Tennessee Valley Authority v. Imperial Professional CoatingsTennessee Valley Authority v. Imperial Professional Coatings
MEMORANDUM
This is an action for judicial review of a decision by the Tennessee Valley Authority [TVA] Board of Contract Appeals [Board] rendered pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 607(g) (Supp.1984). The Board held that under the Changes Clause of a requirements contract between Imperial Professional Coatings [IPC] and TVA for paint to coat concrete at proposed nuclear power plants, IPC was entitled to an equitable adjustment 1 when TVA ceased to have requirements for the paint after it decided to cancel construction of the plants. The case is before the Court on cross-motions for summary judgment.
In this case, federal law governs the contract rights and obligations of TVA.
Tennessee Valley Authority v. U.S. Carbon Products, Inc.,
The facts of the case are agreed on by the parties, are accurately set forth in the Board’s decision, and will be only briefly recited. In 1978, pursuant to a bid, TVA awarded to IPC a contract to supply protective coating paint for proposed nuclear reactors. The estimated amount of the contract was $2,717,426.79, as reflecting the estimated amount of materials and surfaces to receive the protective coatings at the prices specified by IPC. In early 1982 TVA deferred construction of the nuclear plants. The decision to defer construction presumably was made on the basis that anticipated growth in the demand for electric power had been overestimated. (Letter to IPC from C.H. Strickland, August 6,
The parties do not dispute that this is a requirements contract or that TVA made a good-faith decision to cease construction of the nuclear power plants, thereby terminating its requirement for paint. The dispute centers on whether IPC is entitled to an equitable adjustment on the theory that TVA’s decision to cease construction was a change within the changes clause of the contract.
The pertinent contract provisions are set forth below:
“Quantity. This is a requirement contract for the materials which are required for painting the areas designated in the invitation to bid, Hartsville Nuclear Plants A and B, and Phipps Bend Nuclear Plant which is expected, but not guaranteed, to be completed about first quarter 1986. The area stated is TVA’s estimated area, and the quantity is the theoretical quantity for estimated areas for the term of this contract; however, TVA does not guarantee to purchase any maximum or minimum amount as TVA’s actual requirements may differ from the TVA estimate. Any quantity for which TVA has not requested delivery as of the date of completion of painting of the designated area of each plant is automatically cancelled.
“Changes. The Contracting Officer may at any time, by written order, and without notice to the sureties, make changes in the work within the general scope of the contract, including changes in the drawings and specifications. If such changes cause an increase or decrease in the amount of work under this contract or in the time necessary for its performance, an equitable adjustment will be made in the price or the time allowed for performance, or both, and the contract shall be modified in writing accordingly____
IPC’s position is that: (1) The requirements contract provides an objective measurable standard (the designated areas described and measured in the invitation to bid) for what is required, and specifically provides for equitable adjustment if that standard is changed, such as by a decision to cancel the plants.
(2) Neither party.foresaw or contemplated a cancellation of the project and the facts and circumstances surrounding the contract indicate the parties did not intend for IPC to assume the risk of cancellation.
TVA’s position is that: (1) Because this is a requirements contract it obligated itself to purchase whatever its requirements proved to be and that IPC assumed the risk of a decrease or cessation of requirements caused by TVA’s good-faith decision to cancel the plants.
(2) A decrease in requirements caused by cancellation of the plants is not a change compensable under the changes clause.
A requirements contract is “ ‘a contract in which the purchaser agrees to buy all of its needs of a specified material from a particular supplier, and the supplier agrees, in turn, to fill all of the purchaser’s needs during the period of the contract.’ ”
Mason v. United States,
With these general principles in mind, the Court will address IPC’s argument that although the contract at issue is a requirements contract for paint for nuclear plants and TVA’s requirement for the paint ceased with the good-faith cancellation of the plants, IPC is entitled under the contract to an equitable adjustment.
The essence of this dispute is whether IPC assumed the risk of a good-faith decision to cancel the nuclear plants or whether such a decision is a change within the meaning of the “changes” clause of the contract entitling IPC to equitable adjustment. The Court finds no merit in IPC’s contention that neither party intended that IPC assume the risk of a cancellation of the plant. The intent of the parties is to be determined from the face of the contract.
Brawley v. United States,
IPC appears to argue that the area designated to be painted imposes a limitation on the quantity of paint that TVA was required to order. The areas designated on the invitation to bid merely provided a standard by which TVA’s good-faith requirements could be measured. Had the contract not referred to an objective standard such as requirements or needs of the business but had left the quantity determinable at the personal whim of the contracting officer, the contract would have lacked mutuality. Note, at 1215.
2
By specifying an objective standard, TVA did not agree to purchase a specified amount.
See M. W. Kellog Co. v. Standard Steel Fabricating Co.,
IPC argues, however, that the “changes” clause protects it against a unilateral decision by TVA to cancel the plants. The Court finds this argument to be without merit. It has been held that a change in the government’s needs or requirements is not redressable under a “changes” clause.
Kleen-Rite Corporation,
81-
None of the cases cited by IPC supports its position. In
Ted J. Grimsrud,
1962 B.C.A. (CCH) U 3562 (October 31, 1962), the Board held that the seller’s right to recover under a requirements contract for snow removal service after the base closed depended solely on the termination clause. As previously noted, the contract at issue here contains no termination clause.
California Bus Lines,
76-1 B.C.A. (CCH) ¶ 11,655 (December 9, 1976), held that in a requirements contract for bus service, a route deletion caused by a matter extrane
IPC's argument that an equitable adjustment is proper by virtue of Section 2-306 of the Uniform Commercial Code is also without merit. Section 2-306(1) does not preclude good faith reductions that are highly disproportionate to normal prior requirements or stated estimates.
R.A. Weaver & Assoc., Inc. v. Asphalt Constr. Inc.,
In summary, the Court holds that a good-faith decision to cancel the nuclear plants for which paint was contracted is a risk assumed by the seller, IPC, and is not a change compensable under the “changes” clause. If IPC did not intend to assume the risk of cancellation, it could have protected itself by requiring in the contract a minimum clause or a termination clause. “If the contract did not express the true agreement, it was [IPC’s] folly to have signed it.”
Brawley v. United States,
For the foregoing reasons, defendant’s motion for summary judgment is denied and plaintiff’s motion for summary judgment is granted, and this case is dismissed.
Order Accordingly.
Notes
. The amount of damages, if any, was not before the Board and is not before this Court.
. IPC distinguishes between requirements contracts tied to a subjective standard, i.e., such as the “unbridled discretion" of the purchaser, and requirements contracts tied to an objective standard, such as the instant contract. IPC argues that the seminal case
Brawley v. U.S.,
. IPC argues that
M. W. Kellogg Co. v. Standard Steel Fabricating Co.,
. In
Fort Wayne Corrugated Paper Co. v. Anchor Hocking Glass Corporation,