Second Option Year (Fiscal Year 1990) is 1 October 1989. Third Option Year (Fiscal Year 1991) is 1 October 1990.
Id. at 128,877. The contract further incorporated by reference, inter alia, two Defense Acquisition Regulation (“DAR”) provisions concerning multiyear aspects of contract. The first, named “Cancellation of Items” clause, addressed cancellation of contract based on a lack of availability of funds. This clause stated in pertinent part:
(b)As used herein, term “cancellation” means that Government is canceling, pursuant to this clause, its requirements for items as set forth in Schedule for all fiscal years (1 October — 30 September) subsequent to that in which notice of cancellation is provided. Such cancellation shall occur only if Contracting Officer (i) notifies Contractor that funds will not be available for contract performance for next succeeding fiscal year and any subsequent fiscal year; or (ii) fails to notify Contractor prior to beginning of next succeeding fiscal year that funds have been made available for performance in succeeding fiscal year.
DAR § 7-1903.33(d). 2 A related clause addressed contract execution once funds became available. It stated in pertinent part that:
Upon availability to Contracting Officer of funds for performance of requirements in *1445 next succeeding fiscal year, Contracting Officer shall notify Contractor in writing of amount of funds available for contract performance in next succeeding fiscal year and contract shall be modified accordingly.
DAR § 7-1903.33(c). 3
The contract was awarded on May 10, 1983. Sometime in either late March or early April of 1988, during final program year of original five-year term of contract, Cessna contacted contracting officer (“CO”) to inquire about whether Navy intended to exercise three year option.
Cessna II,
1. You are hereby notified of our intent to exercise option for three option years under Contract N00019-83-C-0090. Pursuant to Special Provision H-6, “Exercise of Option,” we will exercise option for three option years, if at all, not later than 1 October 1988.
Id.
On August 3, 1988, during negotiation meetings concerning unrelated claim for equitable adjustment made by Cessna, Cessna again raised issue of when Navy intended to exercise option.
Id.
At that time, Cessna expressed its view that option had to be exercised
before
October 1, 1988.
Id.
On September 26, 1988, in a telephone conversation between CO and a Cessna official, CO asked whether, because October 1, 1988 was a Saturday, it would be acceptable for option to be exercised on October 3, 1988.
Cessna II,
During period September 27-30, 1988, in midst of further negotiations regarding Cessna’s equitable adjustment claim, Cessna reiterated its view that Navy had to exercise option by September 30, 1988, while the Navy contended that it had until October 1.
Id.
As of September 30, 1988, the Department of Defense Appropriation Act, 1989, Pub.L. No. 100^163, 102 Stat. 2270 (1988), from which the contract at issue would be funded, had been passed by Congress but had not yet been signed by the President.
Cessna II,
On October 1, 1988, after receiving word from a NAVAIR division director that the President had signed the appropriation act, the CO executed the necessary contract modification, deleted the proviso from the Financial Accounting Data Sheet, and faxed the modification and data sheet to Cessna.
Id.
at 139,688. Cessna personnel found the faxed version of the modification and data sheet on Monday, October 3, 1988.
Cessna II,
By letter dated October 7, 1988, Cessna took the position that the purported modification was ineffective.
Id.
The letter further stated that Cessna would continue to provide services and would submit a proposal for continuation of the work.
Id.
at 139,689-90. On December 5, 1988, Cessna submitted a proposal to the Navy for providing services for the three option years.
Id.
at 139,690. In its letter, Cessna stated that it was proceeding under the assumption that its services would soon be embodied in a definitive contract. By letter dated December 7, 1988, the CO responded that the option was exercised properly on October 1, 1988, and instructed Cessna to continue performance in accordance with the contract as modified by the option.
Cessna II,
II.
In April of 1991, Cessna submitted a certified claim to the CO, as revised in June of 1991, seeking approximately $25.7 million as additional compensation for work performed during the three year option period. The CO neither issued a final decision nor informed Cessna when such decision would be issued within the sixty day time limit of Section 6(c) of the Contract Disputes Act (“CDA”), 41 U.S.C. § 605(c). 4 Cessna appealed this deemed denial to the Board. 5
Before the Board, Cessna argued,
inter alia,
that: (i) the CO violated the Antideficiency Act and attendant regulations by obligating funds for the first and third years of the three-year option period prior to apportionment and allocation of the funds (Counts I and XIII); (ii) the CO’s actions in deleting the proviso on the Financial Accounting Data Sheet rendered the option exercise ineffective (Count III); (iii) the Navy failed to exercise the option, in a timely manner, such that the contract was canceled (Count V); (iv) by exercising the option on October 1, 1988, the Navy required Cessna to provide voluntary services in violation of the Antidefieiency Act (Count VI); and (v) the second and third option years were canceled because the CO did not issue a notice of funds availability prior to the beginning of the succeeding fiscal year (Counts VIII and XI).
6
Cessna I,
In due course, the parties filed cross-motions for summary judgment with respect to Counts I, III, VIII, XI, and XIII. The Board granted the Navy’s motion for summary judgment as to Counts I, III, and XIII, and denied summary judgment to both sides on Counts VIII and XI.
Cessna I,
DISCUSSION
I.
Pursuant to the CDA, 41 U.S.C. §§ 601-613 (1994), we review decisions of the Board under the following standard:
the decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.
41 U.S.C. § 609(b).
The Board’s conclusions of law are reviewed
de novo. See Ingalls Shipbuilding, Inc. v. Dalton,
The Board’s decision on a finding of fact may not be set aside unless the appellant can meet its burden of establishing that the finding is arbitrary, capricious, so erroneous as to necessarily imply bad faith, or not supported by substantial evidence.
Erickson Air Crane Co. v. United States,
II.
Before reaching the merits of the appeal, we must address a preliminary issue raised by the Navy. Before the Board, the Navy argued that Cessna lacked standing to contest matters relating to the Navy’s compliance with funding statutes. The Board rejected this challenge to its jurisdiction. The Board noted that under the CDA, it had jurisdiction “to decide any appeal from a decision of a contracting officer ... relative to a contract made by its agency.”
Cessna I,
As it did before the Board, the Navy argues that the Antideficiency Act does not provide Cessna with a private right of action. Thus, it asserts that Cessna’s appeal from the Board’s decision regarding Counts I, III, VI, and XIII should be dismissed because those counts involve claims relating to the government’s funding of its contractual obligations, and no private right of action exists under the Antideficiency Act with respect to such matters. Quoting from
Hagan v. United States,
As the Board noted, pursuant to 41 U.S.C. § 607(d), it has jurisdiction “to decide any appeal from a decision of a contracting officer ... relative to a contract made by its agency.”
Cessna I,
Like the Board, we view Cessna’s claims as “grounded in the CDA.” Cessna’s contract with the Navy was governed by the CDA, and it was under the CDA that Cessna submitted its claim to the contracting officer for additional compensation for work performed during the three year option period. The fact that Cessna argues that the Navy violated the Antideficiency Act and attendant regulations and the fact that Cessna seeks compensation from the Navy based upon a theory of implied-in-fact contract for services rendered during the option years do not mean that Cessna is seeking relief under the Antideficiency Act.
In
Gould, Inc. v. United States,
Upon remand, the government filed a motion to dismiss for lack of jurisdiction. The Court of Federal Claims granted the motion. The court read Gould’s complaint as based solely on a contract with the United States but at the same time as alleging that there was no “stable design” and that the contract was illegal. Under these circumstances, the court reasoned, the only possible basis for contract jurisdiction was a contract implied in law, but such a contract was not within the court’s jurisdiction.
Gould, Inc. v. United States,
On appeal, we held that the trial court had erred in dismissing Gould’s complaint for lack of jurisdiction.
Gould, Inc. v. United States,
Similarly, in this case, Cessna argues that the Navy’s actions in exercising the option in 1988 violated the Antideficiency Act, thereby rendering the option exercise inoperative and canceling the contract. However, Cessna contends, because it supplied services that the Navy accepted and from which the Navy benefited, after all legal requirements had been met (because the appropriations process had been completed), it is entitled to recover under implied-in-fact contracts for each of fiscal years 1989, 1990, and 1991. Under these circumstances, Cessna has put forth a cognizable claim for relief.
See American Telephone and Telegraph Co. v. United States,
Having concluded that Cessna’s claims on appeal with respect to Counts I, III, VI, and XIII are properly before us, we turn to the merits.
Ill
A.
By way of background, the Antideficiency Act finds its origins in a statute enacted in 1870, known as the Act of July 12, 1870, ch. 251, § 7, 16 Stat. 230, 251. The statute addressed the problem that Executive Branch officials were obligating funds before they were appropriated by Congress, and then making deficiency requests for appro
*1449
priations that Congress had little choice in deciding because government agencies had basically committed the United States to make good on its promises.
See, e,g.,
The present version of the Act, found at 31 U.S.C. § 1341 (1994), 9 provides in pertinent part as follows:
§ 1341. Limitations on expending and obligating amounts
(a)(1) An officer or employee of the United States Government or of the District of Columbia government may not -
(A) make or authorize expenditure or obligation exceeding amount available in appropriation or fund for the expenditure or obligation;
(B) involve either government in a contract or obligation for the payment of money before appropriation is made unless authorized by law.
Generally, the Act prohibits government officials and employees from making expenditures or incurring obligations in excess of available appropriations or in advance of appropriations.
See Blackhawk Heating & Plumbing Co. v. United States,
By its terms, the Antideficiency Act restricts the ability of the government to enter into multi-year contracts because funds generally cannot be obligated beyond the current fiscal year. This led to problems in the area of military procurement, as described in the following passage from a Senate Report:
Some services and supplies now being procured with appropriations available for only 1 year require substantial investment by the contractor for equipment having a useful life longer than 1 year, or extensive investment in the hiring and training of personnel. These contracts are for such activities as base maintenance, aircraft and equipment overhaul, vehicle repair, and pilot training. If the contractor can obtain only a 1-year contract, his quoted price must cover all these expenses or he runs the risk of never recovering his unamortized investment if he loses the contract for the ensuing year or years. In such circumstances, however, a successful contractor is in a position to underbid competitors in later years since the competitors must include in their bid prices the same initial investment costs that the contractor confronted. As a result, competition is reduced and the Government can be overcharged in later years.
S. Rep. No. 90-1313, at 1-2 (1968), reprinted in 1968 U.S.C.C.A.N. 2480, 2480-81.
To address these concerns, 10 U.S.C. § 2306(g) was enacted; it permits the government to enter into specified types of military procurement contracts having performance periods of up to five years, with option to extend performance by a period not exceeding three additional years. 10 If funds are not in fact appropriated in a subsequent *1450 fiscal year, section 2306(g)(3) provides that the “contract shall be canceled or terminated.”
B.
Cessna’s first contention is that the Antideficiency Act, in combination with its implementing regulations and certain other funding statutes, prohibits funds from being obligated before they have been both appropriated by the Congress and apportioned by the Executive Branch. 11 Cessna argues that 31 U.S.C. § 1512, which requires that appropriated funds be apportioned, 12 and 31 U.S.C. § 1517, which prohibits government officials or employees from authorizing obligations that exceed apportionment, 13 prevent the obligation of funds, even if appropriated, before they have been apportioned. As a general matter, Cessna maintains that permitting funds to be obligated in advance of apportionments is inconsistent with prohibiting funds from being obligated in excess of apportionments. If no apportionment has been made, Cessna contends, any obligation necessarily exceeds the approved apportionment (of zero).
As further support for its position, Cessna points to the Department of Defense (“DOD”) Accounting Manual, page 22-6, paragraph 4a, which states that:
An apportionment or reapportionment is a distribution made by OMB [Office of Management and Budget] of amounts available for obligation in appropriation or fund account. Except in certain instances, ... apportionments and reapportionments by OMB are required before funds may be obligated.
(emphasis added). In addition, Cessna cites to the Navy Comptroller Manual (“NCM”), paragraphs 073002(2) and 073100, 14 as estab *1451 lishing a particular funding process wherein the first step is to apportion funds, after which they are allocated to the Secretary of Defense, and then allotted, suballotted, and committed to the Navy. Cessna asserts that because the CO attempted, on October 1, 1988, to exercise the option and to obligate funds before they had been apportioned, she acted without authority and the option exercise therefore was ineffective.
We reject Cessna’s arguments. As noted above, 31 U.S.C. § 1341(a) prohibits the government from making expenditures or incurring obligations before funds have been appropriated. However, as for the apportionment process, addressed by 31 U.S.C. §§ 1511-1519, no such timing limitation exists. For example, section 1512 merely requires appropriations to be apportioned to prevent obligations at rates that could result in the need for a deficiency or supplemental appropriation. Section 1513 provides a time table for carrying out the apportionment process, but is silent on the issue of whether the apportionment process must be carried out before obligations can be incurred. For its part, section 1517 prohibits government officials or employees from authorizing obligations that exceed apportionments, but says nothing about incurring obligations pri- or to carrying out the apportionment process. In sum, the relevant statutory provisions do not prohibit government agencies from incurring contractual obligations before completing the apportionment process. The remaining sections pertaining to apportionments are similarly silent.
This same reasoning applies to paragraphs 073002(2) and 073100 of the NCM; these paragraphs say nothing about the timing of incurring obligations versus carrying out the apportionment process. Therefore, they are of no assistance to Cessna. In addition, we note that paragraph 022064 of the NCM, entitled “Availability of Funds Prior to Apportionment,” contemplates the possibility of incurring obligations before apportionment. It states:
After the beginning of the fiscal year and prior to the specific allocation of funds pursuant to apportionment to the head of the responsible office ... the head of the responsible office is authorized by the Comptroller of the Navy to suballocate funds and to issue allotments under any appropriation act of such fiscal year in such amounts as will not exceed the amount contained in the appropriation warrant or the request for apportionment and allocation submitted to the Comptroller of the Navy.... Upon issuance of the approved budget activity allocations pursuant to apportionment, the limitations of such allocations will apply to all suballocation and allotment action taken prior to the receipt of such budget activity allocations.
The provision permits allotments and suballotments to be issued before apportionment, with restrictions as to their amounts. It would logically follow that obligations may also be incurred, with the same amount restrictions.
Finally, we turn to the DOD Accounting Manual, paragraph 4a, page 22-6 (“paragraph 4a”). Initially, we assume, without deciding here, that this provision could be properly considered a regulation. We must still determine whether the provision is a binding regulation, whose breach a contractor may assert against the government. The primary intent of a statute or regulation must be to protect or benefit a class of persons in order for that class to be able to bring suit against the government for violating the statute or regulation.
See generally Rough Diamond Co. v. United States,
In this case, paragraph 4a is primarily intended to benefit the government, not contractors such as Cessna. The provision is best described as internal operating provision for the management of funds within the agency. In
Blackhawk Heating & Plumbing Co. v. United States,
We also find instructive the Supreme Court’s reasoning in
American Farm Lines v. Black Ball Freight Service,
Thus, we hold that the CO’s exercise of the option did not violate the Antideficiency Act even though funds were obligated before they were apportioned. 15
C.
Cessna next contends that section H-6 — the option clause that required the Navy to exercise the option “not later than 1 October 1988” — must be interpreted to have required the Navy to exercise the option by September 30,1988, which the Navy failed to *1453 do. First, Cessna argues that because funding for the original contract term expired at midnight on September 30,1988, the contract ceased to exist at that point and “[o]nce the contract ceased to exist, the option ceased to exist.” Therefore, the deadline for proper exercise of the option had to be September 30, 1988. Second, Cessna contends that permitting the Navy to exercise the option on October 1, 1988, would yield illegal result. Cessna states that the Navy forced it to provide services between midnight on September 30, 1988, when funding ceased under the original contract, and the evening of October 1, 1988, when the option was purportedly exercised. Requiring Cessna to perform services in the absence of a contractual obligation would violate the prohibition against voluntary services set forth in 31 U.S.C. § 1342. 16 In this case, Cessna contends, such services included providing the support needed in order to fly aircraft and operate flight simulators, retaining personnel at the site, and performing maintenance services to maintain aircraft, radar, simulators, spare parts, etc. Cessna states that in order to sustain the validity of the contract, the option clause should be interpreted to have required the Navy to exercise the option by September 30,1988.
We disagree. First, the option clause states that the Navy had to exercise the option “not later than 1 October 1988.” We give effect to a plain reading of the clause, which is that the Navy had up until and including October 1, 1988, to exercise the option.
See McAbee Constr., Inc. v. United States,
Neither was Cessna compelled to perform voluntary services between midnight on September 30 and the evening of October 1, 1988. The Board made a finding of fact that “there is no evidence that the Navy proposed, directed or encouraged Cessna to incur rental and subcontractor costs.”
Cessna II,
D.
Cessna’s final argument is that the Navy’s exercise of the second and third op *1454 tion years, on October 1,1989, and October 1, 1990, respectively, were ineffective. Cessna contends that the Cancellation of Items clause of the contract conflicts with section H-8 of the contract Schedule because the former clause stated that the contract was canceled if the CO did not notify the contractor prior to the beginning of the next succeeding fiscal year that funds were available for performance in the succeeding year, while the latter clause permitted the CO to notify Cessna of the availability of funds on the first day of the succeeding fiscal year. In basic terms, Cessna asserts, the Cancellation of Items clause required the Navy to provide it notification by September 30,1988, while section H-8 gave the Navy until October 1.
Furthermore, Cessna argues that the Cancellation of Items clause was a mandatory clause required to be included in all multiyear contracts pursuant to DAR § 1-322.6(c), 18 and that section H-8 constitutes a deviation from the Cancellation of Items clause under DAR § 1 — 109.1(i). 19 Under those circumstances, says Cessna, DAR § 1-109.2 required that the Navy obtain authority before implementing the deviation, which was not done. 20 Cessna asserts that the failure to obtain a deviation rendered section H-8 unenforceable and that therefore the Navy’s exercise of the second and third option years was ineffective.
We reject Cessna’s arguments. Initially, as a contractual matter, section H-8 took precedence over the Cancellation of Items clause. In that regard, the Order of Precedence clause of the contract stated as follows:
In the event of inconsistency in this contract, unless otherwise provided herein, the inconsistency shall be resolved by giving precedence in the following order: (a) the Schedule (excluding the Specifications); (b) General Provisions; (c) the other provisions of the contract whether incorporated by reference or otherwise; and (d) the Specifications and (e) the Contractor’s proposal No. CMP-1351.
In this case, section H-8 was found in the contract’s schedule, while the Cancellation of Items clause was a general provision.
See Cessna II,
Cessna’s argument on this point suffers from the same defect as its first contention on appeal — that appropriated funds must be apportioned before they are obligated. We conclude that the primary purpose behind the Cancellation of Items clause is to protect the government’s interest by encouraging government officials to monitor the availability of funds for each fiscal year and to provide notice to contractors accordingly. Consequently, the clause may not form the basis for a contractor’s right of action. In order for contract performance to continue each year, the Cancellation of Items clause required that the CO notify the contractor that funds would be available for the succeeding fiscal year, act which inherently required the CO to first ensure that sufficient funds are in fact available. See DAR § 7-1903.33(d).
In
ITT Federal Lab., A Division of IT&T Corp.,
ASBCA No. 12987,
The Navy apparently deviated from the Cancellation of Items clause in drafting section H-8 without first obtaining the proper authority to do so. However, because the Cancellation of Items clause is primarily for the benefit of the government, Cessna may not rely on the deviation in arguing that the Navy’s exercise of the options for fiscal years 1990 and 1991 was ineffective. Thus, Cessna is bound by section H-8, and there is no dispute that the Navy fully complied with the section.
CONCLUSION
For the foregoing reasons, the decision of the Board is affirmed.
COSTS
Each party shall bear its own costs.
AFFIRMED.
Notes
. We addressed other claims that Cessna made arising out of the same contract in Dalton v. Cessna Aircraft Co., 98 F.3d 1298 (Fed.Cir.1996).
. The DAR has since been replaced by the Federal Acquisition Regulation ("FAR”). The analogous FAR provision is 48 C.F.R. § 52.217-2 (1996).
. No FAR provision analogous lo section 7-1903.33(c) currently exists.
. Section 605(c)(2) provides that "[a] contracting officer shall, within sixty days of receipt of a submitted certified claim over $100,000 — (A) issue a decision; or (B) notify the contractor of the time within which a decision will be issued.” 41 U.S.C. § 605(c)(2) (1994).
. Section 605(c)(5) of the CDA provides in pertinent part that "[a]ny failure by the contracting officer to issue a decision on a contract claim within the period required will be deemed to be a decision by the contracting officer denying the claim and will authorize the commencement of the appeal or suit on the claim as otherwise provided in this chapter.” 41 U.S.C. § 605(c)(5) (1994).
.While Cessna made other claims before the Board, those claims are not relevant to the present appeal and are not discussed in this opinion.
. The Claims Court was renamed the Court of Federal Claims pursuant to § 902 of the Federal *1448 Courts Administration Act of 1992, Pub.L. No. 102-572, 106 Stat. 4506, 4516 (1992), effective October 29, 1992.
. The Navy's reliance on
Hagan
is misplaced. In that case, the plaintiff, Richard Hagan, sought monetary recovery for services provided while serving on a grievance panel.
Hagan,
. While the central provision of the Act is found at 31 U.S.C. § 1341, other provisions have been passed to supplement this provision, including 31 U.S.C. §§ 1342, 1501-1519 (1994).
. Section 2306(g) provides in relevant part:
(g)(1) The head of an agency may enter into contracts for periods of not more than five years for the following types of services (and items of supply related to such services) for which funds would otherwise be available for obligation only within the fiscal year for which appropriated -
(C) specialized training necessitating high quality instructor skills (for example, pilot and other aircrew members; foreign language training);
whenever he finds that -
(i) there will be a continuing requirement for the services consonant with current plans for the proposed contract period;
(ii) the furnishing of such services will require a substantial initial investment in plant or equipment, or the incurrence of substantial contingent liabilities for the assembly, training, or transportation of a specialized work force; and
(iii) the use of such a contract will promote the best interests of the United States by encouraging effective competition and promoting economies in operation.
(2) In entering into such contracts, the head of the agency shall be guided by the following principles:
*1450 (B) Consideration shall be given to the desirability of obtaining an option to renew the contract for a reasonable period not to exceed three years, at prices not to include charges for plant, equipment and other nonrecurring costs, already amortized.
. Cessna further contends that the funds must be allocated, allotted, and suballotted to the subagency level, and that the agency must commit the funds to a contract, before funds can be obligated to a contract.
. Section 1512(a) provides:
(a)Except as provided in this subchapter, an appropriation available for obligation for a definite period shall be apportioned to prevent obligation or expenditure at a rate that would indicate a necessity for a deficiency or supplemental appropriation for the period. An appropriation for an indefinite period and authority to make obligations by contract before appropriations shall be apportioned to achieve the most effective and economical use. An apportionment may be reapportioned under this section.
. Section 1517(a) provides that "[a]n officer or employee of the United States Government ... may not make or authorize an expenditure or obligation exceeding — (1) an apportionment.”
. Paragraph 073002(2) states that:
On the basis of the enacted Department of the Navy appropriations, the Treasury Department prepares appropriation warrants which, after being countersigned by the General Accounting Office, are forwarded to the Department of the Navy as certification thaL the specific amounts are available for obligation and expenditure. Fund availability is established through compliance with procedures for submission, review, and Office of Secretary of Defense (OSD)/Office of Management and Budget (OMB) approval of apportionments and/or financial plans. In conjunction with the apportionment procedure, the Office of the Assistant Secretary of Defense (Comptroller) establishes the authorized level of obligation and expenditure for each appropriation, as well as any controls or limitations required below the appropriation level, as a means of requiring compliance with the terms of approved programs and budgets. In passing obligational authority (as an allocation or as a limitation within operating budget authority) to other echelons of command, the Comptroller creates administrative subdivisions of appropriated funds with clearly defined responsibility for 31 U.S.Code 1517 violations, i.e., for the creation of any obligation or making of any expenditure in excess of an apportionment or reapportionment, or of an amount specified in an administrative subdivision thereof. The process of distributing financial authority is continued through the chain of command in the form of suballocations, allotments, operating budgets, or operating targets. Allotments, as well as the specified obligational authority within operating budgets, constitute administrative subdivisions of appropriated funds, subject to the sanctions of the Anti-Deficiency Act (31 U.S.Code 1518 and 1519) for the holders of allotments or operating budgets. Operating targets (e.g., those established for individual ships by type commanders) are administrative limitations of funds for which the legal responsibility is retained by the grantor.
Paragraph 073100 states, in pertinent part, that "[l]he action required to obtain release of appropriated funds by means of the apportion *1451 ment process is the initial step in the budget execution phase.”
. As noted, Cessna also contends that the option exercise was deemed ineffective because the CO acted without authority in deleting the proviso on the Financial Accounting Data Sheet and then exercising the option. Cessna's contention is without merit. The proviso provided that execution of the data sheet was conditioned upon the passage of the relevant appropriation act. This condition was automatically satisfied when the President signed the appropriation act. Therefore, in substance, the condition had been satisfied, and it made no difference whether or not the CO deleted the proviso before executing the data sheet.
. Section 1342 provides in pertinent part that "[a]n officer or employee of the United States Government ... may not accept voluntary services for [the] government or employ personal services exceeding that authorized by law except for emergencies involving the safety of human life or the protection of property.” 31 U.S.C. § 1342 (1994).
. Cessna further argues that even if the Navy had until October 1, 1988, to exercise the option, Cessna did not receive notice of the option exercise until October 3, 1988, rendering the option exercise untimely. In that regard, Cessna challenges the Board’s finding of fact that Cessna and the CO reached an agreement that sending the option modification by facsimile would be acceptable, and Cessna also challenges the Board’s reliance on the Navy’s statement to Cessna personnel on September 30 to wait by their facsimile machines on October 1 to receive the option exercise.
See Cessna II,
We disagree. A Cessna official acknowledged that the parties had an established practice of faxing modifications.
Cessna II,
. Section 1-322.6(c) states that DAR § 7-1903.33(d) — the Cancellation of Items clause— must be included in multi-year service contracts. The analogous FAR provision is 48 C.F.R. § 17.109(a) (1996).
. Section 1 — 109.1 (i) defines deviation to include the situation where "a contract clause is set forth in ASPR [Armed Services Procurement Regulation] for use verbatim, [and] a contract clause covering the same subject matter which varies from ihe ASPR coverage [is used]." The analogous FAR provision is 48 C.F.R. § 1.401 (1996).
.Section 1-109.2 states that deviations from the regulations affecting only one contract or procurement may be authorized provided that (i) the circumstances justify a deviation, and (ii) written notice of the deviation is furnished to particular agency officials. The analogous FAR provision is 48 C.F.R. § 1.403 (1996).
. The Board in
ITT
also stated that another primary purpose was "to relieve [the contractor] of any obligation to incur production costs for successive years until funds were assured from which to pay [it].”
ITT, 69-2
