*1 negligent buyer If a Kirby Systems In v. Mineral is not Building foreclosed Wyo., 704 P.2d Explorations Company, warranty recovery from breach of even (1985), jury found though we noted that his negligence, compared, may neg- Building Corporation Drake to be 35% of have exceeded that the seller then a interesting ligent. It is to note Cen- that party position Corporation in the of Centric only negligent. Corporation tric 20% by not be foreclosed would the contribution computations are my While mathematical recovering consequential from its statute correction, subject jury ver- always to damages attributable to its own conduct in $8,392,216.90 per- of reduced dict proximate the context of cause. A fact centage attributable to the fault of might comparative negli- finder use $419,610.85 plaintiff of leaves a balance gence resolving proxi- determination $7,972,606.05. Thirty-five percent that question, per- cause I not mate but am $2,790,412.12. is That was the suaded that it be bound to do would so. disposed compromising which Drake of in reiterate, not To this issue was before negligence sum claim it for the case, the court for decision but it $250,000. I do not understand how we investigation justi- seems me a careful say Building Corpo- can really that Drake adopting fied forth in before views set pay again. They ration not should Rooney’s special Justice concurrence. paid yet. haven’t first time special concurring opinion, In his Justice
Rooney’s consequential thesis is that dam-
ages arising out under of a contract claim Code con- Uniform Commercial are provisions trolled the contribution in our TEXAS WEST AND OIL GAS CORPO pertaining negligence statutes actions. Johnson, RATION and Bob true, I necessarily am satisfied not (Plaintiffs), Appellants court, urge and I would the trial counsel, give of briefs assistance v.
matter careful consideration if it must be
FITZGERALD, Appellee
D.N.
addressed.
(Intervenor),
Rig
v.
Equipment
Sheldon
Unit
&
Wyo
and Rentals of
Sales
Co.,
(10th Cir.1986)
presented in this case. *3 Gosman,
Jeffrey Casper, C. for Texas Corp. West Oil and Gas and Bob Johnson. Schwartz, Bon, Harold E. Meier of McCrary Walker, Casper, & for D.N. Fitz- gerald. ” October, Overeem, ing the first weeks of Casper, for Oil two 1981’ Maher
Susan crucial and that Oil Patch had failed to Wyoming, Inc. and Rentals Patch Sales addition, fulfill contract. Texas C.J., BROWN, THOMAS, Before figure West stated that million $5.1 MACY, CARDINE, JJ. URBIGKIT only approximation; that Oil Patch expenditures nearly had not shown MACY, Justice. amount; price and that the contract could origins their in the These two cases have less than million. $5.1 first contract. We will consider same complaint against Texas filed a West dispute plain- relating to the between facts asserting Patch in October Corporation tiffs Texas West Oil and Gas failing Patch had breached the contract West) (Texas defend- and Bob Johnson and complete rig. deliver com- Wyo- Patch Sales and Rentals ant Oil sought possession plaint as well (Oil Patch). ming, Inc. damages allegedly caused breach. *4 explor- is in the business of Texas West Patch answered and asserted that it Oil for, developing, producing impossible complete and oil and ing rig was the with the 1, 1981, agreed originally Texas West set out in the con- gas. On June drawworks drilling rig from Oil Patch. tract and that Texas West had refused to purchase a $500,000 pay- specify for a substitute drawworks which it provided The contract accept repudiated had the con- execution and four would and day ment on the $750,000. tract. Oil Patch counterclaimed for the payments The con- monthly purchase price i.e., of the balance price paid $5.1 the to be tract also stated that — any sought million—less setoffs and inci- approximately drilling rig $5.1 for the was damages dental it claimed to have suffered defi- figures million “exact to be made with repudiation. from Texas West’s agreement par- the nite and certain ties, agreed upon, by or if unable to be requested After Oil Patch that the issue arbitration, is to be based actual purchase price to arbi- be submitted of Seller as well as time involved costs tration, parties stipula- entered into a the Finally, provid- the contract construction.” they agreed to submit all tion anticipated rig the ed that it was that dispute in the to an legal and factual issues completed in 1981. would be October panel. hearing April a After arbitration 1984, that panel concluded the arbitration paid mil- Although Texas West the $3.5 price million a contract was with $5.1 the contract, Patch required by lion the Oil any in case of overrun of costs provision rig parties had could not deliver the as the rig Because the beyond that amount. problems anticipated because of completed, panel awarded Oil Patch not rig’s to Oil delivery of the drawworks million minus the price the contract of $5.1 parties Patch. After the had discussed completing rig, panel which the cost of drawworks, Patch problems with the $1,133,000, pay- found to be and the down February sent Texas West a letter on panel The also found ment of million.1 $3.5 requested that which Oil Patch pay Texas West should interest on the that drawworks, Texas West select substitute price of the contract from March balance pay the additional cost for these substitute drawworks, and advance balance time, of- contract. At the same Oil Patch in district court to Texas West moved award, rig delivering modify the alternative of fered or the arbitration vacate exchange for the Patch asked for an order confirm- without drawworks while Oil price ing less the cost The district court deter- balance of the contract the award. responded that the award should not be set Texas West mined drawworks. $100,000 (except for the delivery ‘dur- aside or modified by stating that the date of “ $567,000. $467,000. party would be for Neither in an award the award 1. This results $467,000. panel disputes meant panel arbitration miscalculated and stated error) guaranty. accordingly entered arithmetic These actions induced Oil Patch confirming order and dismiss- award to breach contract requiring more ing modify. Texas price motion vacate than the contract before it would de- appealed has from this order. West rig. liver the These actions form also against basis for Texas West’s claim Fitz- presented dispute also We are gerald. which, although connected with the con- West, tract between Oil Patch and Texas against Fitzgerald Texas West’s claim Fitzgerald parties now involves as D.N. was tried a jury before which found that Fitzgerald and Texas West. Fitzgerald had interfered with the contract original complaint in the named filed between Oil Patch and Texas West. The Patch, Texas West but he inter- jury also found that as a result Texas West hold vened because he claimed to damages Fitzgerald suffered of million. $4 Patch, inventory interest in the of Oil judgment notwithstanding moved sought which included the Texas West (JNOV) verdict alternatively a new possess. intervened, Fitzgerald After trial or remittitur. The trial court denied complaint joining Texas its West amended granted the motion for JNOV but the mo- Fitzgerald and others as In its defendants. tion new trial unless Texas West complaint, alleged amended Texas West $3,431,675. consented to a remittitur of intentionally interfered appealed order, Texas West has from this with the contract between Oil has cross-appeal taken a itself, which caused Texas West to suffer portion from denying the order damages. motion for JNOV. *5 Fitzgerald original incorpo- had been an president rator and vice of Oil Patch. As ARBITRATION AWARD guarantee agreed corpora- such he to The order of the affirming district court
tion’s loans from First Bank Interstate the arbitration award is affirmed. Casper, (Bank). Although N.A. he re- merely The motion Texas West stated signed as a director of Oil Patch in March that the arbitration award should be vacat- Fitzgerald the Bank did not release ed or for any modified and all reasons $500,000. guaranty fact, from his In in contemplated by allowed or law. Fitzgerald April 1982 guaran- increased the ty to According $1.1 million. This became to the brief Texas West important Oil ap- because Patch filed in the in support borrowed district court of its proximately motion, million from the Bank $1.1 Texas West contended that completing rig it worked on award Texas should be set aside because it is Fitzgerald’s guaran- West. In addition to manifest mistake of to prof- law award full in ty, March acquired the Bank also it on a contract which the seller failed to perform. alternative, interest in all of Oil inven- In the Texas Patch’s West tory receivable, and accounts which includ- contended that the award should be mod- rig. By (1) ed the September $226,000, ified to the loans reduce the award past due, had become and the Bank which it profit asked claims is the ratio of for the Fitzgerald to guaranty. Fitzger- portion honor his completed; (2) of the not to ald did so and received the note securi- $100,000 reduce award to reflect the ty error; previously (3) interest held require- Bank. arithmetic to strike the payment ment for the interest attor- Texas West asserts that in- fees; ney’s require to to duced the Bank rig. to take the lien on the convey incompleted title to the oil rig to Then assumed control over the upon receiving Texas payment any West disposition rig, requiring addi- unpaid balance owed it. money paid tional be under the contract between Oil Patch and Texas West in order opposition its brief in motion protect West, himself from on the Texas Oil Patch contended that the
1Q61 presents following in Texas West that it did issues was insufficient motion relating to grounds the arbitration award review particularity the there- state with 7(b)(1), W.R.C.P., before Court: by Rule required for as part that: provides refusing “Did the err in which District Court vacate the arbitration award as a mani- for an order application “An to the court injustice buyer fest where the under a which, unless made shall motion is forced pay contract for sale full trial, during hearing or shall be made seller, profit defaulting on a contract to a writing, partic- state with shall [and] * * complete who has refused to and deliver ularity grounds therefor goods the contract under the terms of added.) (Emphasis contract? further contends in its brief Oil Patch [Cjourt “Did err confirm- [District any has failed to show that Texas West ing the arbitration award of interest at convincing why reason the award clear above the First Interstate Bank of 2% any grounds vacated on should be N.A., Casper, prime unliqui- rate on an l-36-114(a), W.S.1977, enumerated in § period began dated sum for a which shall vacate provides that the court (2) years prior run two to the arbitration an award where: arbitration award? “(i) procured by corrup- The award was “Did the District Court err in not vacat- means; tion, undue fraud other ing being the award of interest as “(ii) partiality There was evident panel’s excess of the arbitration authori- neutral, corrup- appointed as a arbitrator ty?” or miscon- any
tion of of the arbitrators Patch has addressed the issues of any party; prejudicing duct by restating Texas West them as follows: “(iii) pow- their The arbitrators exceeded refusing “Did Trial Court err in ers; the arbitration award as a mani- vacate injustice? fest “(iv) postpone refused to arbitrators being hearing upon confirming sufficient cause “Did the District Court err shown, to hear evidence material award of interest? refused the arbitration *6 controversy or otherwise conduct- err in not vacat- “Did the District Court hearing prejudice to substan- ed the as being ing the award interest tially party; the of a or panel’s the authori- excess of arbitration ty?” “(v) agreement, There was no arbitration adversely determined
the issue was not
third issues
The second and
were
provided by
the
by a court as
law and
dispo
presented
the district court for
not
participate in the arbi-
applicant did not
is,
It
by trial brief or otherwise.
sition
hearing
raising
objec-
tration
without
therefore,
appropriate for this Court
that the relief
such
tion.
fact
or not the arbitra
now determine whether
granted
that it could not or would not be
those
award should
vacated for
tion
be
equity
Dennis,
a court of
or
is not a
Wyo.,
law
specific reasons. Dennis v.
refusing
(1984).
to con-
ground
vacating
firm the award.”
dealing
with the first
issue
Although the court’s order contained
West,
contend
Patch continues to
Texas
Oil
recognizing
Texas
statement
that
West’s
only time an
award can
arbitration
grounds for va-
specify
motion did not
pleads
applicant
an
be vacated is when
modification,
appears
it
from the
grounds
cation or
set out
proves one of the
agree.
the motion was
judge’s
l-36-114(a).
decision letter that
do not
The stat
We
that
court
va
merely
not denied for such reason and
ute
states that the
must
grounds
any
if
stated
arguments
counsels’
cate the award
order is based on
pro-
does not
exists. The statute
tracking
therein
their briefs.
vacating
hibit the
court from
an
Patch
district
tween Oil
and itself. This action was
grounds.
other
We
said
award on
tried before a jury which returned
$4a
can
that an award
also be vacated if
before
million
verdict
of Texas
favor
West. On
it
appeal Fitzgerald presents
following
fraud,
corruption,
“was obtained
be-
issues:
beyond
jus-
havior
the bounds of natural
“THE COURT ERRED IN NOT
tice,
authority,
excess of
or a manifest
A
GRANTING JUDGMENT NOTWITH-
appearing
mistake of fact
lawor
STANDING THE VERDICT IN THAT
* *
face
award
Riverton
THERE WAS NO EVIDENCE FROM
Valley Electric Association v. Pacific
A
WHICH JURY COULD FIND:
Company,
Light
Wyo.,
Power and
“A. That
D.N.
interfered
P.2d
with the contract between Texas West
We have also
that
is a
stated
arbitration
[Corporation
Oil and Gas
Oil
voluntary
disputes
method of
settlement of
Patch
of Wyoming,
Sales and Rentals
public policy Wyoming
embedded in the
Inc.; or
Court,
and is
this
favored
that
this
Court is reluctant
“B. The
of any damages
disturb arbitrators’
amount
sus-
controversies,
just
solutions
and that
tained as a
of any
result
interference.
upset
before we will
a district court deci-
“THE COURT ERRED IN NOT
upholding
award,
sion
an arbitration
A
GRANTING JUDGMENT NOTWITH-
applicant
discharged
proof
must have
its
STANDING THE VERDICT IN THAT
convincing
burden
clear
with
evidence.
THE INTERVENOR PRESENTED [A]
Supply Company
Northern
v. Town of
DEFENSE WHICH ENTITLED HIM TO
Wyo.,
Greybull,
JUDGMENT AS A MATTER OF LAW.”
have examined the arbitration
We
Texas
presents
following
West also
award,
panel’s
and we are
find
unable to
relating
damages
issue
in-
for contract
any profit
that Oil Patch realized
much less
terference:
profit
$226,000.
To arrive at
“Did the District Court err in applying
find,
amount
must
we
as Texas West con
legal
incorrect
standard
determin-
tends,
that
million it
$3.5
advanced
ing
the jury
verdict
in-
equals the
expended by
actual costs
Oil
rig
tervenor,
Fitzgerald,
get
stage
Patch to
the oil
in the
D.N.
was excessive
construction which it existed
when
and shocked the conscience of
dispute
are
arose. We
unable to do this
Court?”
any more than we could find that
Patch
In order to establish the
claim
expended
may
million
million.
$1
$4
It
contract,
tortious
interference
anticipated
that it would
plaintiff
prove
must
following
ele
profit
make a
completed,
when
*7
(1)
contract; (2)
ments:
the existence of the
wholly
but Texas West has
failed to draw
knowledge
contract;
the defendant’s
of the
any
testimony
our attention to
document
(3) intentional
plain
interference with the
panel
which was before the arbitration
indi
justification;
tiff’s contract without
cating
Oil
did
that
Patch
so. The conten
resulting damages. Basin Electric Power
tion
Texas West is
on an
based
unwar
Cooperative-Missouri
assumption.
ranted
Basin
For
Power
this reason we
Project
Howton, Wyo.,
hold
v.
that Texas West has failed to
fore, entering judgment did not err in af making When
firming determination of the arbitration award. whether or a trial court should have CONTRACT INTERFERENCE verdict, directed a this Court considers the evidence alleged Fitzgerald party against Texas West that inten- favorable the tionally interfered with be- gives the contract whom the motion is directed and that taking rig. from the There- Carey Texas West inferences. all reasonable evidence after, that a lien existed Jackson, P.2d 868 Gibson admitted Wyo., 603 v. that the matter was out of his hands. a contract being question no that There attempted speak with Dunnavant then knowledge Fitzgerald had and that existed ” “ shots,’ calling the person the ‘who [was] it, carefully examined we have and, had of a conversation he result determine whether appeal record Harries, principals one of the with Tom interfered with Fitzgerald unjustifiably Patch, told he contacted who Oil and, so, Texas West if whether contract rig to take the Texas him that order damages as a result. suffered pay the Bank the have to West would to Texas The evidence favorable $508,000 negotiation and that there was no unjustifiable concerning Fitzgerald’s West point. on that prob that even after interference shows delivery and the infer- developed with find from this evidence lems We drawworks, relationship between Texas may drawn therefrom that ences that On Feb Patch was amicable. and Oil intentionally justifi- West and without 19, 1982, however, Gordon Gibson ruary with the contract between cation interfered to Texas West offer sent a letter Oil Patch Patch and Texas West. Oil paying the of either ing it the alternative pur Having million that there was suffi $5.1 million balance of found $1.6 drawworks, price, jury less the cost of to the to find presented chase cient evidence drawworks, the new paying the cost of interfered Fitzgerald unjustifiably advancing the along balance between Oil Patch and with the contract rig. price completed for the Gib purchase West, must determine Texas we now the first time the that this was son testified sufficient evi or not there was whether money discussed question of additional jury to find that presented to the dence This and Oil Patch. Texas West between damaged actions Texas West. such Gibson, money, according to additional presented jury There was evidence $508,000 which applied to be toward rig value of the without that the market to the Bank on an unsecured Patch owed mil- approximately $3.2 the drawworks was by Fitzgerald. guaranteed loan interference during the times of the lion Milliken, 11, 1982, A. February John On at rig worth would been officer, Fitzger- contacted the Bank’s loan completed if Patch had million Oil least $4 obligations to concerning Patch’s ald possible It is rig with the drawworks. guaranty. Fitz- Fitzgerald’s the Bank and damage this measure of jury used to take a lien on the gerald asked the Bank million. its verdict of $4 it returned when (including rig) and accounts inventory that it lost Texas West contends Patch. The Bank took receivable of Oil interference, and Fitzgerald’s as a result of April during the month of security, and therefore, should be the mar- damages, its liability on 1982, Fitzgerald increased his rig. ket value This new million. to $1.1 though the Bank given even guaranty was relies Texas West The cases to loan Oil made no commitment of dam- value as a measure market concern the time for money or extend additional personal or destruction of age for the loss any existing loans. Packing Co. property. Rocky Mountain (1964); Branney, Wyo., meantime, was at- In the Texas West *8 Hansen, Wyo., 361 P.2d Rogers v. agreement a tempting to finalize or infer (1961). to conclude We are unable to finish party joint for a venture third jury presented to the the evidence Dunnavant, from L.N. rig put it work. to rig. The infer- lost the that Texas West West, that on president of Texas testified interfered with the Fitzgerald ence is that 19, 1982, the existence denied June Gibson delivery rig to Texas West. rig prevent any lien on the which would of We, therefore, judge delivery hold that the trial to rig Patch withhold until applying pay- not his discretion not made did abuse Texas West sufficient additional applicable protect market value as the standard of to ments him from on damages he determined the jury when guaranty.
verdict
was excessive
therefore,
We,
Fitzgerald’s
hold that
de-
of
and shocked the conscience
the court.
fense is untenable and that the court did
previously
grant
held
refusing
We
not err in
judgment
to
a
damages
of
inter
Fitzgerald notwithstanding
measure
intentional
the verdict.
compen
ference is
amount which will
proximately
of
detriment
sate
all
TRIAL
REMITTITUR—NEW
duty.
of
caused
Martin v.
presents
following
Texas West
issues
(1983).
Wing, Wyo.,
to drawworks
one of his
ordering
discretion in
a remittitur or new
Dunnavant,
nies and that he and
on behalf
trial?
West, attempted
negotiate
of Texas
to
a
complete
rig
put
deal to
it to
“Did the
work.
District Court abuse it’s [sic]
Bishop further testified that he
ordering
was “dead
discretion in not
a new trial as
but, according
serious”
the venture
damages only,
about
to
when the District Court
Dunnavant,
testimony
of
the deal
expressly found that there was sufficient
was killed when
refused to allow
support
evidence
the jury
to
verdict find-
payment
to be delivered before
was
ing liability against the intervenor D.N.
to
lien
the rig.
made
release the
Fitzgerald for
interference with
Plaintiff’s contract?”
jury
The
properly
could have
found that
Fitzgerald’s
proxi-
interference was the
power
The
to order a new trial
Bishop
mate cause
Texas West and
damages
for excessive
is committed to the
getting together
complete
put
Cody
sound discretion
the trial court.
rig to
work
that Texas West
dam-
Atkins,
(1983).
Wyo., 658
The trial
aged thereby.
jury
The
could also have
authority
also
court
has
com
order a
found,
contends,
as Texas West
that Fitz-
plete
damages
new trial or
one limited
gerald’s
proximate
interference was the
when the
is
Wright
verdict
excessive. 11
&
nondelivery
the rig
cause
and that Miller, Federal Practice and Procedure:
damage equaled
Texas West’s
the invest-
(1973);
Blair,
Civil 2815
Wyo.,
Smith v.
rig.
ment value
ap
standard for
Although the extent and the amount of
pellate
judge’s
review of a trial
order
damages
may
have resulted from granting a new trial for an excessive dam
Fitzgerald’s interference are difficult
age
verdict
whether
trial
court
ascertain,
find that there was
we
sufficient
abused its
Taylor
discretion.
v. Wash
presented to the jury
evidence
for it to find
ington Terminal
Company,
F.2d 145
damaged.
that Texas West
(D.C.Cir.),
cert. denied 396 U.S.
S.Ct.
determination THOMAS, Justice, specially con- Chief Fitzgerald.1 by D.N. terference curring. disposition by dissent from the I must case for a remands the judg- this court which
I in the affirmance of concur damages only. trial on the issue Fitzgerald. Recogniz- new ment D.N. ordered a remittitur or problems The district court ing significance of the which a new trial. Whether dissenting opinion the alternative raised in the been complete new trial or re- new trial should be Urbigkit, especially the law’s of Justice which I limited new trial is a matter wrongful interfer- quirement that there be discretion placed to be within the existing perceive ence causes breach of may well contract, judge district and which does disclose that sub- the record perception of how much depend sequent early 1982 Texas events plaintiff required to induce the leverage is Corporation and Oil West Oil Gas remittitur. accept Wyoming, and Rentals of Sales Howton, Wyo., verdict, Project judg- Missouri Basin Power motion for 2. Motion for directed verdict, Fitzger- notwithstanding and the One in 404-405 ment finding judgment. position court’s in its order the Bank's is entitled to all of ald’s guaranteed obligation which he has on an justification 1. Whether interference is without it, he has no lawful basis when he satisfies but jury improper question is a of fact for the enhancing creating any rights. Cooperative- one of law. Basin Electric Power *10 1066 implicated lending process trial has wide discretion con- in court this normal granting history, of a new since earliest recorded no
cerning propriety and case Atkins, of this nature is either cited or Wyo., presently 658 P.2d Cody trial. directly indirectly holding found (1983). I majority 63-64 do not read the guarantor surety right does not have the opinion reaching as a conclusion that there protection request principal from the in was an abuse of the trial court’s discretion the event of a for payment. lender call regard. in I do think the record Yet, justify would such a in conclusion. This convoluted and controversial field of of that conclusion what has absence tort law comes this court’s consideration occurred is that this court has substituted significantly any different than other its for of discretion the district court. directly factual situation addressed dis- principles jurisprudence Since of foreclose precedent.2 Preliminarily, covered an in- of our discretion for that substitution trinsically logical inconsistency is created court, I district would remand the in by affirming this case the arbitration case for a new trial on both the issues of decision which determined that no contrac- damages. and liability by nondelivery by tual breach occurred manufacturer in the of payment absence of Justice, URBIGKIT, concurring part remaining due, amount and ap- then dissenting part. and proving third-party liability causing for breach which had not occurred. I concur in the of decision this court to award, respect- affirm arbitration and Unfortunately, questions evidentiary and fully comprehensively and dissent in analysis confused discussion and decision establishing guarantor decision legal on the status which established application of a theory tort an intention- law should have been determinative. al with interference a contract. judgment The Texas theory West and singularly important banking-in- recovery
This is a buyer in its claim for suretyship dustry Principles by appli- decision. intentional interference should fail legal princi- case are cation of three in this well-established and law merchant invoked law, ples: as old as Roman perhaps and older.1 stated, Succinctly this case (1) concerns the Guarantor does not wrong- invoke a principal retained and his purpose ful by requesting or intent assets when required security position protec- lender obtain good guaranty.
stand on a The contention involving tion available assets of the of intentional has interference never Any been debtor. claimed position history (1985); ascribing Handler, 1. A well-considered the differ- 39 Sw.L.J. 123 Broida and ing surety language derivation of from Roman Prospec Tortious With Contract and Interference usage history and Illinois, and from Teutonic Advantage tive 32 De Paul L.Rev. 325 Radin, Guaranty Surety- to be found in and (1982-83); Commentary, With Con Interference (1928-29). ship, 17 Cal.L.Rev. 605 It is contend- Alabama, tractual and Business Relations 34 general ed princi- some authorities that the Comment, (1983); Ala.L.Rev. 599 Interference ples relationships involving suretyship can Prospective With Gain: Must There abe Con history be dated back to the earliest of man in a tract?, Diego (1985); Note, San 22 L.Rev. 401 relationship. societal Tortious With Contractual Relations Interference Century: in the Nineteenth The Transformation subject 2. The of intentional interference aas Contract, Tort, Property, 93 Harvard comprehensively tort is addressed authorities (1980); Perlman, L.Rev. 1510 with Note, Interference journals Leigh law which include: Expectancies: Contract and Other Economic A Carpet Furniture and Co. v. Isom: Utah's New Doctrine, Clash Tort and Contract 40 U.Chi.L. Prospective Tort with Economic for Interference (1982); Note, Rev. 61 Tortious with Relations, (1984); J.Contemp.Law Interference Com Society’s Contract: A Reassertion Interest ment, Analysis An Property Formation Stability Commercial Integrity, and Contractual Rights Underlying Tortious Interference (1981); Dobbs, 81 Colum.L.Rev. 1491 Tortious Relations, Contracts and Other Economic Relationships, with Contractual (1983); Gavin, Hughes U.Chi.L.Rev. 1116 Interference (1980-81). Practices, Ark.L.Rev. 335 Deceptive Commercial Torts and Trade Patch, newly any entity, balance created only co-existent with guaranteed $500,000. loan total of unpaid. 30, 1981, guarantor, any pre- did not cause 2. March as a Guarantor *11 organizer principal, determined vious and a contract since arbitration withdrew princi- operational from the in unpaid was and the involvement that a balance interest, primary party corporation, except guaran- in for continued pal, as the drilling rig responsibility. not release the without tor would receipt. No of contract payment 1, 1981, drilling rig 3. June a manufac- existed. ture contract was executed between Oil West, of an interest in the Patch and Texas contract As a holder secured, clarity was a model for lack of and transaction as a debtor to be term specificity. guarantor privileged as a matter protect his status law to seek to business 4. Patch came Oil to have two loans at by the col- in the normal business effort Bank, one unsecured except by guar- inventory assignment lateral of business anties, operational with an line of credit and receivables. $508,000, with a balance of a and second $645,000, by secured real estate mort- guarantor relationship is a subcate- gage property Casper. on its in business general suretyship, gory of the field of 11, 1982, commonly noted difference be- 5. On March both notes with were surety category having pri- delinquent, rig a due and and the in- tween a as undelivered, guarantor only complete mary liability, and the sub- and with contro- versy as to the construction contract ject monetary by call default price. principal. primary This is the versus sec- ondary liability differential. This field of 6. As a consideration of note-extension generally suretyship, called law (as negotiations, guarantor well as the
procedural aspects here involved as that of being princi- two others the officers and Stearns, guaranty. Suretyship Law of Patch) pals re-signed continuing 1.1, 1.5, (5th 1951). at 4 ed. §§ guaranty in favor of the Bank $1,100,000. larger amount
This case is a business transaction involv- Additionally, 7. the Bank took a securi- ing Fitzgerald (guarantor), First Interstate financing statement ty agreement and (lender), Casper, Bank of N.A. involving “Any and All from Oil Patch Wyoming (principal Sales and Rentals of Inventory,” and Accounts Receivable manufacturer), and and Texas West Oil and File No. U-513862. Corporation (buyer-customer), wherein Gas Texas West entered into contract obligations of the two notes 8. The purchase drilling rig. The a constructed were then renewed and extended $508,000 not unusual construc- days, case accommodates the one for due interest, payment delivery, on com- reciting tion factors of and renewal = Inventory pleted partial payment, incomplete Any con- and All and “S/A F/S Receivable”; $645,- conflict, struction, the one for price with the bal- Accounts having extended renewal dispute. Stripped ance then due in been month to involving for an earlier one jury-trial hyperbole banks and attachment 11,1982, was further extended for buyers or claims of factual is- March contested sues, following days, *12 Inc., Wyoming, operating & Rental of 22,1982, 13. Fitzgerald, October in hon- time, money from time to at and the oring his guaranty on the line-of-credit present note, time have a by secured loan, purchased $508,000 the note with mortgage first on all account receiva- interest, accrued assignment and secured inventory bles and in the amount of financing filed both statements. $508,000. 14. This replevin case commenced aas our Bank “When entertained loan re- by action Texas (long West since denied quests from Oil Patch and Sales Rental court), by the trial by moved intervention Wyoming, request loan by Fitzgerald contest, to priority a lien approved upon your based financial consider, and now comes to after com- standing your guarantee. pleted contract-price arbitration, past 9, July “Both loans are due since question guarantor of whether a “inten- performance with no to date on tionally justification and without inter- either on building loan. Interest fered” with the sales contract September $65,- loan to security loan-renewal document taken 700.42, per with a charge $340.42 diem lender on the borrower’s business after that date. The due interest to inventory and receivables. September 20, inventory 1982 on the 15. The stip- record reflects an in-court $51,745.44, loan is with a $268.11 ulation that amounts due from Texas day charge each after that date. unpaid West as the balance are due to promised performance “Due lack of Fitzgerald repayment guaran- on his loans, on these hereby asking we are ty payment, which amounts were settled you your guarantee. to honor Upon subsequent the arbitration award and payment notes, in full these we will court confirmation. assign you, your protection, our banking The issue in terms is whether a mortgages in the security which colla- lender, or request a lender at the of a teralizes each note. guarantor, require security can collateral “May we hear from you no later than being note subject renewal without Monday, October 1982.” a claim of intentional interference with a 15, 1982, 10.October the Bank secured Pragmatically, also, contract. ques- - financing second statement from Oil tion of whether there could in- have been Patch, granted which security listed terference with a ques- contract since equipment specifically included proof tion of contract itemized inclusions the undelivered Texas principal as vendor with the vendee is rig,
West
financing
statement was
issue not otherwise
except by
determined
19, 1982,
filed October
Coun- prior
Natrona
collateral decision
an arbitration
ty
generalized
covered
detail
that a
unpaid
balance remained
when the
prior
financing
collateral contained
provided
contract
delivery upon
full
statement.
payment.3
exhaustively
Texas West
briefed the issue for
the trial court that
constrained
Conceding everything
juncture
at
to mined effect of the 1982
replevin
denial of
majority
Texas
or the
of this
either
West
appeal.4
as not raised on this
court,
only
intrinsic,
I would consider
essence
the case as a mercantile
unquestioned banking transaction and its
question invoking
law
suretyship precedent
dispositive
clearly
attributes as
under the
quotation
is defined in a
from the majority
perspective
current status and historical
opinion:
the law.
“ * * * We do not find as a matter of law
Obviously,
guarantor
was interested
Fitzgerald’s position
as a
protecting
guaranty exposure,
his
entitled him to induce Oil Patch to with-
being
issue
whether the law constrains that
delivery
hold
until Texas West
See Martin v.
being unjustified.
effort as
made
payments
sufficient additional
Texaco, Inc.,
(S.D.Miss.
F.Supp.
protect him
guaran-
from
1969).
ty.”
(a) absolutely no
conflicting
evidence that
Patch
as to whether the offer was
agreed
payment,
release
without
both).
made Oil
or Fitzgerald,
reason;6
whatever
stipulated
It was
parties
between the
at
(b)
has now determined
arbitration
that a
any
trial that
wrongful
contention of
con-
due;
balance was
only
duct of
occurred
suit
before
(c) Fitzgerald
money
wanted
out
filed,
and consequently
honoring
his
rig to
the loan balance and
cover
accepting
the collateral
guaranty;
assignment for collection assistance in sub-
(d)
Wyoming
both the contract and the
rogation and indemnity
not a
claimed
provided
statute
had
vendor
factor for contractual interference.
right
payment
to demand
in full before
majority
The
opinion finds relevant evi-
release
merchandise.
asking
dence of
interference
the lender
In order
define the case in
some mean
requiring
take the lien and then
payment
ingful terms, since the scenario shifts in
negotiation
release,
without
on the Bank’s
litigation,
the course
it
is first neces
premised on the manufacturer’s concur-
sary
times,
to ascribe
events or actions to
rence. This standard fails to include the
wrongfully.”
the “intentional interference
improper motives,
means,
improper
and ef-
lacks
record
evidence to find interfer
fective cause of contractual breach
ence,
deter-
more so to
but even
find lack of
required
minations which
liability.
are
justification
surety-
activities
ship transaction,
Leigh
Isom,
despite
Carpet
Furniture and
Co.
application of
v.
Utah,
appellate
(1982);
the usual
Top
standards of consider
delivery, financing 2-511, burdened its bank at 7.
obligations?
19, 1982,
judge,
The trial
on October
first,
Addressing
question
the
subject by
second
the
addressed the
letter to counsel
complicated,
issue is
since the trial court
for Texas West:
replevin,
denied
which became the law of
“Upon reviewing
legal
the file and some
designated
the case and is not now
as er-
authorities,
appears
it
to me that a writ
ror, and is further inflicted
the
arbi-
replevin
in
My
cannot issue
this case.
determining
tration award
that a balance
understanding
buyer
of the law is that a
remained due.
goods
only
replevin
can
maintain
when
However,
complete.
the contract of sale is
The
subject
we can address the
obligation
ambiguous
the issue of the
contract here is
as to
manufacturer’s
least,
partial
pay-
price.
very
to deliver
total
purchase
plain-
under a
At the
price
developed.
unpaid
ment where
conflicts
Un-
tiff
need to tender the
would
bal-
L.Rev.,
Conner,
suretyship principles,
supra
Enforcing
8. An exhaustive review of
n.
See also
exoneration,
including
Vanishing
sub-
reimbursement and
Commercial Guaranties in Texas:
defenses,
Limitations,
Questions,
rogation,
houn,
Remaining
as well as
is found in Cal-
12 Texas
(1981).
Suretyship
Lawyer,
the Iowa
67 Iowa
Tech.L.Rev. 785
price
Sprinklers,
on the
million. Even
Wyo.,
(1985),
$5.1
anee
1073
‘(1) that a valid contract existed
ruled
be
The trial court
ation.
plaintiff
party;
tween the
and another
determining
they did not
plaintiffs
knowledge
that the defendant had
means,
rep-
make false material
illegal
use
of the contract and intended to induce
resentations,
to fraud or intimi-
or resort
thereof; (3) that the
a breach
contract
dation,
they
what
believed to
and exercised
breached; (4)
proximate
as a
re
legal rights
good
faith.
their
wrongful
sult of the defendant’s
or
appellate court concurred.
conduct; (5)
unjustified [unprivileged]
the four-factor
rule
Wyoming follows
resulting
damage
plaintiff.
to the
position
representative of the
generally
Fox,
Abrams &
Inc. v.
[Citations.]’
770:
Restatement of Torts
adopted
§
(1974),
604, 608,
Briney
Cal.App.3d
39
recognized
prior
cases the
“We have
328,
Cal.Rptr.
114
331.” Internation
interference with con-
tort of intentional
Dry,
al Wood Processors v. Power
and have identified the
tractual relations
Inc.,
710,
(D.S.C.1984),
F.Supp.
593
729
following elements of such action:
(4th Cir.1986).
aff’d
“On
Associates,
Restatement, Torts,
773, p.
Ltd. v. Golden State
ing
out in 4
87
Strawberries,
F.Supp.
(1939),
that:
(E.D.Mo.1983),
aff’d 747 F.2d
privileged purposely
to cause
“One
(8th Cir.1984).
contract, or
perform
not to
another
rela-
enter into or continue a business
Washington
four-point
test
follows
tion,
good
person by in
with a third
Wyoming delineation. Cal
similar to the
asserting
threatening
pro-
faith
Knudtzon,
65 Wash.2d
bom v.
legally protected inter-
properly
tect
P.2d 148
may
est of his own which he believes
from those
significant
A
number of cases
destroyed by
impaired or
otherwise be
position
support
taken
jurisdictions
the contract or
performance
here.
Willey,
transaction.” Wartensleben
Wyoming prece-
particularizing
Without
supra,
See Restatement, ples we which follow A.L.R. 43. judg- the disabilities of the would consider five-part test: follows a California in this case the factual issue ment without *17 questions. law, inducing breach California “Under (1) security request that ele- Guarantor’s tort with five basic
of contract is a wrongful. is not See Allen v. obtained ments: 1074 Co., Inc., In Ford Incorporated, v. C.E. Wilson & supra;
Safeway Stores
su-
Quinlivan
Co.,
v. Brown Oil
pra,
posi-
96 Mont.
the Bank exercised its
v. C.E.
147,
Ford
(1934);
29
374
tion
intentional
interference was de-
Inc.,
Co.,
(2d
&
Wilson
third-party
“There
store
Ohio, Inc.,
rate, additional,
164,
1
tems
overriding
Op.3d
reason
Ohio
47
precludes Ethyl’s liability
App.2d 20,
(1975) (val
‘in-
Ohio
1075
Lewis,
law,
Davis v.
construction);
“At
Tex.
common
where the creditor re-
pipeline
security
principal
ceived
from the
(1972) (auto re
for the
411
Civ.App., 487 S.W.2d
debt,
payment
surety
of the
could not
shop
contro
company
direction
pair finance
Steck,
force the creditor to look first
Sakowitz, Inc. v.
to such
versy). See also
payment.
surety
for his
The
(1984) (enforcement
Tex.,
of
105
669 S.W.2d
protect
by paying
could
himself
the credi-
agreement);
employment
noncompetition
thereby becoming subrogated
tor and
Knudtzon, supra (attorney’s
Calbom v.
rights
security.”
the creditor’s
in the
fees).
Id.,
7.22 at 237.
§
resulting in a
Factual determinations
“Subrogation
suretyship
in
is ‘a mode
intentional-interfer
attack as an
successful
equity adopts
compel
the ulti-
Pipe
in Alyeska
are illustrated
ence claim
discharge
of the
him
mate
debt
who
Service,
Air
Co. v. Aurora
line Service
it,
good
ought
pay
conscience
and to
Inc., Alaska,
(1979) (sub-sub
1090
604 P.2d
him
relieve
whom none but the creditor
ill
and bad faith and
will
terminated
right
pay.’
scope
could ask to
The
fact);
alleged creating issue of
general
subrogation
consists
the immediate
Co., 16 Cal.
Leasing
Bridges v. Cal-Pacific
transfer,
law,
by operation of
(1971) (com
118,
Cal.Rptr. 796
App.3d
93
promisor
suretyship
all
transaction, advice to third
plex real estate
principal
the creditor
whenev-
payments,
to make
inference
party not
promisor pays
er the
the debt or satisfies
Koz
support
justification);
lack of
could
obligation.
right
subrogation
This
Bank, 6
lowsky
National
v. Westminster
agreement
independent
any
be-
(1970) (offi
593,
Cal.App.3d
Cal.Rptr.
86
52
parties
upon princi-
and rests
tween
Morgan,
v.
McEnroe
discharge);
106
cer
Id.,
ples
justice
equity.”
of natural
(1984)
326,
(justification
Idaho
the
change
security documents did not
the
eral
Fitzgerald
relationship
also be made that
and Texas
Note must
between Oil Patch
pay-
right
possession
West,
assignment
after
en-
only claimed
since the collateral
consequent as-
cumbering inventory
and
and
could
ment
receivables
by
him
rights to
If
signment
only
of the collateral
and did
encumber
receivable.
nothing,
he
the
lender. At that time
became
it was entitled
the
Texas West owed
event,
assign-
This
as earlier not-
rig possession,
secured lender.
and the collateral
ed,
rig.
not the interference
in the
by stipulation was
ment afforded no interest
changed
pledge
way
in no
title
causative factor.
collateral
and
money
If
was due
status.
Charged
Party To be
Interest of
nothing
right
payment,
likewise
had a
With Claimed Interference
changed except
right
the
of the lender
Torts
In accord
the Restatement of
guarantor to receive that
or subordinated
hard to define a more
provision,
it is
money upon payment of whatever amount
asset value remain-
specific interest
contrac-
due as derived from the
remained
than that held
ing due to the manufacturer
relationship
the manufacturer
tual
between
guaranteed indebt-
when the
Corp. v.
buyer.
and
Tidal Western
into de-
payment matured
edness without
Tex.Civ.App., 297 S.W.
Shackelford,
lender for
then called
fault
Fi-
guarantor payment. Zoby v. American
(4) Damage
Cir.1957)
(4th
242 F.2d
Company,
delity
substantial”);
damage
(“economic
for determination of
Assumptive
interest
Steck,
Fitz-
Sakowitz,
supra,
anything
669 S.W.2d
of how
question
Inc. v.
basic
legal rela-
adversely affected the
gerald
did
by the
tionships determined
arbitration
Legalistically,
position of Texas West
award.
resulting
appro-
after
jury
verdict
consequent
creates
priate summary-judgment motions
contend for
To
malicious-prosecution con-
to determine as
amorphous,
damages,
required
it is
surety
Fitzgerald,
right of the
turned
law
cept denying
principle
business
guaranty payment,
to contest and claim
some time before
lender after call
to release the
forced the seller
delinquent borrow-
should have
rights to the
collateral
direct and
buyer
with two
only
equipment
theory
This
is not
er’s assets.
First,
significant asset
results.
func-
divisive
province
any operational
within the
stigated
gone
repay-
by Fitzgerald
be
from which funds for
would
which loss was
ment to the
could
been
sustained
Texas
Unfortunately,
West.
expected,
juncture
case,
and for
present
in the
of this
principal
avoid indemnification would
speculate
trial court is left to
as to the
if
Secondly,
have been lost.
contractual default which constitutes the
makes demand on the borrower to release
damages might
fact from which
subse-
security,
then the borrower
collateral
proved
be
quently
by the
evidence
as-
right
has the
to claim an offset for the
jury.
complex
sessed
This is a
against any
due either
instru-
value
debt
since,
requirement,
my opinion,
no con-
subrogated right of
assignment or
ment
proved.
tract default has been
indemnity.
majority
Since the
is determined to re
what
of Califor-
No matter
construction
court,
verse the trial
excise
remittitur
nia,
York, Oregon, or
New
Restatement
jury
and reactivate
further
for the deter
tort,
may
rules
utilized
damages,
mination
the court should de
appropriate
justify
transaction was not
termine the event of contract default and
*21
$500,000, $4,000,000,
verdict for
damages
provide
the measure of
in order to
may
later
be determined
whatever
expectancy
litiga
some rational
this
conclusion,
jury
figure
aas
that suits their
pursued
seasonably
tion
since 1982 will be
jury
Inc.
as witnessed
Texas
Texaco
probability
terminated without the
of an
(2d
Company,
It contemplation is not with idle I affirm would the decision of the trial damages concern about measure of arbitration, court on and would also today addressed. none par- Where reverse entry the trial court and direct the ticipants really drilling want the stacked judgment in of a favor defendant Fitz- rig, one is called to envision a morass with- gerald plaintiffs on the counterclaim safety rope out into which the trial court intervenor, against the expectancy will be thrust an effort to instruct the possibly litigation without further jury authority respon- next as to their parties investment in cost all would now sibility. Texas West owes I agree be concluded. would $467,000, plus sum of interest and attor- original court that neither jury award $678,387.17 ney’s totaling fees as of March nor the reduced amount remittitur was 13, 1985, statutory percent ten interest proven proper damage aas award. See payment, since that date. On Texas West dissenting majority opinions in Petty- rig, drilling should entitled to the which Ray Geophysical, Geosource, Division of apparently parties now value at about Ludvik, Wyo., Inc. v. $250,000.11 Against presently the amounts creditable due,
aas there debt determined would then jury damages
be the to be from a derived
determination of the ki- contractual default
11. The determination of amounts due award, arbitration which amount has been as judgment signed derived from the entered in favor of by Fitzgerald. to and is collectible West, pursuant Oil Patch Texas with notes is left the same both the case extension-period percent sequences unquestioned carrying an time events: interest rate. 1.December, 1980, Fitzgerald and oth- July 1982 came signed continuing guaranty ers 9. The due date 22,1982, (now went, September and on Casper First National Bank of First N.A.) Bank made written demand on Casper, Interstate Bank of to ac- (what honor his operational commodate an line of credit banking 18, 1982, the “guaranty known October the lawsuit was call”): instituted Texas West recover the Patch, raising from Oil the basic know, 30, 1981, on you “As June question possessory right of its for im- Casper Bank of First Interstate loaned delivery. mediate Wyoming, Oil Patch Sales & Rental Of 15,1982, Slough Equipment 12. October Inc., $645,000, secured a first mort- (a Company company not then controlled gage on the real estate located by Fitzgerald) bought the real estate St., Casper, Wyo- West Yellowstone mortgage Bank, from the received an ming. assignment of mortgage, com- “We also loaned Oil Patch Sales menced power foreclosure of sale.
