History
  • No items yet
midpage
Texas Department of Transportation v. Jones Bros. Dirt & Paving Contractors, Inc.
92 S.W.3d 477
Tex.
2002
Check Treatment

*1 insurаnce, professional medical DEPARTMENT TEXAS OF inevitably impact

would availability TRANSPORTATION, Auld, medical care. See 893. Petitioner, To the “availability increase of medical Texans,” care for Legislature sought v. liability make health damages care more predictable professional so medical in- JONES DIRT & BROTHERS PAVING surance would be available affordable CONTRACTORS, INC., rates. Id. Respondent.

Mandating prejudgment the award of No. 00-1067. interest on past damages, Legisla- as the Supreme Court of Texas. P, ture has done under subchaptеr does goal. not undermine that Prejudgment Argued on Jan. calculation, interest to precise and thus the maximum amount of addition- Decided June exposure may al readily be anticipated Auld,

insurance carriers. See (Hankinson,

at 909 J. concurring and dis-

senting). Legislature

Had the intended to limit prejudgment award of interest under

subchapter cap, K’s it would have referred

to that subchapter it subchap- when added Furthermore,

ter P in 1995. Leg- had the

islature prejudgment intended for interest

to be awarded in liability some health-care others,

cases but not it would not have

chosen the mandatory language did for

subchapter P. Given the self-contained Act,

structure of the it seems extremely

unlikely to me that the Legislature would ignored

have both K subchapter and used

mandatory language subchapter P had

it not intended exempt prejudgment past

interest on damages liability from the

cap. Because the Court concludes other-

wise, I dissent. *2 Cornyn, Attorney of the

John General Texas, Andy Taylor, First Assis- State Gilbert, General, Attorney F. tant Jack General, Attorney Leigh Assistant Ronda Neff, Click, Grady Boyd, Office Jeffrey S. General, Austin, Attorney for Peti- of the tioner. Hearne, Epp- D. &

Douglass Hearne Powers, & right, Eppright Ann R. Hearne Austin, Gest, for Respondent. opinion BAKER Justice delivered the Court, in which Chief Justice HECHT, PHILLIPS, Justice Justice OWEN, HANKINSON, Justice Justice O’NEILL, Justice JEFFERSON and joined. RODRIGUEZ Justice Paving Brothers Dirt & Contrac- Department with Texas tors’ contract Transportation provides prior Disadvantaged terminating removing (DBE) Enterprise Business subcontractor project, from a Jones had to demonstrate Oppor- Business “to the satisfaction of the in Austin” tunity Program Office [BOP] DBE was or unable unwilling stan- appropriate decide perform. We un- reviewing the BOP’s decision dard clause. We the contract’s satisfaction der of the decide whether section 201.112 also Code, which estab- Texas lishes administrative remedies TxDOT, exclu- disputes provides with remedy for common-law sive declara- breach of claims for tory relief.

We conclude that the Administrative The contract authorized Jones to deter- Judge correctly Law reviewed the BOP’s DBE mine what work the that Jones ‍‌‌​​‌‌‌‌​​‌‌​‌‌‌‌​​‌‌​​​​‌​‌‌​​‌​‌‌‌​​‌​‌​‌‌‌​‌‌‍chose decision for whether it was based on perform. forty- would Jones contracted tiality, error. Concrete, percent two of the work to AK *3 Therefore, аppeals the court of erroneous- However, DBE. Jones and TxDOT soon ly instructed the trial court to remand the AK became concerned that Concrete was claim administrative to the ALJ to review unqualified, and its substandard work had the BOP’s decision under a different stan- project progressed. to be corrected as the dard. 899-900. Further- formally AK Jones notified Concrete that more, we Transportation conclude that the unsatisfactory, its work at- was then provides Code remedy exclusive tempted tо terminate AK Concrete from Jones’s against common-law claims project. Jones also notified the BOP Thus, TxDOT. the court of appeals incor- that replace wanted to AK Concrete rectly remanded claims to the trial court with another DBE subcontractor. replead for Jones to showing facts waiver BOP, charged TxDOT subdivision sovereign immunity. S.W.3d at 902. administering with DBE programs, re- Accordingly, we reverse ap- the court of quested provide that Jones to documents peals’ judgment remanding Jones’s com- demоnstrate that AK Concrete was unable mon-law claims to the trial court for re- unwilling perform. to reviewing After pleading, dismiss those claims for lack of the documentation provided, Jones and af- jurisdiction, and remand remaining Concrete, ter interviewing Jones and AK claim to the trial court for proceedings that, although BOP concluded AK consistent with opinion. Concrete’s work substandard and had I. BACKGROUND corrected, to be there was no evidence that problems delayed had project. Jones contraсted with to recon- TxDOT Therefore, the BOP denied request Jones’s struct 4.28 miles of FM in Presidio replace to AK Concrete. County. Because federal partly funds supported project, the contract re- Eventually, discharged TxDOT AK Con- quired Jones to subcontract at least ten attempting crete for to bribe a TxDOT percent Also, of the work to a DBE. be- time, inspector. by But Jones cause of this funding, govern- the federal longer secure substitute subcontrac- required ment Jones’s contract with tor and completed thus the work itself. provision TxDOT to have a requiring this, late, job Because of Jones finished the Jones to obtain approval from TxDOT’s $22,500 liquidated TxDOT assessed a DBE terminating BOP before that Jones damages against failing Jones for to meet project: hired for a deadline. Prior to terminating removing a DBE pro- Jones then initiated administrative

subcontractor named in the commit- ment, ceedings Code to the Contractor must demonstrate $139,000 costs, recover about additional Op- satisfaction of the Business $22,500 which included a refund of the portunity Program Office in Austin the originally designated liquidated damages DBE that TxDOT assessed was not able TraNsp. Jones. See to willing perform.... Any against substitu- tions of ap- DBEs shall be 201.112. TxDOT’s contract claims com- Next, proval by Opportunity the Business Pro- mittee claim. denied Jones’s gram requested hearing Office Austin. a contested case in the peti- Hearings. appeals noted Jones’s

State Office of Administrative 201.112(b); showing facts a waiver allege tion failed 2003.021(b)(1). 2001.051, sovereign immunity §§ of TxDOT’s Gov’t Code and declar- was not common-lаw breach of contract The ALJ determined claims, have atory judgment for the dam- Jones should liquidated liable to amend. 24 S.W.3d ages, opportunity but denied claims for the an she Jones’s Therefore, re- finishing additional related Jones’s costs ALJ deter- manded claims to trial court AK Concrete’s work. The these opportunity replead denying mined the BOP’s decision allow Jones exception as an DBE “waiver conduct” request to terminate its “was immunity. 24 was not TxDOT’s reasonable and based *4 misconduct, appeals thе of fraud, or error.” at 901-02. Because court gross any under recovery the deci- did not affirm Jones’s adopted proposed TxDOT ALJ’s it liquidated grounds, the did not decide Jones sion reimburse Jones 24 at 902. damages. attorney’s fees. S.W.3d damages deny and additional recover re- parties petitioned Both re- sought substantial evidence view. trial court. view of decision the TxDOT’s 201.112(d); Thansp. suit, 2001.171. In that II. ADMINISTRATIVE Gov’t original claims for common-law REVIEW also raised PROCEEDING —JUDICIAL contract, declaratory judgment, breach against claim TxDOT— Jones’s and fees. TxDOT answered attorney’s in the and proceeding in the administrative immunity against and asserted recover, among other trial court —seeks issuing claims. original Jones’s Without incurred allegedly the things, costs Jones law, the findings of fact or conclusions not its re- approve the BOP did because the part trial court affirmed of TxDOT’s DBE. trial replace the In the quest damages, reimbursing liquidated order the court, the ALJ commit- Jones claimed deny- part of order but it reversed the the law, ted an error of because she damagеs. The trial court ing additional she the wrong standard when reviewed the for Jones then rendered deny request to decision to BOP’s $139,077 included damages, terminate the DBE. Jones asserts $22,500 inter- damages, plus in liquidated deci- reviewed BOP’s ALJ should have attorney’s and fees. est under a “reasonableness” sion re- applies when the trial because that standard reversed The court appeals First, viewing a under “satisfaction” ap- court of decision judgment. court’s v. Pipe Lake Line Co. claim contract. See Black thе administrative peals remanded (Tex. Co., 80, 88 Constr. to remand Union trial with instructions court 1976), grounds, part overruled in other decision to review the BOP’s ALJ Co., 767 v. Marathon Oil S.W.2d AN Sterner request to terminate denying Jones’s hand, (Tex.1989). 686, other 690 On the under a different standard Concrete re- the ALJ Second, properly TxDOT asserts 24 899-900. review. S.W.3d partial- decision under viewed BOP appeals concluded the court of misconduct, fraud, gross or error stan- ity, rule on it did not trial court erred because and, dard, applies when that standard jurisdiction in- becаuse plea TxDOT’s deci- referee’s stead, reviewing agreed-upon it ren- it overruled when impliedly v. McKen- Antonio City court of sion. See San judgment. The dered final Bros., 315, zie Constr. 136 Tex. clause. See State v. Martin S.W.2d (1942) (1941). 989, 505,160 58, (plaintiff S.W.2d allege prove highway must that State Jones, The court of appeals agreed with engineer’s partiality, decision was based on reversed the trial judgment, court’s fraud, misconduct, error); Austin gross remanded the case to the trial court. The Bridge Teague, Co. v. 137 Tex. appeals court of detеrmined (1941) 1091,1092 (applying partiali- subdivision, is a BOP the satis- fraud, misconduct, ty, gross error stan- effectively subject faction clause was Highway Engi- dard of review “State TxDOT’s sole determination. 24 S.W.3d at clause); neer’s” decision under satisfaction Relying on Black (Tex. Clark, State v. appeals concluded that the ALJ committed writ) (court 1985, will set App.-Austin an error of law when it reviewed Jones’s highway engineer’s aside State decision claim, proper because the review only if plaintiff proves was based on standard is reasonableness rather than fraud, misconduct, partiality, er- or gross er- ror); State, Bridge Austin Co. v. Thus, ror. 24 S.W.3d at 899-900. 937 (Tex.Civ.App.-Austin court of instructed the trial court *5 n.r.e.) (absent pleadings writ refd to remand to the ALJ to decide whether proof engineer’s that State decision was deny the BOP’s decision to request fraud, misconduct, partiality, based on or AK terminate Concrete was unreason- error, gross engineer had exclusive and able. S.W.3d at 899-900. authority final to determine satisfaction of performance). Applicable A. Law There are two different standards for The second review standard —whether reviewing decisions under a contract’s the decision was applies “reasonable” — provision. “satisfaction” Which standard when the to the contract has the applies depends on the nature of the con- authority ultimate determine whether tract involved. The first standard— satisfaction clause has been satisfied. See whether the decision partiali- was based on Lake, (adopting Black 538 S.W.2d at 88-89 fraud, ty, misconduct, or gross error —is reasоnableness test because construction McKenzie, derived from our decision provided contract that one party to con- McKenzie, 150 S.W.2d at 989. In tract could overrule its inspectors’ own Court held that parties “[w]hen to a build- decision about whether performance was ing agree questions to submit Cranetex, satisfactory); Inc. v. Precision may arise thereunder to the decision Inc., Houston, Rigging Crane & engineer, of the his decision is final and (Tex.App.-Texarkana conclusive; unless in making guilty it he is denied) (apрlying writ reasonable- fraud, misconduct, or such gross mis- a party ness test ‍‌‌​​‌‌‌‌​​‌‌​‌‌‌‌​​‌‌​​​​‌​‌‌​​‌​‌‌‌​​‌​‌​‌‌‌​‌‌‍because to the contract imply take as would faith bad or failure to designated and not a final expert had de- McKenzie, exercise an honest judgment.” termination perfor- about satisfaction of 150 S.W.2d at 996. mance). objective reasonableness

Texas courts applied have this standard which is to prove, less onerous in other cases in which desig- allays agreements the contract concerns that condi- engineer nates an building project upon might on the party’s tioned one satisfaction to determine whether aspect per- illusory they some be could be vulnera- formance suffices under a party’s satisfaction ble to that whim or bad-faith with- Lake,

holding approval. Black 538 a “whim” or party’s “caprice” be illusory, S.W.2d at 88. the Court concluded that the

ty’s performance about decision whether satisfactory objectively must be reason- B. ANALYSIS Lake, Ap- at 88. able. Black We conclude ALJ facts, plying that standard correct review standard — decided that the contractors could recover gross re error—-to “not for the additional work if it was rea- view the BOP’s decision to deny Jones’s scope sonably within contract’s request remove AK Concrete from the simply technical and not specifications” Lake, In job. Black this Court had to Black the addi- inspectors Lake’s ordered required whether decide the contract fraud, mis- tional work “the absence of prime contractor and to per subcontractor Lake, conduct, Black mistake.” Lake, form additional work for Black at 89. whether the work extra-contractual Here, of appeals the court determined compensable quantum and therefore between Jones and Lake, meruit. Black 538 S.W.2d at 86. analogous TxDOT is to the contracts prove To the work was not “extra” But this two im- disregards Black Lake. contract, required but was Black portant case not factors make this like relied on prime Lake contract and the Black and most to those comparable Lake subcontract, which both stated that cases Black Lake declined to follow. See inspectors decisions of Lake’s Black under (distinguish- Black 538 S.W.2d at 88 work-performance satisfaction clauses Bros., 60; Aus- ing Martin “final and were conclusive” the contrac 1091; Bridge, tin *6 binding tors but were not on Black Lake. 989). McKenzie, 150 at S.W.2d Lake, Black 538 at 88. Lake S.W.2d Black that, long contended as the inspectors’ as First, contract between TxDOT and the to decisions order additional work were about ter- Jones made the BOP’s decision misconduсt, fraud, gross not based on or parties, DBE all the minating binding a mistake, the Court should deem the work including TxDOT. Unlike the contract “required” under the contract. Black right Lake to overrule gave Black a Lake, 538 S.W.2d at 88. The Court disa perfor- inspectors’ its decisions about greed. mance, in the contract here provision the BOP’s deci- allows TxDOT overrule that, in The Court first noted the cases Lake, at 88. sion. Black 538 S.W.2d Cf. upon, pro- Black Lake relied the contracts Second, court of contrary that an or what the engineer’s vided architect’s deci- analysis suggests, the Court’s de- appeals’ under a clause would bind sion satisfaction Lake, reasonable- parties. apply all the Black at cision in Black Lake a S.W.2d Bros., 58; Black (citing at ness standard did not turn on Lake’s Martin S.W.2d 1091; McKenzie, having authority to de- Teague, inspectors at own the S.W.2d 989). Then, satisfactory. at the if performance 150 S.W.2d Court ob- termine was (“Because that, contrast, in the Lake See 24 at 893 the BOP is served Black S.W.3d [TxDOT], we provided inspectors’ de- a within believe сontracts subdivision effectively conclusive clause was only cisions were final and this satisfaction contractors, party; Black to the determination the while Lake is the accordingly applicable the the standard inspectors’ overrule decisions. Be- test.”). As objective dis- satisfying cause a contract conditioned on reasonableness above, And, holding terminating cussed our in Black Lake a DBE. as the record having shows, turned on Black Lake itself regulations it is the federal about right to ovеrrule its decisions. inspectors’ comply DBEs with which TxDOT had to Lake, (“Black Black funding project. 538 S.W.2d at 88 receive federal for the (1993). Lake’s satisfaction was the conclusive test Consequently, See 49 C.F.R. objective of whether the work properly per- Black Lake’s concern that an inspectors formed. When the [the ordered “reasonableness” review standard was nec- work, perform essary prevent contractors] extra in the contract that case order only was effective because Black being illusory from is not raised here. See stand.”). Lake, Lake let it Accordingly, though Black at BOP’s subdivision, the BOP is a TxDOT this is temptation request to refuse a to termi- not critical determining factor when “caprice” nate a DBE on a “whim” or is what review standard applies. externally oversight. checked federal Lake, See Black at 88. Ac- Indeed, those cases which the cordingly, correctly the ALJ applied fraud, applied partiality, courts or gross fraud, gross error standard error standard engineer’s to review the denying review the BOP’s decision clause, decision under the satisfaction request to terminate its DBE. engineer was an employee of a McKenzie, Finally, contract. See 150 S.W.2d at we note even if the court of 996; Teague, 1093; requiring Martin were correct in review Bros., 61; Clark, 160 S.W.2d at reasonableness 675; Bridge Austin expressly at ALJ concluded its final order Yet, courts still the BOP’s decision was “reasonable.” fraud, tiality, challenged sufficiency error standard to Jones has not engineers’ review the decisions. the evidеnce that the support- As this ALJ found explained ing Black that conclusion. “[i]n decid- ing those cases we refrained from substi- III. SOVEREIGN IMMUNITY

tuting our for that of the archi- tect engineer, and we held that In seeking judicial ‍‌‌​​‌‌‌‌​​‌‌​‌‌‌‌​​‌‌​​​​‌​‌‌​​‌​‌‌‌​​‌​‌​‌‌‌​‌‌‍addition to review decision of the engineer decision, architect or agency brought two *7 final and conclusive in the absence original causes of action in the trial court: mistake.” a common-law breach of contract claim Black at 88. declaratory judgment and a action. Both premised claims are on the same contract Here, we likewise should refrain from dispute that was the of the suit for substituting our for that of the judicial review. TxDOT claims that the BOP. The record shows that the BOP is a jurisdiction trial court lacked the decide TxDOT subdivision in Austin with the sole claims, original because Jones’s adminis- purpose of the DBE administering and remedy trative action is the exclusive Historically Under-Utilized Business Pro- available on the contract claim. Further, grams. the record establishes regulations that federal require determining that thе In trial the court could to, claims, contractor provide original documents and re- the court of resolve the from, that, approval appeals ceive the BOP before ter- had stated Jones sued after Moreover, session, minating a DBE. the federal the legislative Jones would contract, government reviews the BOP’s records to not have able to been assert the properly procedures declaratory ensure it follows for judgment actions addi- seeking obtaining agency prоcess tion to the decision. The avail itself that before the appeals Legislature’s court of relied on a amend- the consent sue under Transportation ment to the Code that es- Civil Practice and Remedies Code. Little- procedure Tex, the tablishes administrative at 597. resolving disputes contract with TxDOT. 1997, the Legislature In amended recognized at 900. The court an ad- Transportation Code establish that not- Legislature provided procedure through ministrative law, any withstanding proce- other disputеs resolve with may ties contract Transportation proscribed dures 1, 1997, 75th June TxDOT. See Act of Code “shall constitute the exclusive reme- 1.36(a), R.S., 1171, § Tex. Leg., ch. dy resolving law” for a claim that sec- (codified 4427, Laws, Gen. Tex. governs. 24 Act (citing tion S.W.3d at 900 201.112). TraNSp. § Legisla- Code 1997, R.S., 1171, Leg., 75th ch. June amendment ex- ture’s comment to this 1.36, § 1997 Tex. Gen. Laws plains Code’s stat- (codified TRánsp. 201.112, § at Tex. remedy utory procedure the exclusive cmt.)). appeals But the court of concluded determining disputes between that it clear not whether exclusive private parties. TxDOT and

remedy rule when Jones’s action 201.112, § cmt. This exclu- TRANSP. Code arose. 24 900. Consequently, S.W.3d at remedy any claim applies sive rule appeals court of focused whether pending before on the amend- any demonstrating pled facts date, September ment’s effective immunity sovereign TxDOT waived its Transp.Code 201.112, cmt. The See concluding from After suit. that Jones Legislature to mean the “pending” defined so, appeals had not done court of re- claim with TxDOT but has been filed manded the breach declar- yet judicial not sought claimant has review. atory the trial judgment claims to court 201.112, cmt. See replead any give opportunity facts whether TxDOT demonstrating Analysis B. immunity waived from suit. its We conclude S.W.3d at remanding erred in Jones’s common-law Applicable declaratory judg breach of contract and

A. Law replead- ment claims to trial court for protects Sovereign immunity ing. analogous case is Little-Tex This money damages from lawsuits for State Co., we Insulation in which held Legislature expressly unless thе consents in the participate must administra Comm’n v. suit. General Sews. expressly pro process Legislature tive Little-Tex Insulation *8 contract claims vided for certain breach of (Tex.2001). party seeking a Generally, seeking Legisla as a prerequisite breach contract can estab redress for of Prac consent to under the ture’s sue Civil by bringing lish consent to sue legislative Little-Tex, tice and Remedies Code. See obtaining special suit under a statute Here, the Legislature Little-Tex, legislative resolution. See that Trans expressly has determined 596; Tex. PRAC. & S.W.3d at Civ. Rem.Code provides the exclusive rem Further, portation Code § when a statute ex 107.001. against TxDOT. edy for contract claims pressly provides pro for an administrative Transp. 201.112, § cmt. types certain of contract See cedure to resolve Tex. Code State, rule remedy applies claims must This exclusive against dispute. Jones’s Jones its adminis- conclude that the ALJ re- filed Because we the cor- trative claim with viewed the BOP’s decision under TxDOT Decembеr the ALJ issued her final that rect we reverse the court order adopted TxDOT in and insofar as it remands appeals’ December trial sought judicial substantial evidence that issue to the court with instruc- April review on review the Accordingly, tions remand ALJ to remedy provision applies, exclusive be- decision under a different standard. BOP’s Furthermore, cause Jones filed its claim with because we conclude that TxDOT but yet sought judicial Transportation provides had not review on the Code the ex- remedy amendment’s effective date. See Tex. clusive for breach of contract Transp. 201.112, TxDOT, § against The trial we reverse the cmts. claims also Code jurisdiction court appeals’ judgment remanding thus lacks over Jones’s court common-law breach of contract and declar- common-lawbreach of contract and declar- claims, atory judgment atory judgment no matter how claims to the trial court for Therefore, pleads replead them. Jones to im- we hold waiver munity. erred in remand- Accordingly, we rеverse the court ing those appeals’ judgment entirety, claims to the trial court for re- dis- its pleading. miss common-law breach of con- Jones’s declaratory judgment

tract and claims against jurisdiction, for lack of and IV. CONCLUSION remaining remand the claim to the trial jurisdiction The trial court’s in this case court for proceedings consistent with this was limited to a substantial evidence re- opinion. view of TxDOT’s final order. 201.112(d); § Code Tex. Gov’t concurring Justice ENOCH filed a and § 2001.171. Accordingly, the trial Code dissenting opinion. only court could hаve affirmed the ALJ’s opinion Justice ENOCH filed an decision, or reversed and remanded it concurring part dissenting part. the trial court determined that the ALJ’s was, decision among specific other statuto- I do not take issue with the standard considerations, ry by affected an error of that the Court concludes the Administra- § law. See Tex. Gov’t Code 2001.174. Judge apply Con- tive Law should to this claim. sequently, the trial court erred proceed- award- Jones initiated the administrative ing interest, damages, Code, Jones additional ings Trаnsportation under the and I attorney’s fees. In rendering judg- agree its with the case need ment, the trial court either exceeded its not be remanded for review under a differ- power review disagree substantial evi- ent standard. But I with the rule, dence entertained origi- holding Court’s nal jurisdiction claims over which it had no provides remedy Code the exclusive procedure pro- the administrative against breach of contract claims the Tex- vides remedy. the exclusive See Department Transportation. as TRAnsp. 201.112, cmt; statutory allowing provision admin- Gov’t discussed, 2001.174. we remedy As have istrative this case1 is substan- *9 identify failed tially provisions similar to the at issue trial court’s errors. General Services Commission v. Little- Transp. 1. See Tex. 201.112.

486 Therefore,

Tex for the rea- InsulUtion Co.2 Little-Tex, MIDLAND COM JUDICIAL DISTRICT expressed my sons dissent AND COR MUNITY SUPERVISION I respectfully part dissent from that of the DEPARTMENT, Peti RECTIONS dismissing Court’s com- Jones’ tioner, mon-law breach of contract and declarato- ry judgment claims. v. It a fair I question why ask contin- JONES, Respondent. Ruthie Ann dissenting sovereign

ue from this Court’s immunity concerning con- No. 01-0557. jurisprudenсe when clearly tracts the Court so decided Supreme Court of Texas. Sign issue v. Federal ‍‌‌​​‌‌‌‌​​‌‌​‌‌‌‌​​‌‌​​​​‌​‌‌​​‌​‌‌‌​​‌​‌​‌‌‌​‌‌‍Texas South- University3 ern Re- Texas Natural 27, June source v. IT— Conservation Commission (Tex.2002).4 74 Davy, Simply, 849 decided, wrongly

these cases were unabated,

damage wreaked continues full cost remains untotalled. List grow.5 continues to As to the immunity holding, I re-

Court’s

spectfully again. dissent — 2001, (Tex.2001). no (Tex.App.-Houston [1st Dist.] 2. 39 S.W.3d 591 304 Rivera, pet.); No. Safety Dept, Tex. Pub. v. (Tex.1997) 3. 951 S.W.2d 401 13-01-00446-CV, Tex.App. 2001 LEXIS 7681 15, (not 2001, (Corpus pet.) Nov. no Christi (Tex.2002). 4. 74 S.W.3d 849 designated publication); Landry’s for Crab 03-00-00690-CV, Regents, No. Shack v. Bd. of 5. See Tex. Dep’t Transp. v. Bros. Dirt 1240832, Tex.Aрp. WL 2001 LEXIS 2001 Contractors, Inc., 477 92 Paving & 2001, (Austin 18, (not pet.) des- 6948 Oct. no (Tex.2002); Assocs., County v. & Travis Pelzel ignated publication); v. for Bexar Ondemir (Tex.2002); 77 S.W.3d 246 v. IT- TNRCC 04-00-00497-CV, Clerk, 2001 WL County No. (Tex.2002); Davy, 74 S.W.3d 849 Gen. Servs. (San 1136074, Tex.App. LEXIS v. Comm'n Little-Tex Insulation 2001, 26, denied) (not pet. Sept. des- Antonio (Tex.2001); S.W.3d 591 Dep’t ignated No. Perry, publication); for v. O’Dell (Tex. Inc., ‍‌‌​​‌‌‌‌​​‌‌​‌‌‌‌​​‌‌​​​​‌​‌‌​​‌​‌‌‌​​‌​‌​‌‌‌​‌‌‍Aer-Aerotron, 39 v. 726387, 03-00-00603-CV, 2001 WL 2001); Univ., Sign v. Federal Tex. S. 29, 2001, (Austin Tex.App. LEXIS 4367 June (Tex.1997); S.W.2d 401 Dep’t Pub. (not pet.) designated publication); no for 40 S.W.3d 687 Safety Corp., Capital v. Int’l (Austin Ramirez, S.W.3d 376 DOT State v. 2001, pet.); City (Tex.App.-Austin no Denver 2001, filed) (not designated publica- pet. (Tex. Moses, 51 S.W.3d 386 Ind. Sch. v. Dist. tion); Corp., Sys. AFEX A & M Univ. v. App.-Amarillo pet.); no Gendreau v. 03-00-00222-CV, 2001 WL No. (Tex.App.- Hosp., Medical Arts 1, 2001, (Austin filed); Tex.App. LEXIS 1266 Mar. pet. City Eastland Houston v. (not designated pet.) publication). Northwood Util. Dist. No. Mun.

Case Details

Case Name: Texas Department of Transportation v. Jones Bros. Dirt & Paving Contractors, Inc.
Court Name: Texas Supreme Court
Date Published: Jun 27, 2002
Citation: 92 S.W.3d 477
Docket Number: 00-1067
Court Abbreviation: Tex.
AI-generated responses must be verified and are not legal advice.