Appellants are the owners of two adjoining lots with a frontage of 100 feet on Main Street in the City of Little Bock, and in the year 1912 they let a contract to the Shenk Construction Company (an Oklahoma corporation) for the construction of a building to be occupied as a department store) The contractor proceeded with the work of constructing the building, out abandoned the building before the work was completed, and appellants had to complete the building themselves. Said principal contractor while engaged in carrying out the contract purchased material from appellees, who were manufacturers of structural and ornamental iron work in the State of Oklahoma. Appellees furnished certain materials which were used in the building by the principal contractor, and this is an action instituted by them against appellants to enforce the lien on the building .and lot for the amount of the unpaid account. There are two gross items in the account which, according to the testimony adduced by appellants, represent separate contracts made by them with the principal contractor for iron work used in the building. At the time the principal contractor abandoned the job one of the contracts between the present claimant land the principal contractor had not been completed, but was subsequently completed under a contract between appellants as owners and appellees. The work of completing the contract was paid for by appellants and a credit of $285.00 was given on the account. Appellants defended' against the asserted lien on numerous grounds.
Conceding that the words “just and true account” mean, as ordinarily construed, an itemized account, (Brooks v. International Shoe Co., 132 Ark. 386) this court has decided that failure to itemize the account does not defeat the lien. Wood v. King, 57 Ark. 284. In reaching ■that conclusion the court followed the rule which had been repeatedly announced here that the lien of a mechanic or material furnisher ‘ ‘ springs out of the appropriation and use by the land owner of the mechanic’s labor or the furnisher’s materials, and not from the taking of those formal steps which the statute enjoins for the preservation and assertion of the lien and for giving notice to others of its existence and extent;” that the statute is highly remedial in its nature and that “when’ the controversy is between the holder of the lien and the proprietor of the land, an exact compliance with the statute at all points is not indispensable. ” Anderson v. Seamans, 49 Ark. 475.
It is argued that the decision in Wood v. King, supra, relates to a controversy between a material furnisher under contract with the owner himself, and that the statute ought not to be given that effect in a controversy between a sub-contractor and the owner. The answer to that contention is that there is only one statute on the subject which applies to liens asserted by sub-contractors, as well as those asserted by principal contractors, and that the statute must be given the same interpretation in both cases. In fact, we see no reason why the rule should be different in the two classes of cases, for, after all, the design of the law-makers was to provide a method for giving public notice of an assertion of the lien and the extent thereof. That design is fully carried out by giving the ■statute such, an effect as will require a notice which will apprise the public of the extent of the claim. Of course, when it comes to an enforcement of the claim by a suit in court, then for purposes of defense the owner may insist upon the presentation of an itemized claim. Brooks v. International Shoe Co., supra. But in testing the sufficiency of the account so far as concerns the preservation of the lien, we hold that it is not essential that the account filed be an itemized one.
There is also a contention that the court allowed appellees a lien for items of material not furnished for use under the contract between appellant and the principal contractor, but were used under the contract between the principal contractor and the lessee of the building. The proof does not sustain appellant’s contention on that point as we understand it. The court only allowed for item® which were used by the. principal contractor in carrying out its contract with appellant.
The account taken from the books of appellees contained items for labor, but the labor formed a part of the price -of putting in the iron work as a completed job, and appellees were entitled to a lien, not as for labor, but as for the price of material furnished in the place to be used.
We think the conclusions reached by the chancellor on all of the propositions raised by appellant were correct.
There is a cross-appeal by appellees as to two items disallowed by the court, or rather- for two credits placed by the court on the account of appellees.. It appears that on one of the jobs which was incomplete at the time the principal contractor abandoned the work, the cost of completion would have been the sum of $387.00, and instead of completing the job under the old contract appellees made a hew contract with .appellant to finish up the work for $285.00. That sum was paid in cash and was credited on the original account of appellees against the principal contractor, but the court held that there should have been a credit on the original contract price to the extent of the value of the item, which was $387.00. The court, therefore, .allowed an additional credit of $102.00, which seems to us to be correct.
. The other item of credit allowed by the court was the sum of $175.00, which the proof showed was an item furnished under the contract with the lessee and erroneously charged up under the contract between the principal contractor and appellants. The court merely corrected that error and required appellees to credit it back, or rather’ struck it out of the .account.
Our conclusion is that the decree was correct in all respects, and it is affirmed both as to the original appeal and the cross-appeal.