148 Ky. 361 | Ky. Ct. App. | 1912
Opinion of the Court by
Affirming.
r In November, 1906, appellee, Charles B: Nordeman,entered into a contract with appellant, the' Tennant Land Company, whereby he agreed to purchase, and it agreed to sell him, lot 666 and a part of lot 665 in the Tennant Land Subdivision of the Dulaney farm, near 18th and Lexington streets, in the city of Louisville. The purchase price was $900, or $20 a front foot, payable in certain installments. The lot so purchased was located on Grand avenue. Appellee’s deposit book, which was the contract between the parties, contained the following stipulation:
“The improvements of Grand avenue, as advertised, are included in the price named in the contract.”
According to the advertisement, appellant agreed to construct a large sewer, sufficient to drain the entire tract, water and gas mains, with connections to the property line, concrete side-walks and curbing, and a modern asphalt roadway.
In February, 1907, Nordeman, by a similar contract,
As the contract between the parties provided for the improvements as. advertised, it was, .of course, proper to show what improvements were advertised. As it was advertised that a “modern asphalt roadway” would be constructed, and this was one of the improvements provided for in the contract, it was competent to show by parol evidence what the .parties contemplated, and this was done by showing what was generally understood in the community at that time as constituting a modern asphalt roadway. It appears from the evidence that when the contracts were entered'into, the only asphalt streets in Louisville were what is known as hot or sheet asphalt streets. The method of constructing such a street is as follows: A base of concrete about six inches deep is' first made. Then a binder of crushed
It appears that appellant attempted to comply with its contract by constructing a cold Kentucky rock asphalt street. This kind of a street is constructed with a macadam base. On top of the base is placed cold Kentucky rock asphalt, which is raked and rolled. The cold Kentucky rock asphalt differs in its ingredients from powdered asphalt in that it is made of powdered Kentucky rock, and does not contain the same amount of bitumen as the hot asphalt. All the evidence in the case shows that a cold Kentucky asphalt street is not a modern asphalt roadway, and at the time the contracts with appellee were entered into, no such thing as a cold Kentucky rock asphalt street was known. If also appears that the cold asphalt street is not as lasting as the hot asphalt' street. As the former chairman of the Board of Public Works puts it, “if you attempt to sweep the street, there will be nothing left.” The evidence leaves no doubt that the construction of the cold asphalt street was not a compliance with appellant’s undertaking.
It also appears from the evidence that the parties contemplated sewer connections for each lot, but appellant decided to put in one connection for each two lots. This, however, did not comply with the city sewer ordinances, and the city refused to1 permit connection to be used except for one lot. This left every other lot without sewer connection.
As the property in question was unimproved suburban property, it is manifest that the improvements contemplated by the contract were necessary to its proper enjoyment as a home, or to its profitable sale. That being true, they constituted an essential part of the consideration. As appellant utterly failed to comply with its contract with reference to such improvements, we conclude that the chancellor properly decreed a rescission.
But it is insisted that because the advertisement stated that the improvements were well under way and would be completed in the fall of 1906, and appellee bought one of the lots in the early part of 1907, and about two years and a half thereafter took deeds to both
It appears that in the month of May, 1911, after this action had been pending about ten months, appellant tendered .an amended answer and counterclaim, wherein it pleaded that the city of Louisville, pursuant to an ordinance passed by it, had entered into a contract with one Gosnell for the improvement of Grand avenue. That Gosnell was engaged in fulfilling his contract, and that .appellant had agreed and obligated itself in writing to pay Gosnell the apportionment warrant to be issued by the city of Louisville against the property of appellee, Nordeman. The court declined to permit this answer to be filed, but by order made it a part of the record. This action of the court was proper. Appellee had already elected to rescind, and had brought his suit for that purpose. An offer to perform, or a partial performance after suit was brought, did not constitute a defense. Fabrice v. Von der Brelie, 190 Ill., 460, 60 N. E., 835.
Judgment affirmed.