TERRA FIRMA BUILDERS, LLC v. WILLIAM KING A/K/A BILLY M. KING AND MELANIE L. KING A/K/A MELANIE L. FRANTZ
No. 2593 EDA 2018
IN THE SUPERIOR COURT OF PENNSYLVANIA
FILED JULY 19, 2019
2019 PA Super 219
KUNSELMAN, J., MURRAY, J., and PELLEGRINI*, J.
J-A09038-19; Appeal from the Order Dated August 22, 2018 In the Court of Common Pleas of Delaware County Civil Division at No(s): CV-2015-001536; * Retired Senior Judge assigned to the Superior Court.
OPINION BY PELLEGRINI, J.:
Terra Firma Builders, LLC (Contractor) appeals from the order entered in the Court of Common Pleas of Delaware County (trial court) granting the motion to strike a mechanics’ lien filed by William King a/k/a Billy M. King and Melanie L. King a/k/a Melanie L. Frantz (Owners) pursuant to the Mechanics’ Lien Law of 1963 (Mechanics’ Lien Law).1 For the following reasons, we reverse.
I.
We derive the relevant background of this case from our independent review of
On April 29, 2013, Contractor then refiled the exact same mechanics’ lien it had previously perfected in March 2013 and it was given a new docket number. This time, though, Contractor failed to file an affidavit of service for the refiled lien as required by Section 502 of the Mechanics’ Lien Law.2 The
Owners did not file any preliminary objections to the claim as provided for in Section 505 of the Mechanics’ Lien Law. On February 19, 2015, Contractor then filed a Complaint to enforce the lien. Owners did not file preliminary objections to the Complaint alleging the defect in service of the underlying mechanics’ lien nor did they otherwise raise it as a defense in that action.
On December 8, 2017, the trial court then consolidated the lien, the Complaint to enforce the lien as well as Contractor‘s breach of contract action against the Owners. The consolidated matters then proceeded to trial with the Owners prevailing on the merits. Post-trial motions were then filed.3
In June 2018, while post-trial motions were still pending, the Owners then filed a petition to strike the mechanics’ lien4 because Contractor failed to strictly comply with statutory requirements governing perfection of the lien, specifically,
court granted the motion to strike, i.e., preliminary objections under § 505 of the Mechanics’ Lien Law could be filed at any time, even after the enforcement action was filed and the trial was over. This timely appeal followed.
II.
A.
On appeal, Contractor contends that the trial court erred in striking the mechanics’
To answer this question, we examine how mechanics’ lien claims can be challenged and enforced under the Mechanics’ Lien Law.
B.
Mechanics’ liens “were unknown at common law and are entirely a creature of statute.” Terra Technical Services, LLC v. River Station Land, L.P., 124 A.3d 289, 299 (Pa. 2015) (quoting Bricklayers of Western Pennsylvania Combined Funds, Inc. v. Scott‘s Development Co., 90 A.3d 682, 690 (Pa. 2014)). “Such liens are designed to protect persons who, before being paid (or fully paid), provide labor or material to improve a piece of property. Mechanics’ liens accomplish this goal by giving lienholders security for their payment independent of contractual remedies.” Id. (internal citations omitted). The Mechanics’ Lien Law not only provides for such liens but creates a statutory procedure for the filing of and enforcement of such liens. “[T]he right to a mechanic[s‘] lien is purely a creature of statute and it is only available if the conditions of the legislature are strictly followed.” Schell v. Murphy, 153 A.3d 379, 381 (Pa. Super. 2016) (citation omitted).
After notice of a claim has been given as required by § 501 of the Mechanics’ Lien Law,
Any party may preliminarily object to a claim upon a showing of exemption or immunity of the property from lien, or for lack of conformity with this act. The court shall determine all preliminary objections. If an issue of fact is raised in such objections, the court may take evidence by deposition or otherwise. If the filing of an amended claim is allowed, the court shall fix the time within which it shall be filed. Failure to file an objection preliminarily shall not constitute a waiver of the right to raise the same as a defense in subsequent proceedings.
This allows the owner to strike the lien for the above-enumerated reasons. If the labor and material were furnished for residential construction the owner could also claim that the contractor or subcontractor waived his right to file such a lien. See
However, while the filing gives the contractor an in rem lien for the materials and labor that were expended under contract for the owner, it does not give the contractor the right to execute against the property to collect those debts or to keep that lien in force “forever.” To be able to maintain and collect against the lien, the contractor must bring an action pursuant to Section § 701 of the Law,
This action must be filed by the contractor within two years of the filing of the lien. See
Also, at any time after the filing of the lien, the owner can compel, by praecipe, the contractor to file a complaint within twenty days after service of the rule or be forever barred from enforcing the lien. See
C.
From the above, an owner who desires to challenge the perfection of the lien or the ability of the contractor to file the lien must do so by filing a preliminary objection to the claim under Section 505 of the Mechanics’ Lien Law. Because Section 505 statutory preliminary objections are governed by the Mechanics’ Lien Law itself, not the Rules of Civil Procedure, Section 505 preliminary objections do not have to be filed within twenty days like those to a normal civil complaint. Moreover, any defenses authorized by Section 505 but not raised by statutory preliminary objections are not waived and may be used a defense in subsequent proceedings.
That does not mean, though, that Section 505 preliminary objections can be filed at any time to the claim; after all, they are denominated as “preliminary.” Given the Mechanics’ Lien Law‘s statutory scheme that governs leading to final resolution in the § 1701 enforcement action, Section 505 can properly be construed as providing that if one of the specified defenses has not been raised “preliminary” by the time a § 1701 enforcement action has been filed to obtain judgment on the claim, but the owner desires to assert a Section 505 defense, it has to be raised in the enforcement proceeding in accordance with the manner provided for in the applicable rules of civil procedure. If it does not do so, then the claim is waived.8
Order reversed.
Judge Kunselman joins the opinion.
Judge Murray files a dissenting opinion.
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 7/19/19
Notes
(a) Perfection of Lien. To perfect a lien, every claimant must:
(1) file a claim with the prothonotary as provided by this act within six (6) months after the completion of his work; and
(2) serve written notice of such filing upon the owner within one (1) month after filing, giving the court, term and number and date of filing of the claim. An affidavit of service of notice, or the acceptance of service, shall be filed within twenty (20) days after service setting forth the date and manner of service. Failure to serve such notice or to file the affidavit or acceptance of service within the times specified shall be sufficient ground for striking off the claim.
(b) Venue; property in more than one county. Where the improvement is located in more than one county, the claim may be filed in any one or more of said counties, but shall be effective only as to the part of the property in the county in which it has been filed.
(c) Manner of service. Service of the notice of filing of claim shall be made by an adult in the same manner as a writ of summons in assumpsit, or if service cannot be so made then by posting upon a conspicuous public part of the improvement.
