Tennessee Gas Pipeline v. 104 Acres in Prov. Cty.Tennessee Gas Pipeline v. 104 Acres in Prov. Cty.
OPINION
On Mаy 18, 1989, the Federal Energy Regulatory Commission (FERC or Commission) granted Tennessee Gas Pipeline Company (Tennessee Gas) a Certificate of Public Convenience and Necessity authorizing construction of a 36 mile high-pressure natural gas pipeline extension from Worcester County in Massachusetts to a southern terminus in Cranston, Rhodе Island. The certificate was issued following a hearing before the Commission for which notice was given in accord with statute and FERC regulations. 1 After the certificate was issued, a rehearing was thereafter granted to some affected property owners and the certificate was amended on September 9, 1990 to аlter the southern end of the route to “reduce potential land use impact.” Tennessee Gas Pipeline Co., F.E.R.C. No. CP87-75-002. The Commission has yet to consider additional requests for rehearing filed by Consolidated Edison Company of New York, Inc., Tennessee Gas Pipeline Company, and Peoples Gas Light and Coke Company.
As amended, the certificate authorizes the construction of a 20-inch high-pressure natural gas pipeline from Tennessee Gas’ existing line in Massachusetts to Sherman Road, just over the Massachusetts/Rhode Island state line in Burrillville, Rhode Island. From Sherman Road, the certificate permits construction of a 16-inch pipeline to Cranston, Rhode Island. Over the entire route, the certificate authorizes acquisition of temporary easements 75 feet in width for use during construction and the retention of permanent rights of way and easements that are no more than 50 feet wide. The certificate also allows acquisition of a parcel of land at the southern end of the line for а metering facility. The certificate is conditioned on Tennessee Gas’ adherence to specific environmental mitigation measures before and during construction, including the obligation to obtain a permit before construction from the FERC’s Office of Pipeline and Producer Regulation after review of cultural rеsource surveys and mitigation plans.
Tennessee Gas now asks this Court, pursuant to Section 7(h) of the Natural Gas Act, 15 U.S.C. § 717f(h), to condemn rights of way, easements and land for the construction and maintenance of the pipeline. Tennessee Gas asserts, and Defendants do not contest, that Tennessee Gas was unable
The Defendants are various landowners whose land is the subject of this condemnation proceeding. In their challenge to Tennessee Gas’ claim of eminent domain, Defendants make two basic arguments: first, that Tennessee Gas’ FERC certificate is invalid and, second, that the extent of the condemnation exceeds the scope or otherwise violates the terms of the certificate.
Validity of the FERC Certificate
Defendants argue: (1) that FERC lacked authority to еnter an order issuing a certificate to Tennessee Gas because the affected property owners were not afforded personal notice and an opportunity to intervene in the administrative hearings; and (2) that the FERC certificate is not “final” because the Commission has before it applications for rehearing on matters relating to the certificate. For the reasons stated below, this Court lacks jurisdiction to determine these issues.
United States District Courts have a limited scope of review in condemnation proceedings brought under Section 7(h) of the Natural Gas Act. Disputes over the reasons and procedures for issuing certificates of public convenience and necessity must be brought to the Federal Energy Regulatory Commission for rehearing. 15 U.S.C. § 717r(a). Appeals may thereafter be brought to a United States Court of Appeals. 15 U.S.C. § 717r(b). The District Court’s role is to evaluate the scope of the certificate and to order condemnаtion of property as authorized in the certificate.
See Williams Natural Gas Co. v. Oklahoma City,
Defendants’ argument that the Commission improperly denied landowners notice and a hearing on the issue of the necessity of the condemnation is a collateral attack on the validity of the certificate. The issue is, therefore, not a matter which this Court may decide.
Tennessee Gas Transmission Co. v. Violet Trapping Co.,
Even if this Court could consider this issue, it is beyond doubt that Defendants’ argument lacks merit. To hold that the FERC certificate is invalid because landowners were not afforded personal notice of the hearings would require the Court to overlook a long line of decisions holding that landowners have no due process right to notice and a hearing in agency proceedings to determine the need for condemnation.
See Bragg v. Weaver,
Defendants’ contentions concerning the finality of the certificate are similarly without effect. Applications for rehearing by three public utility companies are presently before the Commission. However, The Natural Gas Act directs that an application for a rehearing shall not operate as a stay of the Commission’s order unless specifically ordered by the Commission or by a reviewing Court of Appeals. 15 U.S.C. § 717r(c);
see Ecee, Inc. v. Federal Power Comm’n,
Scope and Construction of the FERC Certificate
In their second basic argument, that the condemnation sought exceeds the scope or violates the terms of the FERC certificate, Defendants make five points. The defendants argue that Tennessee Gas’ petition is overbroad or otherwise violates the terms of the certificate because: (1) the easements sought are perpetual, (2) the easements sought allow the size of the pipeline to be changed at a future date, (3) the easements sought specifically allow the transport of substances other than natural gas, (4) condemnation pursuant to the certificate is premature because the Commission’s order and state and federal law require permits which have not yet been obtained, and (5) as to sоme of the affected landowners, the original FERC certificate did not authorize acquisition of their property due to the Commission’s failure to specify their property in its May 18, 1989 order.
Regarding the perpetual or permanent quality of the easements sought, the defendants argue that easements must be limited to the life оf the project. Defendants, however, offer absolutely no supporting law. Furthermore, the text of the statute belies this contention. The statute contemplates two types of condemnation: the condemnation of rights of way to construct, operate, and maintain pipelines and the condemnation of land necessary to locate surface equipment for the operation of pipelines. 15 U.S.C. § 717f(h). Because the statute contains no language to the contrary, it must be concluded that the rights of way may be easements in perpetuity. Furthermore, in its order issuing the certificate in this case, the Federal Energy Regulatory Cоmmission authorizes the condemnation of “permanent” rights of way with restrictions as set forth in its order. Plaintiff’s Exhibit C, 11J, at 17. This Court may not alter this authorization.
Defendants next object to the fact that Tennessee Gas seeks an easement giving it the right to “alter ... renew, remove, change the size of and replace a pipeline.” Unquestionably, Tennessee Gas’ easement includes the right to maintain and repair a pipeline. Accordingly, Tennessee Gas has the right to replace or repair the line as necessary to maintain it. At issue, however, is whether the easement can properly include replacement to increase the size of the line to accommodate future needs. Because Tennessee Gas has no authorization in the certificate from the Commission, it may not now do so.
Tennessee Gas acknowledges that the right of way and easement that it seeks exceeds the scope of the certificate (Plaintiff’s Memo at 35). The scоpe of a certificate of public convenience and necessity is to be construed narrowly against the party
Tennessee Gas cites only one case to support its argument for an easement that includes the right to hereafter expand the size of the pipeline. In
Panhandle Eastern Pipe Line Co. v. S.E.C.,
Defendant’s third objection is to the assertion that Tennessee Gas has an easement to transport “oil, gas, petroleum products or any other liquids, gases or substances which can be transported through a pipeline.” As defendants cogently note, the district court’s jurisdiction is limited to condemnation of property for purposеs authorized by the certificate. But the certificate only authorizes construction of a natural gas pipeline. Indeed, given the purposes of the Natural Gas Act, the Commission’s authority to authorize construction of a pipeline for other purposes is non-existent. Accordingly, the easement is restricted to a right of way for a natural gas pipeline and not a pipeline for any other purpose.
Defendant’s next argument is that condemnation is premature because Tennessee Gas has not obtained permits required by the FERC order and by federal and state law. According to the terms of the certificate, the FERC’s Directоr of the Office of Pipeline and Producer Regulation must approve the pipeline project after reviewing cultural resource surveys and mitigation plans and after consultation with Massachusetts and Rhode Island State Historic Preservation Officers. As Defendants note, this provision in the certificate reflects Fеderal policy as enacted in the National Historic Preservation Act. 16 U.S.C. § 470 et seq. Defendants also argue that Tennessee Gas has not obtained wetland permits required under the Clean Water Act and state enviornmental law. See 33 U.S.C. § 1344; R.I.Gen.Laws § 2-1-21. Defendants assert that because route changes may be necessary to acquirе these permits, condemnation should be deferred until the permits are obtained.
As noted above, this Court does not have jurisdiction to review the Commission’s decision to issue the certificate to Tennessee Gas and thereby to authorize condemnation of property to construct the pipeline. Disputes over the validity of the certificate based on FERC’s failure to require compliance with the Clean Water Act or state law must be brought to the Commission for rehearing. The inquiry, therefore, is whether the Commission’s order requires that condemnation must be deferred pending the grant of the permits.
The FERC order provides that prior to construction and operation of the pipeline Tennessee Gas must obtain written approv
As a last argument, Defendants Lawrence and Moreau object that the scope of the original FERC order did not authorize condemnation of their property. This argument, however, is rendered moot by the Commission’s September 19, 1990 modification of the certificated rоute. The route, as modified, bypasses the Lawrence property and bisects a different portion of the Moreau property than that described in the original complaint. Tennessee Gas has filed a second amended complaint which does not include the Lawrences as defendants and which revises the legal descriptions of properties affected by the change in the route. Condemnation is warranted along the route as modified by the September 19, 1990 order.
Accordingly, the condemnation of perpetual easements and land for the construction and maintenance of a natural gas pipeline as described in the FERC certificate issued on May 18, 1989, and as modified by the Commission’s September 19, 1990 order is granted. Plaintiff shall prepare and present a form of order in accord with this opinion.
Notes
. See 15 U.S.C. § 717f(d) ("notice ... shall be served upon such interested parties and in such manner as the Commission shall, by regulation, require."); 18 C.F.R. § 157.9 (1990) ("Notice of each application filed ... will be published in the Federal Register and copies of such notice mailed to states affected thereby.”).