Texas Instruments Incorporated (“TI”) appeals the final decision of the Armed Services Board of Contract Appeals (“ASBCA”) that “the amount of $628,069 is determined to be a fair and reasonable price for [Contract] Modification PK0005.”
Texas Instruments Inc.,
90-1 BCA (CCH) 1122,537, at 113,097,
I
Contract No. F19628-77-C-0126, for the supply of tactical photographic interpretation equipment and supporting materials, was awarded to TI on May 27, 1977, by the U.S. Air Force. The contract provided that unpriced line items were to have their firm fixed price bilaterally negotiated after issuance of an order for the item. The Government issued Provisioned Item Order PK0005 on September 30, 1980, with a “not-to-exceed price” of $672,067.95. Ms. Ruby Hill, the ACO, assigned Mr. Jim Jeppe, to meet with TI’s representative, Mr. Alan Johnson, to negotiate a price. Prior to meeting with Johnson, Jeppe reviewed the price analyst’s report, the audit reports and, along with Hill, defined the Government’s objective. On August 24, 1981, after three days of discussion, the two representatives arrived at a firm fixed price. Johnson wrote a letter to Jeppe stating that, as of August 24, TI “agrees to a firm fixed price of $672,067.86.” Johnson also submitted an executed Certificate of Current Cost or Pricing Data that referred to the negotiated price.
Regulations governing procurement by negotiation require that the “contractor shall be required to submit only one certificate which shall be submitted as soon as practicable after agreement is reached on the contract or modification price.” DAR § 3-807.6(a); 32 C.F.R. § 3-807.6(a) (1982). In the absence of such a certificate, “the contracting officer shall withhold making the award or price adjustment.” DAR § 3-807.5; 32 C.F.R. § 3.807.5 (1982); see also § 3-807.3(b) (“certification is required prior to: (1) the award of any negotiated contract (except for unpriced actions such as letter contracts) expected to exceed $100,000 in amount”); 41 U.S.C. § 254(d) (certification that pricing data in non-bid contracts or modifications are accurate, complete and current).
On September 15, Jeppe prepared a PNM reviewing the events that led to the negotiation of the price. Preparation of a PNM after completion of a price negotiation is required by the Defense Acquisition Regulations. DAR § 3-811; 32 C.F.R. § 3-811 (1982). A PNM is an internal document not transmitted to the contractor. In non-bid, negotiated contracts, the PNM must refer to the contractor’s submitted certificate of cost or pricing data. Id. Jeppe noted that such a certificate had been submitted. The PNM further stated that “[t]he negotiated amount of $672,067.86 is considered fair and reasonable” and that “[fjunds have been obligated as follows” with a reiteration of the negotiated amount. Underneath Jeppe’s name as author, the PNM had a signature block which contains Hill’s signature and which reads:
APPROVED BY:
RUBY L. HILL
Administrative Contracting Officer
The ASBCA found that “[t]he PNM had to be acceptable to Ms. Hill before she would sign it” and that “[t]he PNM was submitted to, and approved and signed by Ms. Hill, the ACO.” At the time they *812 signed the PNM, both Jeppe and Hill considered the amount negotiated to be a fair and reasonable price. TI I at 98,073 (Finding 11). Jeppe and Johnson had negotiated several previous provisioned items. In each instance, the ACO had issued a Standard Form 30 (“SF-30”) confirming the agreed upon price following the negotiation and submittal of an appropriate certificate. Jeppe visited the TI plant on September 28, after preparing the PNM and obtaining the ACO’s approval. Johnson stated in a sworn affidavit not disputed by the Government that during a conversation with Jeppe on September 28, Johnson was told to submit a new Certificate of Current Cost or Pricing Data as the caption had been incorrect on the first one. TI forwarded a second executed certificate on October 2. Unbeknownst to TI, events following this meeting on September 28 succeeded in derailing the issuance of an SF-30 by the ACO. First, Jeppe and other Government personnel examined the electronic equipment provisioned by the order. They believed that the cost was not justified by the apparently simple design, but they were mistaken in believing the design to be simple. TI II at 113,090-091 (Finding 19-21). Second, Jeppe was informed that costs for work on software development of the electronic equipment had been allocated to an earlier contract. This information was also wrong. Id. (Finding 19, 22-23).
Finally, and also unknown to TI, the Department of Defense had established an internal audit procedure whereby all contract administration actions taken by ACO’s were subjected to review by Contract Management Boards of Review (“Review Board”). Neither Jeppe nor Hill had discussed this review procedure with TI. Jeppe later noted that “[tjhis review is required for proposed contracts of this type over $250,000, and is required before the Government and contractor enter into a formal (signed) contract.” ASBCA found that the ACO “was not free ... to utterly ignore the review process.” TI I at 98,079. “She was obliged, instead, to await the [Review] Board’s report and, prior to proceeding with the pricing of the order, to give due and careful consideration to any recommendations made therein.” Id. Review Boards are authorized under two published regulations, DAR § 23-104 and DAR § 8-600, neither of which concern contracts to be negotiated by an ACO. 32 C.F.R. §§ 8-600, 23-104 (1982). Under a non-public directive, their authority was extended to include “examin[ation] and evaluation of] documentation concerned with contract administration actions which have been negotiated or otherwise completed and processed by an ACO.”
On October 2, the Review Board requested supplemental data to answer questions on the price negotiations for this Order. TI I at 98,073 (Finding 12). On October 20, Hill wrote to TI and stated that the negotiations had been “subject to review by the DCASR Contract Management Board of Review” and that “[i]t appears that the agreed-to amount of $672,067.86 did not result in a fair and reasonable price.” Hill requested that the negotiations be reopened. TI I at 98,074 (Finding 16). TI objected to the re-opening by asserting that a final binding agreement had been reached.
II
The ASBCA noted that “there is no SF30 executed by the ACO setting forth her acceptance of the negotiated price.” The ASBCA held that the ACO’s signature on the PNM was not “intended to manifest assent,” because “[t]here is no conduct here on the part of the ACO that she had ‘reason to know’ would be understood by [TI] as manifesting agreement to the price negotiated by Mr. Jeppe.” TI I at 98,077. The ASBCA stated:
All we have here is the ACO’s act of signing the PNM. By itself, the signature could not connote the ACO’s assent to the price negotiated on August 24, 1981.
Id.
In other words, because the ACO did not communicate her assent to TI, her signature approving the negotiated price was deemed an insufficient expression of assent to bind the Government. Furthermore, the ASBCA held that in view of the internal directive requiring the ACO to wait until the Review Board rendered its opinion, she could not legally have reached a final decision assenting to the negotiated price.
*813
The ASBCA distinguished its prior decision in
Electrospace Corp.,
72-1 BCA (CCH) ¶ 9,455,
Ill
TI contends that the ASBCA erred in holding that a contract was not formed upon negotiation of the price and its subsequent approval by the ACO. We thus consider whether the ACO’s signature must be understood as establishing a prima facie case of approval of the negotiated price absent contrary evidence.
In
General Electric Co. v. United States,
Colonel McDermott was acquainted with the facts underlying the overrun dis-pute_ [I]t seems clear that, as a responsible Government official, he would have duly investigated the matter before indicating his concurrence, as contracting officer, in a recommended course of action. Failure to do so before signing in an official capacity would have been a neglect of duty. Unless evidence to the contrary is produced, the law presumes that official actions are properly taken.
We disagree with the board’s conclusion that Colonel McDermott used the definite language of recommendation merely as an executive notation that the letter had crossed his desk. To conclude, in the absence of direct evidence, that a contracting officer would so loosely use language embodying his authority conflicts with the mentioned presumption
... Under the facts present here, we believe that when an authorized contracting officer expresses a definite opinion concerning the merits of a claim with knowledge of the relevant facts, a “decision” has been made.
General Electric,
The body of law established by our predecessor courts has been adopted by this court.
South Corp. v. United States,
The Court of Claims also held in General Electric that the Government can be bound by a contracting officer’s “unfettered opinion [as] the person delegated as decision-maker by the parties to the contract,” id., even when that opinion is expressed in internal correspondence. In short, General Electric would require us to find a binding agreement if we were to find that the ACO’s approval signature on the PNM was an expression of her final decision.
IV
The issue before us is whether the ACO’s approval of the PNM in this case was a final binding decision. First, we address whether the ACO had to execute an official document,
e.g.,
an SF-30, as an indication of a final binding decision. In a different context, this court has stated that “any bilateral modification of a contract is a ‘supplemental agreement,’ which requires the execution of a written standard form 30.”
Mil-Spec Contractors v. United States,
any written alteration in the specification, delivery point, rate of delivery, contract period, price, quantity, or other contract provisions of an existing contract, whether accomplished by unilateral action in accordance with a contract provision, or by mutual action of the parties to the contract. It includes (i) bilateral actions such as supplemental agreements, and (ii) unilateral actions such as change orders, orders for provisioned items, administrative changes, notices of termination, and notices of the exercise of a contract option.
A “Supplemental Agreement” was defined in the regulations as “any contract modification which is accomplished by the mutual action of the parties.” 32 C.F.R. § 1-201.18 (1981) (emphasis added). The Government contends that the price negotiation in this case was to terminate in a “supplemental agreement,” or a “contract modification,” and since contract modifications require the issuance of an SF-30, 32 C.F.R. § 16-103 (1981), an SF-30 must have been required.
The regulations governing
Mil-Spec
and
SCM
simply are inapplicable to the facts of this case. In both
Mil-Spec
and
SCM,
the alleged oral agreements were indeed supplemental since they would have altered or modified the existing contract.
SCM,
*815
Second, we address whether the ACO here could not have issued a final binding decision because the Department of Defense had interposed an internally-required Review Board proceeding that precluded such a decision prior to consideration of its recommendations. Generally, “[w]hen the United States enters into contract relations, its rights and duties therein are governed by the law applicable to contracts between private individuals.”
Lynch v. United States,
V
We must now decide whether the facts as found by the ASBCA require the conclusion that a final binding agreement, a “meeting of the minds,” was reached between the parties. We review the ASBCA’s findings of fact for substantial evidence.
United States v. General Electric Corp.,
[WJhere the evidence is undisputed but it is of such a nature that ... the [ASBCA] could have made only one finding of fact, it would seem that this court can make that finding without sending the matter back to the [ASBCA] for determination of the factual issues; otherwise, litigation would be protracted and unnecessary delay and expense would result simply in order to have the [ASBCA] formally decide a fact which legally can be decided in only one way.
Maxwell Dynamometer Co. v. United States,
Whether a legally enforceable contract has been formed by a meeting of the minds depends upon the totality of the factual circumstances. We base our conclusion that a contract was formed upon uncontested facts and those facts specifically found by the ASBCA. The ASBCA found a signed writing by each party approving the agreed upon price of $672,067.86. We have held that the signatures must be given effect as a matter of law. The uncontested evidence establishes that the ACO’s approval of the negotiated price was communicated to TI. TI expressed its approval of the negotiated price in the Certificate of Current Cost or Pricing Data. Furthermore, there had been a mutual expectation that negotiation would result expeditiously in a final decision as confirmed by the prior episodes of negotiation to final agreement, Jeppe’s preparation of the PNM memorializing final agreement, the approval of the PNM by the ACO, the filing of a Certificate by TI stating the date of agreement as August 24, 1981, and the request by Jeppe, after approval of the PNM by Hill, of submission of a corrected Certificate. In short, the single term, price, is found in contemporaneous documents signed, indicating agreement thereto, and acknowledged by both parties to the contract.
*816
Finally, we ask whether the discovery of new information could authorize the AGO to revoke a previously-established agreement. The reopening of negotiations based upon allegedly newly-discovered, unchecked, erroneous information, has been condemned by the ASBCA in
Kurz & Root Co.,
74-1 BCA (CCH) ¶ 10,543,
REVERSED.