This is a breach of contract suit.
Frank Thrasher instituted a suit on a sworn account against Robert P. Barnhill, the appellee and cross-appellant. Barnhill filed a third party action against Texas Power and Light Company (T P & L), appellant and cross-appellee, alleging a breach of contract and seeking both actual and exemplary damages. Thrasher obtained a summary judgment against Barnhill and the third party action against T P & L was tried before a jury. T P & L appeals from the award of exemplary damages and Barn-hill appeals the trial court’s action in disregarding the jury’s finding that $180,000.00 would reasonably compensate him for damage to his business.
In November of 1976, T P & L and Barn-hill entered into a written contract in which Barnhill agreed to clear a right of way upon which T P & L planned to erect a transmission line. Barnhill hired Frank Thrasher on an hourly basis to do part of the work. He worked from December of 1976 until June of 1977 when he left because Barnhill owed him over $44,000.00. On June 27, 1977, while Barnhill was clearing the right of way, Tyler O’Teter, T P & L’s Supervisor of Contract Construction, brought him a letter informing him that his contract had been terminated. This litigation followed.
In response to special issues the jury found that: No. 1) T P & L owed Barnhill $43,344.32 at the time his contract was can-celled; No. 2) T P & L did not have good cause to terminate the contract; No. 3) Barnhill would not have made any profit had he been allowed to complete the contract; No. 4) Barnhill incurred damage to his business from the time of the cancellation of the contract to the present date; No. 4-A) the sum of $180,000.00 would reasonably compensate for the damage to his business; No. 5) T P & L acted intentionally or willfully or with a degree of gross negligence which indicated a fixed purpose to bring about the cancellation of the contract; No. 6) T P & L previously or subsequently approved the acts of its agents; and No. 7) $100,000.00 would adequately punish T P & L for its conduct.
Both parties moved for a judgment with T P & L requesting that the court disregard the jury’s answers to Special Issues Nos. 4, 4-A, 5, 6, and 7. The court disregarded the answer to Special Issue No. 4-A and entered judgment for Barnhill for the sum of $143,344.22.
T P & L by its first eight points of error deals with the court’s award of exemplary damages, asserting that it was error because: this was a breach of contract action and no independent tort was pleaded, proved or found; the jury failed to find actual damages; there was no evidence or insufficient evidence to warrant submission of the issue; the pleadings failed to support an issue on exemplary damages; there was no evidence or insufficient evidence to warrant a finding that T P & L condoned or approved of the action relied on for recovery of exemplary damages.
In Texas, it has long been the rule that exemplary damages cannot be recovered for a simple breach of contract, where the breach is not accompanied by a tort, even though the breach is brought about capriciously and with malice.
A. L. Carter Lumber Co. v. Saide,
T P & L asserts that Barnhill has completely failed to plead or prove that a tort was committed. Barnhill alleged that T P & L’s termination of the contract was “arbitrary, capricious, and unwarranted” and done with “malicious intent” and here asserts that T P & L’s actions constituted not only a breach of contract, but also the tort of wrongful termination of employment. He claims that T P & L’s conduct toward him was harsh and oppressive and cites
K.W.S. Mfg. Co., Inc. v. McMahon,
As before noted, both T P & L and Barn-hill find fault with the court’s actions in regard to issues 4 and 4-A. T P & L asserts that the submission of the issues, even though no recovery thereon was allowed, was error and Barnhill, on his cross-appeal, contends that the court erred in disregarding the jury’s answer to 4r-A because it was supported by the pleadings and by legally and factually sufficient evidence.
As stated before, the jury found that Barnhill’s
business
had been damaged (Special Issue No. 4) in the amount of $180,-000.00 (Special Issue No. 4-A). The pleadings pleaded damages to his “business reputation” and the prayer sought damages to “plaintiff’s reputation.” T P & L objected that issues No. 4 and No. 4-A were not supported by the pleadings. Its objections, however, were stock objections and too general to preserve the point on appeal. Tex. R.Civ.P. 274 reads, in part, “A party objecting to a charge
must point out distinctly the matter to which he objects and the grounds of his objection.”
(Emphasis added). One of the purposes of Rule 274 was to discourage the use of general stock objections.
Monsanto Company v. Milam,
The point is not preserved because T P & L’s objections did not “make it apparent that the trial court, though fully cognizant of the ground of complaint, nevertheless chose to submit the issue.”
Bell v. Missouri-Kansas-Texas Railroad Co. of Texas,
T P & L also argues that the court erred in submitting issues No. 4 and No. 4-A without giving the jury any guidelines as to the proper measure of damages. Again, T P & L failed to adequately preserve this point for appeal. T P & L failed to distinctly point out its grounds for objection as required by Tex.R.Civ.P. 274. It stated merely that “there is nothing in this record to give the jury any guidelines about answering said special issue ...” and that “the issue as framed permits and requests the jury to engage in speculation and conjecture with regard to damage to business .... ” See
Hicks v. Fredericks,
Having dealt with T P & L’s objections to the submission of the issues we must now review the trial court’s action in disregarding the jury’s answer to Special Issue No. 4^A. We hold that the trial court erred.
Rule 301 of the Texas Rules of Civil Procedure provides, in pertinent part, “that upon motion and reasonable notice the court may ... disregard any Special Issue Jury Finding that has no support in the evidence.” “No evidence,” as used in connection with this rule does not mean literally no evidence at all. Instead, it encompasses “those situations wherein by the application of established principles of law, the evidence is deemed legally insufficient to establish an asserted proposition of fact.”
National Life and Accident Insurance Co. v. Shern,
In determining whether the trial court erred in disregarding the jury’s answer to Special Issue No. 4r-A this Court must consider only the evidence and the reasonable inferences therefrom which support the jury’s answer.
C. & R. Transport, Inc. v. Campbell,
A general rule of contract law, illustrated by the famous case of Hadley v. Baxendale, 9 Exch. 341 (1854), is that the non-breaching party in a breach of contract action may recover those damages,
*336 “as may fairly and reasonably be considered either arising naturally; i.e., according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of the breach.”
See
5 A. Corbin, Contracts § 1007, n. 1.5 (1964). This case involves a specific application of this rule. The only damage to his business for which Barnhill had any apparent basis for recovery under contract law was lost profits from collateral contracts. Lost profits from collateral contracts, however, are recoverable only if such collateral contracts are known to or are within the contemplation of the parties at the time they enter into the contract which is subsequently breached.
Longview Const. & Dev., Inc. v. Loggins Const. Co.,
Viewing the evidence in the light most favorable to the jury’s answer, Barnhill sufficiently established losses from collateral contracts, e.g., the loss of an $840,000.00 contract. Although the actual amount of lost profits is subject to dispute, there is evidence from which the jury could calculate damages with a reasonable degree of certainty. And while there is no direct evidence that the parties contemplated T P & L was aware of Barnhill’s collateral contract, there is a very strong inference that T P & L knew of them, given T P & L’s long-term relationship with Barnhill. The court therefore erred in disregarding the jury’s finding of $180,000.00 in damages to Barnhill’s business.
The last issue concerns T P & L’s argument that it was entitled to the submission of the following issue and instruction:
“Do you find from a preponderance of the evidence that R. P. Barnhill prior to June 27, 1977, failed to perform in a professional manner the duties of general contractor under the contract in question?”
The instruction also requested:
“The work of general contractor is professional in nature and that anyone agreeing to do the same is bound to exercise such care, skill and faithfulness in performing such work as would be reasonably expected of other individuals similarly situated.”
There is a common law duty accompanying each contract “to perform with care, skill, reasonable expedience and faithfulness the thing agreed to be done, and a negligent failure to observe any of these conditions is a tort, as well as a breach of the contract.”
Montgomery Ward & Co. v. Scharrenbeck,
The cause is reversed and remanded with instruction that the judgment be amended preserving the sum of $43,344.32 as the sum of money awarded to Robert P. Barnhill by Texas Power and Light Company under the contract, deleting the $100,000.00 of punitive damages, and adding the $180,000.00 for the damage to Robert P. Barnhill’s business.
