OPINION AND ORDER
Telenor Mobile Communications AS (“Telenor”), a Norwegian telecommunications company, and Storm LLC (“Storm”), a company organized under the laws of Ukraine, jointly own Kyivstar G.S.M. (“Kyivstar”), a Ukrainian telecommunica *336 tions venture. Telenor and Storm are engaged in a dispute over, inter alia, the validity and effect of a 2004 shareholders’ agreement (the “Shareholders Agreement” or “Agreement”) related to the corporate governance and management of Kyivstar. To resolve the dispute, Telenor invoked the arbitration provision of the Shareholders Agreement. The parties appeared before the arbitrators (“the arbitrators” or “the Tribunal”) at a series of hearings held during December 2006. On August 1, 2007, the Tribunal issued a unanimous final award (the “Final Award” or “Award”), granting various relief to Telenor, including conditional divestiture of Storm’s Ky-ivstar shares and an anti-suit injunction. The case is before this Court on (1) Tele-nor’s petition to confirm the arbitration award pursuant to 9 U.S.C. §§ 9 and 207, and (2) Storm’s cross-motion to vacate the Award. For the following reasons, Tele-nor’s petition will be granted, and Storm’s motion will be denied.
BACKGROUND
Many of the following facts have already been set forth in a prior decision by the Court.
See Storm LLC v. Telenor Mobile Comm’ns AS,
No. 06 Civ. 13157,
The 2004 Agreement
The 2004 Agreement is the product of a series of negotiations and transactions which arose from the desire of Alfa Telecommunications, a predecessor company of Altimo Holdings & Investment Limited (“Altimo”), to acquire a significant share in Kyivstar. (Zeballos Deck Ex. E ¶¶ 16, 21.) Ownership of Kyivstar had previously been divided up among a group of shareholders, including both Telenor and Storm. (Award at 3.) In 2002, Alfa purchased a majority interest in Storm, and used Storm in turn as the vehicle to acquire an interest in Kyivstar. (Id. 4.) Because Storm obtained over 40% of the Kyivstar shares' — which under Ukrainian law gave it substantial rights in corporate governance — Telenor negotiated an agreement obligating Storm not to exercise its rights in certain ways. (Zeballos Decl. Ex. E ¶ 22; see id. ¶ 17 (stating that Telenor currently owns approximately 56.5% and Storm owns approximately 43.5% of the Kyivstar shares).) 1 Wary of the Ukrainian legal system, Telenor also negotiated an arbitration clause (the “Arbitration Agreement”), which provided that “[a]ny and all disputes and controversies arising under, relating to or in connection with” the Shareholders Agreement would be resolved by a tribunal of three arbitrators in New York in accordance with the Arbitration Agreement and the United Nations Commission on International Trade Law (“UNCITRAL”) Arbitration Rules. (Agreement § 12.01.)
Telenor received several assurances that Storm’s purchase of the Kyivstar shares was authorized by Storm’s shareholders and management. During negotiations between the parties in 2002, Storm provided documents warranting that its general director, Valeriy Vladimirovich Nilov, who signed the agreement on its behalf, was legally authorized to do so. (Zeballos *337 Decl. Ex. E ¶ 41.) In addition, a resolution passed by unanimous consent of Storm’s shareholders on October 7, 2002, specifically authorized the general director to enter the Shareholders Agreement on behalf of Storm. (Id. ¶ 32.) Furthermore, upon execution of the final agreement on January 30, 2004, Storm and Telenor exchanged customary certificates that each signatory possessed full authority to sign on its behalf. (Id. ¶¶ 40, 41.) 2 Storm delivered to Telenor two identical documents entitled “Certificates of Incumbency and Authority,” one of which was signed by Yuri Tomanov, the Chairman of Storm, who certified that Nilov “is duly authorized to sign” the Agreement on behalf of Storm. (Id. ¶ 41.)
The Initiation of Arbitration and Ukrainian Court Proceedings
Telenor and Storm performed their respective obligations under the Agreement for over a year. During 2005, however, increasing friction developed between the parties, and Telenor now accuses Storm of violating the Shareholders Agreement in ways that effectively paralyze Kyivstar. Specifically, Telenor claims that Storm has violated the Shareholders Agreement by failing to (1) attend shareholder meetings, (2) appoint candidates for election to the Kyivstar board, (3) attend board meetings, and (4) participate in the management of Kyivstar, including enforcement and amendment of the Kyivstar Charter. (Award at 15; see Sills Decl. I, Ex. B ¶¶ 25-28.) Telenor also claims that the partial ownership of two competing Ukrainian telecommunications companies by Alfa, the direct parent of Altimo, and Russian Technologies, a subsidiary of Alfa, violates the Agreement’s non-compete clause. (Sills Decl. I, Ex. B ¶¶ 29-33.)
On February 7, 2006, Telenor sought redress for these alleged violations by invoking the arbitration clause. Telenor requested several forms of relief, including an order requiring Storm to comply with the Agreement’s requirements relating to shareholder and board meetings, appropriate relief against the breaches of the non-competition provision of the Agreement, a permanent injunction against court actions instituted in violation of the Agreement’s arbitration provisions, and an order requiring Storm to take steps to amend the Kyivstar Charter to conform both to the Shareholders Agreement and to a December 22, 2005, Order of the High Commercial Court of Ukraine. 3 (Id.) Telenor also requested an award of damages for Storm’s alleged breaches of the Agreement. (Id.)
Storm responded to the arbitration demand by appointing an arbitrator and participating in proceedings before the arbitrators. (Award at 18.) However, notwithstanding the fact that Storm was simultaneously participating in the arbitration proceedings, on April 14, 2006, legal proceedings were instituted in the Ukrainian Commercial Court. In the Ukrainian proceedings, Alpren, the 49.9% owner of Storm, sought a declaration of the invalidity of the Shareholders Agree *338 ment. (Zeballos Decl. Ex. B.) Telenor was not named as a defendant in the suit, and neither Telenor nor the arbitrators were advised of its pendency. Storm did not retain counsel or file written opposition to the action. (Sills Decl. I, Ex. B ¶ 38.) Instead, its general director, Va-dim Klymenko, appeared in person and registered oral opposition to Alpren’s demands, a method of proceeding that Storm contends is permissible, and not unusual, in Ukraine. (Zeballos Decl. Exs. C, F.)
Whether or not unusual under Ukrainian custom, the proceeding had a number of curious features. Although Klymenko, who acted for Storm in the matter, is not a lawyer, a resume submitted by him in connection with the arbitration notes that he is a Vice President of Altimo, the ultimate parent both of Storm and of Alpren, and that his responsibilities in that role include the management of “litigation[,] arbitration, representation and implementation of shareholders’ interests.” (Zeballos Decl. Ex. C.) The initial Ukrainian proceeding appears to have lasted all of twenty minutes (Award at 21), suggesting that Klymenko’s oral opposition was somewhat perfunctory. As a result, on April 25, 2006, the Ukrainian court declared the Shareholders Agreement invalid, finding that Nilov had “acted unlawfully and in excess of [his] powers” by executing the Agreement. (Zeballos Decl. Ex. B at 3.)
Storm appealed the result to the Ukrainian Appellate Commercial Court, again without submitting any substantial defense of its position. 4 Instead Storm only made a cursory argument that the Agreement was not examinable by the Ukrainian court because of the pending New York arbitration, and presented no evidence regarding the authority of Nilov to enter into the Agreement, nor any other factual submissions. (Award at 22.) Once again, Telenor was not present or notified of the hearing. (Id.; see Sills Decl. Ex. B ¶ 70 (“Telenor Mobile first learned of [the Ukrainian decisions] through an Altimo press release, issued after the Ukrainian appellate court issued its judgment .... ”).) Immediately following the hearing, on May 25, 2006, the appellate court affirmed the lower court’s decision against Storm. (Zeballos Decl. Ex. D.) In addition, although Storm made no argument regarding the severability of the arbitration clause to the appellate court, the appellate court broadened the lower court’s ruling by finding specifically that the Arbitration Agreement was invalid. (Id.)
On May 30, 2006, Storm filed its Statement of Defense to Telenor’s claims in the arbitration proceeding, taking issue with each of Telenor’s claims. Specifically, Storm argued that it did not violate the Agreement because (1) it was justified in not attending the shareholder and board meetings; (2) the Kyivstar Charter is vio-lative of Ukrainian law, and therefore, Telenor’s attempts to enforce and amend it were improper; (3) the non-compete clause of the Agreement is overbroad and unenforceable; and (4) it was not required to submit to arbitration because Telenor waived its right to arbitration by failing to raise the issue in the prior Ukrainian court proceedings — even though Telenor was not a party to, and had never been notified of, those proceedings. (Award at 16.) In the alternative, Storm argued that the Agreement itself was invalid “because it was entered into without the requisite authority and fails to comply with the registration *339 and execution requirements of Ukrainian law.” (Id. 16-17.)
Storm’s Motion to Dismiss and the Partial Final Award
Although Storm submitted a Statement of Defense and appointed an arbitrator to the Tribunal, on June 7, 2006, Storm moved to dismiss the arbitration on the alternative ground presented in its Statement of Defense, specifically, that the Tribunal had “no authority to decide the merits of Telenor’s claim because the Ukrainian courts had ruled ... that the January 30, 2004 Shareholders Agreement was ‘null and void in full, including the arbitration clause.’ ” (Id. 18-19.)
The Tribunal, composed of Kenneth R. Feinberg, Gregory B. Craig, and William R. Jentes, held a series of hearings on Storm’s motion to dismiss during the summer of 2006. On October 22, 2006, the arbitrators entered a “Partial Final Award” rejecting Storm’s jurisdictional argument. (Zeballos Decl. Ex. H.) As an initial matter, the Tribunal found that it had authority to determine its own jurisdiction.
(Id.
12-13, citing
Sphere Drake Ins. v. Clarendon Nat’l Ins.,
Further Attempts to Avoid Arbitration and the Preliminary Injunction
After losing its motion to dismiss before the Tribunal, Storm’s attempts to avoid arbitration proceeded in two fronts, in both the Ukrainian and American courts. First, on November 8, 2006, Storm obtained a “clarification” from the Ukrainian courts that broadened the scope of their initial rulings by specifically stating that the arbitration clause of the Shareholders Agreement was invalid, apparently in response to the arbitrators’ suggestion that the Ukrainian courts had not considered the possible severability of the Arbitration Agreement. (Zeballos Decl. Ex. K.) In addition, the November 8 ruling sought to cure Alpren’s failure to join Telenor as a party in the earlier proceedings by announcing that the court’s earlier order “shall apply and be binding also upon those entities that were not among the parties to the [original] court proceedings.” (Id.) The Ukrainian court also ruled that “[sjhould the parties and the arbitrators ... ignore the above circumstances and render an award on the dispute, such acts shall constitute a violation of the court decision.” (Id.) Storm again returned to the Tribunal, arguing that the November 8 ruling precluded it from appearing at the upcoming arbitration hearing and requesting postponement of that hearing, but the Tribunal denied the postponement and reaffirmed the December hearing dates. (Award at 28.)
Meanwhile, on November 13, 2006, Storm filed a petition in New York state *340 court to enjoin the arbitration from continuing, and seeking to vacate the Partial Final Award. Telenor removed the action to this Court, asserting subject matter jurisdiction under the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards, June 10,1958, 21 U.S.T. 2517, 830 U.N.T.S. 3 (the “New York Convention” or “Convention”). See 9 U.S.C. §§ 203, 205. On November 22, 2006, this Court denied preliminary relief, holding that the Court could not review an interlocutory order of an arbitral panel, and that to the extent Storm relied on the general equitable power of the Court, it was insufficiently likely to prevail on the merits, given the likely correctness of the arbitrators’ ruling, the apparently collusive nature of the Ukrainian litigation, and the lack of conflict between the arbitrators’ decision and the Ukrainian judgment, given that Storm had not been prohibited by the Ukrainian court from participating in the arbitration. (See 11/22/06 Tr. 19-38.)
Following this decision, the Ukrainian parties returned to court. This time, Al-pren once again threw its hat into the ring, and sued not Storm but Klymenko himself as general director of Storm. On December 1, 2006, again without notice to Tele-nor, Alpren secured an injunction from the Ukrainian court barring Telenor, Storm, and Klymenko from participating in any way in the arbitration — notwithstanding that Telenor had again not been notified of the action nor named as a party to it. (Award at 28; see, e.g., Sills Deck I, Ex. C at 1.) Telenor was not served in Ukraine with the order of the Ukrainian court; it obtained a copy of the judgment only via New York counsel for Storm in connection with the arbitration proceedings and this litigation. (Sills Decl. I, Ex. B ¶ 41.) Three days later, on December 4, 2006, Storm again sought to halt the arbitration on the basis of the December 1 injunction. (Id.) The Tribunal again denied the request, and ordered the hearing to proceed as scheduled. (Award at 28.)
After this ruling, Telenor sought relief from this Court, counterpetitioning to compel arbitration, and simultaneously seeking an anti-suit injunction against Storm, Alpren, and Altimo to prevent further litigation in the Ukraine.
Storm,
The Arbitration Hearings
Despite Storm’s attempts to indefinitely postpone the arbitration proceedings, the arbitration hearings took place on December 18-19, 2006. At the beginning of the hearing, Storm requested that the Tribunal “adjourn [the] hearing until such time as the Ukrainian Court action has run its course,” arguing once again that the Ukrainian action prohibited Storm from participating in the arbitration proceed *341 ings. (Award at 31.) When the Tribunal denied Storm’s application, counsel for Storm stated that, “[b]ecause of the December 1 ruling [in Ukraine], Storm feels that its hands are tied and that it cannot go forward on the merits.” (Id.) Storm then physically withdrew from the hearing room and did not participate in the hearing. (Id.)
At the hearing, Telenor presented two witnesses and submitted one new affidavit into evidence. The first witness was Jay Moland, Chief Financial Officer at Telenor and Deputy Chairman of the Board of Kyivstar. (Id.) Moland testified about the failure of Storm’s members of the Kyivstar Board of Directors to attend board meetings beginning on March 18, 2005, and continuing to the present. (Id.) He described the damage caused to Kyivstar that resulted from Storm’s boycott, and testified that Storm — up until the commencement of the arbitration — had never explained their Board members’ absence by claiming that the Shareholders Agreement was invalid. (Id. 31-32.) The second witness was Fredrik Lykke, former in-house counsel for Telenor. (Id. 32.) Lykke described the drafting and negotiation of the Agreement, the fact that there was no objection to identifying the law of the State of New York in the choice of law provision, and the importance to Telenor of having a non-compete provision included in the Agreement. (Id.)
In total, over the course of all of its hearings, the Tribunal heard or received testimony from eighteen different witnesses by live appearance and by affidavit. (Id.) It received hundreds of exhibits and thousands of pages of other documentary submissions. (Id.) Both Storm and Tele-nor also submitted lengthy pleadings, briefs, letters, and submissions of legal authorities in which they analyzed the facts, discussed the relevant law, and argued their positions. (Id.) The Tribunal also received post-hearing briefs from both parties, although only Telenor filed a post-hearing brief. (Id.) However, in response to an order directing further briefing on the choice of law issue, Storm participated in the final briefing of the case. (Id.; see Sills Decl. I, Exs. R & T.) On May 8, 2007, the Tribunal closed the hearings. (Sills Deck I, Ex. U.)
The Final Award
On August 1, 2007, the Tribunal issued a unanimous final award. First, the Tribunal reaffirmed the Partial Final Award, finding that “[n]othing that has ... transpired” since the Partial Final Award “has caused the Tribunal to change its earlier decisions.” (Award at 33.) Instead, the arbitrators found that the November 8 ruling of the Ukrainian court “actually convince[d]” them “that the [Ukrainian] Court ... failed to take into account several crucial factors bearing on a determination of the validity of the arbitration clause.” (Id. 34.) In addition, the Tribunal found that the persuasive force of the November 8 ruling is “further reduced by the fact that Telenor (again) did not receive notice of the proceeding before the [r]uling was rendered,” and by the limited evidentiary record submitted to the Ukrainian court in support of that ruling. (Id.) Specifically, the Tribunal noted that the Ukrainian court did not consider certain evidence of Storm’s “clear intent to have its disputes with Telenor resolved with arbitration, ... thus removing a key underpinning for the Alpren decisions.” (Id. 34-35.) The arbitrators also rejected the December 1 injunction as not binding on the Tribunal, and found that their proceedings were consistent not only with the anti-suit injunction entered by this Court, but with “the directives of the UNCITRAL Rules, the Parties’ intent as reflected in the Shareholders Agreement, and well-settled inter *342 national commercial arbitration practice.” (Id. 35; see, e.g., id. (“[T]he Tribunal points out that international commercial arbitration is a centerpiece of dispute resolution in today’s global economy .... For commercial arbitration to succeed in this international environment, an arbitral tribunal must be free to proceed in accordance with the arbitration rules selected by the Parties.”).)
Next, the Tribunal determined that New York law governed the arbitration, as “designated by the parties” in the arbitration clause. (Id. 36, quoting Agreement § 13.06.) The Tribunal rejected Storm’s attempts to apply Ukrainian law, finding that application of New York law was consistent both with the terms of the arbitration clause, and with New York, federal, and international law. (Award at 39-42.) In addition, the Tribunal again rejected Storm’s argument that it should “give conclusive effect to the decisions of the Ukrainian courts, regardless of what contrary results might be reached under New York law.” (Id. 41-42.) The Tribunal found that “the same reasons” that led the Tribunal to “decline[ ] to accept those ... decisions in connection with the issues of its jurisdiction,” including the collusive nature of the Ukrainian litigation and the fact that Telenor was not named as a party to that litigation or notified of it until after the appeal had been rendered, also led it “to reject those decisions in favor of the application of New York law to the merits of this controversy.” (Id. 42.)
Applying New York law, the Tribunal found that the 2004 Shareholders Agreement was validly executed and binding on the parties. In so finding, the Tribunal determined that Nilov had both actual and apparent authority to execute the 2004 Agreement. (Id. 45-53.) The Tribunal also found that, because Storm had intentionally created an appearance that Nilov had the authority to enter into the Agreement, and because Telenor relied on that representation to its detriment, Storm was estopped from challenging the validity of the Agreement. (Id. 53-54.)
Finally, the Tribunal found that Storm had breached, and continues to breach, the Agreement by “failing] to maintain its membership on the [Kyivstar] Board” (id. 56), and by impeding arbitration through “its steadfast efforts before this Tribunal to block the resolution on the merits of Telenor’s claims” in violation of the Agreement’s arbitration clause (id. 61). The Tribunal also found that Storm had breached the Agreement’s non-compete clause when Storm’s affiliates, Alfa and Russian Technologies, acquired an interest in competing Ukrainian telecommunications companies (id. 58-61). Furthermore, the Tribunal found that Storm had also breached the Arbitration Agreement by instituting litigation in Ukraine for the sole purpose of enjoining Ernst & Young from providing auditing services to Kyivstar (the “E & Y actions”), which Ernst & Young had agreed to provide pursuant to an agreement with Kyivstar (id. 62-64; see Zeballos Decl. Exs. T-V). 6
Because the Tribunal found that Telenor had failed to prove an amount of damages, the Tribunal did not award damages to Telenor as a result of Storm’s breach. (Award at 66.) However, based on its findings, the Tribunal ordered that Storm: (1) transfer certain of its Kyivstar shares to “newly-formed affiliated companies” that can nominate members for the Board of Directors; (2) “take such steps as are necessary to assure that its nominated *343 candidates are elected to the” Board of Directors; (3) “cause its duly authorized representatives to attend” all meetings of Kyivstar; and (4) “take such steps as are necessary” to amend the Kyivstar Charter in compliance with the December 22, 2005, Ukrainian court order. (Award at 66-67.) In addition, the Tribunal ordered that Storm must divest its Kyivstar shares within 120 days unless Storm, and any affiliated entities, divest their holdings in the competing telecommunications companies that exceed five percent. (Id.) Finally, the Tribunal ordered the entry of an anti-suit injunction against Storm, prohibiting Storm and “anyone acting in concert with it” from initiating any suit “relating to, or in connection with, any obligations described in the Shareholders Agreement,” as well as prohibiting the continued prosecution of “any existing litigations currently pending in the Ukraine,” including the E & Y actions. (Id. 67-68.)
On August 1, 2007, Telenor filed a petition to confirm the Tribunal’s Final Award with this Court. 7 Storm responded and cross-moved to vacate the award on August 24, 2007, and Telenor responded to Storm’s cross motion on August 30, 2007. Both motions were fully briefed as of September 12, 2007. 8
DISCUSSION
I. Legal Standards
In order to ensure that “the twin goals of arbitration, namely, settling disputes efficiently and avoiding long and expensive litigation” are met, arbitration awards are subject only to “very limited review.”
Folkways Music Publishers, Inc. v. Weiss,
Telenor’s application for enforcement of the arbitral award against Storm is governed by the New York Convention, which was enacted into law by Chapter 2 of the Federal Arbitration Act (the “FAA”), 9 U.S.C. §§ 201 et seq. Section 207 of the FAA provides that a party to an arbitration may apply for an order confirming an award made pursuant to the New York Convention “[wjithin three years after [the] arbitral award ... is made.” 9 U.S.C. § 207. Section 207 further provides that “the court shall confirm the award unless it finds one of the grounds for refusal or deferral of recognition or enforcement of the award specific in the” Convention. Id.
The New York Convention, in turn, sets out narrowly limited bases upon which the Court may decline to recognize and enforce an award. Under Article V, a district court may refuse to confirm a foreign arbitration award upon a showing that one or more of the following enumerated grounds exist:
(a) The parties to the agreement ... were, under the law applicable to them, under some incapacity, or the said agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made; or
(b) The party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or of the arbitration proceedings or was otherwise unable to present his case; or
(c)The award deals with a difference not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration, provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, that part of the award which contains decisions on matters submitted to arbitration may be recognized and enforced[.]
New York Convention art. V(l). Recognition and enforcement of an arbitral award may also be refused where “[t]he subject matter of the difference is not capable of settlement by arbitration under the law of that country,” or where “[t]he recognition or enforcement of the award would be contrary to the public policy of that country.” Id. art. V(2). These provisions of the Convention have been implemented by the FAA. See 9 U.S.C. § 207.
Storm invokes each of the aforementioned statutory grounds for vacatur in support of its motion to vacate the Final Award. In addition, Storm argues that the award was in “manifest disregard” of the applicable law, a non-statutory defense to enforcement.
See Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys “R” Us, Inc.,
II. The Standards Applied
A. Manifest Disregard
Storm’s principal argument in support of its motion to vacate is that the Tribunal acted in “manifest disregard” of controlling law when it issued the Final Award. Specifically, Storm argues that the arbitrators were required as a matter of law to *345 follow the prior decisions of the Ukrainian courts which found the Arbitration Agreement invalid. Alternatively, Storm argues that the Final Award should be vacated “as a result of the Tribunal’s manifest disregard of clear Second Circuit precedent providing for a jury trial on the existence of the Shareholders Agreement, including the agreement to arbitrate.” (Resp. Mem. 13.) Telenor argues that the Ukrainian decisions are not binding on the arbitrators, and that there is no factual dispute that would call for a jury trial here. The Court agrees.
Relying on an observation by the Supreme Court in
Wilko v. Swan,
1. The Ukrainian Decisions
Storm argues that the arbitrators were bound by law to follow the holdings of the Ukrainian courts, which found that “the Shareholders Agreement was null and void in full, including the arbitration clause, from the time of [its] execution.” (Resp. Mem. 5 (citation and internal quotation marks omitted).) According to Storm, both a trial court and an appellate court in Ukraine found the Shareholders Agreement, including the arbitration clause, to be invalid. (Resp. Mem. 7;
see
Zeballos Deck Ex. K at 1-2 (reiterating and clarifying the Ukrainian decisions “in light of the [Tribunal’s] Partial Final Award”).) Thus, Storm asserts that comity “militates against disregard” of the Ukrainian decisions (Resp. Mem. 9, citing
Sea Dragon, Inc. v. Gebr. Van Weelde Scheepvaartkantoor B.V.,
First, Storm argues that “the allegedly non-adversarial nature of a foreign matter does not provide a basis for ignoring an otherwise valid foreign decree.” (Resp. Mem. 11.) Storm is incorrect. Although it is “well established that a state may not require a person to do an act in another state that is prohibited by the law of that state,”
Motorola Credit Corp. v. Uzan,
Indeed, far from exhibiting manifest disregard for established legal authority, by rejecting the Ukrainian decisions as nonbinding, the Tribunal followed the longstanding legal rule against “friendly” litigation: “A judgment entered under such circumstances, and for such purposes, is a mere form .... A judgment in form, thus procured, in the eye of the law is no judgment of the court. It is a nullity.”
Lord v. Veazie,
Next, Storm argues that, even if collusion is an adequate basis for setting aside a foreign judgment, “[t]here is no evidence that Storm cooperated with Alpren in the Ukrainian litigation,” and therefore the Ukrainian proceedings could not be characterized as collusive. (Resp. Mem. 11.) Storm made an identical argument to this Court twice before, in support of its November 2006 preliminary judgment motion, and in opposition to Telenor’s December 2006 motion for an anti-suit injunction. The Court rejected that argument on both occasions. The definition of collusion has not changed during the intervening months. Despite Storm’s repeated protestations to the contrary, the Ukrainian decisions are just as collusive now as they were then. It is unnecessary to recite again the factual basis for the collusiveness determination. The Final Award contains a detailed discussion of the factual basis for that determination (Award at 33-36), and the Court’s own consideration of the same issue in its prior rulings resulted in a conclusion identical to the Tribunal’s findings.
See
Storm also argues that the Ukrainian litigation can not be characterized as having the purpose of “undermining federal judgments” because that litigation was instituted before the arbitration proceedings were complete, and because Storm did not “conceal” the Ukrainian judgments from the Tribunal. (Resp. Reply 2-3.) Thus, Storm argues that this case is unlike
Uzan,
in which the Turkish judgments that purported to enjoin the parties to the arbitration proceeding from complying with “imminent orders by the district court” were obtained in secret only after the arbitral award had been rendered and the arbitration had been completed.
(Id.
3.)
See
In addition, although Storm did not “conceal” the Ukrainian decisions from the Tribunal (Resp. Reply 3), it is undisputed that Telenor did not receive notice of the Ukrainian litigation until after the Ukrainian courts had rendered their decisions. Storm argues that Telenor could have intervened during the appellate proceedings; however, as the Tribunal found, “[p]ost-judgment intervention” is not a substitute for being a named adversary in the underlying litigation, as such intervention results in “delay” and “prejudice to existing parties,” and is not consistent “with the fair administration of justice.” (Award at 43, citing
United States v. Yonkers Bd. of Educ.,
The remainder of Storm’s arguments rely on inapposite and unpersuasive case law. For example, Storm argues that “[t]he courts have long held that a final judgment obtained through sound procedures in a foreign country is generally conclusive as to its merits unless” the foreign court lacked jurisdiction to hear the dispute, the judgment was “fraudulently obtained,” or “enforcement of the judgment would offend the public policy of the state in which enforcement is sought.”
Ackermann v. Levine,
Storm devotes a significant portion of its brief to a discussion of
Sea Dragon,
Storm’s application of
Sea Dragon
is unavailing. First,
Sea Dragon
is not controlling law, as it does not bind this Court, was decided over two decades ago, and has not been relied upon for the relevant proposition since it was decided.
See Chemical Overseas Holdings, Inc. v. Republica Oriental Del Uruguay,
No. 05 Civ. 260,
Storm also argues that the Court should follow
Sea Dragon’s,
lead and find that “the purportedly non-adversarial nature of a foreign proceeding does
not
provide a basis for disregarding the entire judgment.” (Resp. Reply 4 (emphasis in original).) Storm argues that the respondent in
Sea Dragon
voluntarily participated in the Dutch proceedings, just as Storm participated in the Ukrainian proceedings, but in that case, participation in the foreign proceedings was not found to be a basis for
*349
setting aside the foreign judgment. Insofar as
Sea Dragon
can be characterized as so finding, that finding has been nullified by the Circuit in a series of decisions, including
Uzan
and
Karaha Bodas.
Moreover, even if the Dutch proceedings in
Sea Dragon
could be characterized as “non-adversarial,” unlike the Ukrainian proceedings, the Dutch proceedings were not found to be vexatious, collusive, or taken with the purpose of undermining the arbitration proceedings. Instead, those proceedings were brought by a third party that was not in any way connected to the arbitration proceeding, and that was acting to protect its own interests as a separate creditor of the respondent.
See
Finally, Storm attempts to impugn the Tribunal’s reasoning by arguing that it was contradictory for the Tribunal to state that it was not criticizing “the integrity of [the Ukrainian] courts or their decisions,” and that it had “found no evidence of any impropriety or violations of any Ukrainian procedures” (Resp. Mem. 9-10), but nevertheless to find that the decisions should not be given conclusive effect. By attempting to shift focus from the parties’ misdeeds to the validity of the Ukrainian legal system, Storm is attempting a legal bait and switch, relying on what may be an otherwise fair legal system to exonerate them for their unfair abuse of that system. The Tribunal’s determination that the Ukrainian litigation was collusive does not impugn the Ukrainian legal system itself; instead, it only impugns the way in which the parties used — and abused — that system. There were no “improprieties] or violation[s]” of Ukrainian procedure by the Ukrainian courts because Storm and its cohorts made it virtually impossible for the Ukrainian courts to adequately consider the issues before it, as the collusive nature of the litigation left those courts with a woefully inadequate, one-sided record. In contrast, the arbitrators were privy to a complete record on the issues, and were thereby able to identify the collusive nature of the Ukrainian litigation. Although it is impossible to know whether the outcome of the Ukrainian litigation would have changed if the parties had not engaged in collusion, the resulting uncertainty is certainly sufficient to strip those decisions of any conclusive effect. 9
Accordingly, the arbitrators were not bound to follow the Ukrainian decisions, and their rejection of those decisions as non-binding did not constitute manifest disregard of the law.
2. Jury Trial
Next, Storm asserts that the Tribunal acted in manifest disregard of the law by allegedly depriving Storm of a jury trial on the validity of the arbitration agreement, as required by
Sphere Drake,
In the Second Circuit, a party challenging the existence or formation of an agreement from which an arbitration proceeding derives is entitled to have those issues decided in court, rather than by the arbi-tral tribunal, if the party (1) presents “some evidence” in support of its claim; and (2) has unequivocally denied that an agreement was made.
Sphere Drake,
a. Independent Determination
Consideration of Storm’s argument requires two steps. First,-the Court must decide whether the Tribunal’s arbitrability determination is entitled to deference, or whether the Court must make an independent determination on that issue. Telenor argues that Storm cannot invoke its right to a jury trial because it specifically agreed in the Arbitration Agreement that the arbitrators would rule on their own jurisdiction, and the Court must defer to that agreement. (Pet. Mem. 15.) Telenor asserts that, by incorporating the UNCI-TRAL Arbitration Rules in the arbitration agreement, which provide that “[t]he Arbi-tral tribunal shall have the power to rule on objections that it has no jurisdiction, including any objections with respect to the existence or validity of the arbitration clause or the separate arbitration agreement,” Storm agreed to give the Tribunal, rather than a court, “the authority to determine whether an arbitration agreement was reached, and whether the arbitration is the correct forum to hear any particular dispute.” (Pet. Mem. 16, citing UNCI-TRAL Arb. R. Art. 21(1).) According to Telenor, when parties incorporate such language in an arbitration clause, courts have “consistently found that this serves as ‘clear and unmistakable evidence of the parties’ intent to delegate such issues to an arbitrator.’ ”
(Id.,
quoting
Contec Corp. v. Remote Solution Co., Ltd.,
The Court disagrees. Telenor primarily relies on
Contec Corp.,
Moreover, there is a strong presumption in favor of judicial rather than arbitral resolution on the issue of arbitrability.
Shaw Group,
Nor is the Court persuaded to defer to the Tribunal’s findings on the arbi-trability of the dispute by Storm’s prior concessions that the Tribunal had jurisdiction to determine its own jurisdiction.
(See
Resp. Mem. 16 n. 2, citing Sills Aff. II, Ex. 202 at 12,
&
Ex. 188 at 21-22.) Storm’s concession that the Tribunal had jurisdiction to determine its own jurisdiction, under the doctrine of “competence-competence,” which in turn is the basis for the UNCITRAL rules (Resp. Reply 6;
see
11/15/06 Tr. 11, 14), did not restrict its ability to later request that this Court independently review the Tribunal’s arbi-trability decision. Instead, under the competence-competence doctrine, “the arbitrators’ jurisdictional decision is subject to judicial review at any time before, after, or during arbitration proceedings.”
China Minmetals,
Furthermore, Telenor’s insistence that Storm waived its right to a jury trial by conceding jurisdiction over the arbitrability issue to the Tribunal is counterbalanced by Storm’s repeated insistence to the arbitrators that they “did
not
want the arbitrators to have binding authority” over the issue of arbitrability.
First Options,
b. Application of Sphere Drake Standard
The Court must therefore consider independently Storm’s argument that it satisfied the
Sphere Drake
standard. To be entitled to a jury trial, Storm must show (1) that it challenged the validity of the arbitration agreement,
see Buckeye Check Cashing,
Storm has not satisfied either prong of the Sphere Drake standard. First, although Storm contends that it “consistently argued throughout the arbitral proceedings that the Shareholders Agreement is void because its signatory to the agreement lacked the requisite authority for its execution (including the authority to agree to a severable arbitration clause)” (Resp. Mem. 14), Storm has presented no evidence supporting its argument. Instead, the record shows that Storm conceded that there was no evidence that Nilov lacked authority to enter into the arbitration agreement insofar as that clause was sev-erable from the Agreement as a whole. *353 (9/5/06 Tr. 98 (“I have no indication that Mr. Nilov lacked authority under the charter to enter into a separate arbitration agreement.”); see Letter from Robert L. Sills to the Court, dated Sept. 18, 2007, at 2 (alleging that Storm specifically disavowed this argument during the arbitration proceeding), citing 9/5/06 Tr. 97-99.) Thus, Storm’s current objections to Nilov’s authority are insufficient to satisfy the Sphere Drake and Buckeye standard.
Second, even assuming arguendo that Storm contested the validity of the arbitration agreement during arbitration, Storm has not presented sufficient evidence to warrant a jury trial on that issue. In its motion to vacate the Final Award, Storm merely states in a footnote, in the most conclusory manner possible, that “[tjhere can be no doubt that Storm would have satisfied the
Sphere Drake
standard.” (Resp. Mem. 16 n. 12.) But, as previously noted,
Sphere Drake
makes it clear that “it is not enough for [a party] to make allegations” that an arbitration clause is invalid; instead, the party “must also produce some evidence substantiating its claim.”
Nevertheless, because the Court must make an independent determination on the issue of arbitrability, it must conduct its own analysis of whether Storm actually agreed to arbitrate the dispute. It is undisputed that the parties extensively negotiated the Arbitration Agreement, and agreed both that New York law controlled their relationship and that the parties would arbitrate any dispute in accordance with New York law. Under New York law, the agreement to arbitrate is severa-ble,
see Weinrott v. Carp,
The record does not support Storm’s argument that Nilov lacked either actual or apparent authority to enter into the Arbitration Agreement. Under New York law, actual authority is “the authority that a principal invests in its agent, which, upon its exercise, binds the principal.”
Seetransport Wiking Trader Schiffarhtsgesellschaft MBH & Co. Kommanditgesellschaft v. Rep. of Romania,
Nilov clearly had actual authority to bind the company to arbitrate a contractual dispute. Storm does not dispute that Nilov was given actual authority by the shareholders to sign the 2002 version of the Shareholders Agreement. 10 Instead, Storm’s only argument is that Nilov did not have the actual authority to sign the revised Agreement in 2004 without formal approval by the shareholders. But it is uncontested that the 2002 version of the Agreement included the Arbitration Agreement. As the Arbitration Agreement is severable from the rest of the Agreement, when Nilov signed the 2002 version of the Shareholders Agreement— which, as conceded by Storm, he did with actual authority—he bound Storm to the arbitration clause within the Agreement. Thus, Storm’s argument that Nilov lacked authority to execute the 2004 version of the Agreement, which contained the exact same arbitration clause as the 2002 version, is irrelevant; if Nilov had the authority to enter into the arbitration agreement in 2002, then he also had the same authority in 2004, regardless of whether he also had the authority to bind Storm to the Shareholders Agreement in 2004. 11
Nilov in any event had apparent authority to bind Storm to the arbitration agreement. Under New York law, apparent authority is created “when a principal places an agent in a position where it appears that the agent has certain powers which he may or may not possess.”
Masuda v. Kawasaki Dockyard Co.,
In this case, Storm, by its words and conduct, communicated to Telenor that Nilov was authorized to sign the arbitration agreement, and Telenor reasonably relied upon that information. For example, the resolution adopted by the shareholders’ meeting held in 2002 explicitly authorized Nilov, by name, to “take or cause any and all other actions as are required or desirable in connection with this Resolution and the above-referenced documents,” including, by association, the arbitration agreement. (Sills Decl. II, Ex. 264.) Moreover, Storm communicated to Telenor that a written polling and live vote of Storm’s participants had been taken in 2002 approving the 2002 Shareholders Agreement, again, including the arbitration clause.
(Id.)
The clear purpose of these actions was to induce Telenor to enter into the Agreement at closing.
(See
Zeballos Decl. Ex. E ¶¶ 32, 34 (stating that, “[s]hortly before” the original closing
*355
date for the Agreement, Storm specifically communicated to Telenor the participants’ “unanimous” approval of the Agreement).) There is also no dispute that Telenor relied on all of these actions, made by Storm’s directors and shareholders, when it entered into the Arbitration Agreement. Such reliance was “entirely reasonable,”
Hallock,
Once it is determined that Nilov had authority to bind Storm to the Arbitration Agreement, Storm’s remaining arguments against arbitrability of the dispute are easily disposed of. For example, Storm argues that the Ukrainian decisions that declared the Shareholders Agreement to be null and void are alone sufficient evidence that the Arbitration Agreement is invalid to warrant a jury trial. This argument fails for at least three reasons. First, the Ukrainian decrees are not evidence of anything. They raise at most questions of law for a court, not questions of fact for a jury. The Ukraine judgments are based on Ukrainian law. But since Ukrainian law is not controlling here, the only potential questions in this case concern the existence of Nilov’s actual or apparent authority, as defined by New York law, to enter an arbitration agreement. The Ukrainian decisions neither constitute nor imply the existence of any evidence on that question.
Second, even if court decisions applying inapplicable law could be taken as evidence of something, the collusive nature of the Ukrainian decisions render them neither binding on this Court nor persuasive authority, and defeat any inference that might otherwise be derived from the existence or content of those decisions.
Third, even if the decisions had not been collusively obtained, the Ukrainian courts never considered the severability issue, but instead declared the entire Shareholders Agreement null and void. Storm argues that the subsequent Clarification Order gave “meaningful consideration” to the severability issue (Resp. Mem. 10 n. 8), but that order shows no such consideration. Instead of considering Nilov’s authority to enter into the arbitration agreement as a separate and distinct issue from his authority to enter into the Shareholders Agreement, the clarifying court merely voided the arbitration clause as part and parcel of the Agreement in toto: “[Sjince the Shareholders Agreement violated the public order of Ukraine and since the representative of one of the parties to the agreement ... was not authorized to execute [it] and the arbitration clause contained therein as its integral part, the arbitration agreement ... is also void/invalid.” (Zeballos Decl. Ex. K at 2 (emphasis added).) Thus, the Ukrainian decisions could be, at most, evidence of the Shareholders Agreement’s invalidity, and not of the invalidity of the separate arbitration clause. Such “evidence” is insufficient to satisfy Sphere Drake.
Similarly, the affidavit from Vadim Klymenko, the General Director of Storm, is insufficient to warrant a jury trial on the arbitrability issue, and actually argues in favor of Telenor’s position. Klymenko testified, not that Nilov lacked authority to enter into the Arbitration Agreement, but that Nilov lacked authority to enter into the Shareholders Agreement as a whole. (Zeballos Decl. Ex. C ¶ 8.) Indeed, according to Klymenko, Storm defended itself in the Ukrainian proceedings by arguing that the Arbitration Agreement was valid. (Id. ¶ 6.) Thus, it is unsurprising that Storm is unable to point to any evidence in the record that it ever argued against the va *356 lidity of the Arbitration Agreement, as Storm argued the exact opposite to the Ukrainian court.
Finally, Storm argues that it was not permitted to fully present its Sphere Drake defense during the arbitration because the Ukrainian decisions foreclosed it from participating in the arbitration proceedings. Thus, Storm argues that “[t]he record that was before the Tribunal is not adequate for the Court’s independent assessment,” and that the lack of discovery on the issue provides an “independent basis for vacatur of the Final Award.” (Resp. Reply 7 n. 2.) This argument is patently disingenuous. First, Storm presented a vigorous defense to the Tribunal; notwithstanding its physical absence from the December 2006 hearings. (Award at 32.) Moreover, the Tribunal gave Storm every possible opportunity to present its case, notwithstanding its refusal to appear (id.), an opportunity Telenor was not provided by the Ukrainian courts. Finally, for Storm to boldly request that the Court set aside the Award because it did not have a full opportunity to participate in the arbitration proceedings, while simultaneously arguing that the Ukrainian proceedings — during which its own vexatious tactics resulted in Telenor having no opportunity to defend itself at all — should bind Telenor, is an exercise in complete and total contradiction.
Accordingly, Storm is not entitled to a jury trial on the arbitrability of the dispute, and the motion to vacate the Award on that ground is denied.
B. Statutory Grounds
Next, Storm argues that several of the New York Convention’s statutory grounds for vacatur apply here. Storm argues primarily that the Final Award violates New York’s public policy, and that the relief granted exceeded the scope of the Tribunal’s powers. Telenor argues that enforcement of the Award would serve, and not undermine, New York’s public policy, and that the arbitrators acted within the scope of the powers bestowed upon them by the Shareholders Agreement in ordering the disputed relief.
1. Public Policy
First, Storm asserts that “an enforcement of the Final Award would force Storm to violate the Ukrainian Judgments,” which in turn would be contrary to New York’s “well accepted and deep-rooted public policy” against the enforcement of arbitration awards that compel a violation of law. (Resp. Reply at 4-5, citing
Sea Dragon,
The public policy exception in Article V(2)(b) of the Convention is very narrow, and applies only where enforcement of the award would violate “the most basic notions of morality and justice” of the forum where enforcement is sought.
Europcar Italia S.p.A v. Maiellano Tours, Inc.,
Storm argues that, unlike the Tribunal, the Ukrainian courts found that “the Agreement ... is null and void.” (Resp. Mem. 13.) Thus, Storm argues that the Tribunal’s decision directly conflicts with Ukrainian law, and therefore, that it cannot comply with the Final Award — which is based on Storm’s non-compliance with the Agreement — without violating that law. Storm also argues that the conditional divestiture order, which is based on Storm’s violation of the non-compete clause, is unenforceable in Ukraine because such clauses are specifically prohibited by Ukrainian antimonopoly law. (See Khomyak Decl. ¶¶ 6, 11.) Storm contends that these conflicting directives violate New York’s public policy against enforcement of arbitral awards that compel a violation of law.
First, it is unclear whether the Final Award even conflicts with Ukranian law. The Ukrainian courts only held that the Shareholders Agreement was null and void; the Ukrainian courts never ordered Storm to take any specific actions in the future that would conflict with any directives in the Final Award. For example, although Storm alleges that the non-compete clause is unenforceable under Ukrainian law, the Ukrainian courts never discussed the possibility that the non-compete clause violated Ukrainian law, even though those courts were given several opportunities during the course of the Ukrainian litigation to address that issue. Similarly, the Ukrainian courts did not prohibit Storm from ceasing the E
&
Y actions, or taking any other specific action with respect to the Agreement. Although the Final Award and the Ukrainian decisions involve overlapping issues, the relevant inquiry is not whether the issues in both proceedings overlap, or whether the reasoning of the different adjudications was inconsistent, but whether the resulting decisions are “directly contrary” in such a way as to make compliance with one
necessarily
a violation of the other.
See Chemical Overseas,
In any event, even if there is a direct conflict between Ukranian law and the Final Award, New York’s public policy does not call for vacatur here. First, it is unclear whether an established public policy against enforcement of arbitral awards that compel a violation of foreign law even exists in New York. Storm cites no authoritative New York precedent, relying principally on only two district court cases from the previous two decades that cite such a policy.
See Sea Dragon,
Moreover, even if such a policy exists, it is outweighed in this ease by the public policy in favor of encouraging arbitration and enforcing arbitration awards. New York courts have explicitly cautioned against allowing a party to “escape from [its contract] obligation on the pretext of public policy.”
Miller v. Continental Ins. Co.,
Storm principally relies on
Sea Dragon
in support of its argument for vacatur on public policy grounds. (Pet. Mem. 12-13.) However, as discussed above,
Sea Dragon,
in which the foreign judgment was secured in compliance with American due process standards,
American Construction Machinery & Equipment Corp. Ltd. v. Mechanised Construction of Pakistan Ltd.,
Accordingly, enforcement of the arbitral award would not violate “the most basic notions of morality and justice” in New York,
Europcar,
2. Scope of Arbitral Award
Storm also argues that the Tribunal acted improperly by ordering the conditional divestiture of Storm’s shares in Kyivstar, *359 and by entering an anti-suit injunction against Storm and its affiliates, thereby enjoining the E & Y actions currently pending in Ukraine. Telenor argues that the Tribunal “acted well within the powers conferred upon it by the Shareholders Agreement and governing law.” (Pet. Mem. 18.) Telenor is correct.
“Arbitrators ... enjoy broad discretion to create remedies unless the parties’ agreement specifically limits this power.”
Arbitration Between Millicom Int’l V N.V. v. Motorola, Inc. & Proempres Panama, S.A.,
No. 01 Civ. 2668,
Here, far from limiting the remedial powers of the Tribunal, the Arbitration Agreement provides the arbitrators with “the power to grant any remedy or relief that they deem just and equitable.” (Agreement § 12.01(a)(v).) Specifically, the Arbitration Agreement permits the arbitrators to order “specific performance, and including, but not limited to injunctive relief, whether interim or final.” (Id.) That power is granted with regard to “[a]ny and all disputes and controversies arising under, relating to or in connection with” the Shareholders Agreement. (Id. § 12.01(a).)
a. Conditional Divestiture
Storm contends that the conditional divestiture order falls outside the arbitrators’ powers. Pursuant to that order, Storm must divest its shares in Kyivs-tar, unless its affiliates — Alfa and Russian Technologies — divest their shares in two competing Ukrainian telecommunications companies, Turkcell Iletisim Hizmetleri A.S. (“Turkcell”) and Ukrainian High Technologies (“UHT”), within 120 days. (Award at 67.) According to Storm, Tele-nor sought only money damages in the arbitration, “and included in its submission only a boilerplate, cursory request referring to equitable relief.” (Resp. Mem. 19.) Moreover, Storm argues that, even if Tele-nor did seek equitable relief, only money damages are permitted under the Agreement as a remedy for breach of the non-compete clause. Finally, Storm argues that only its conduct, and not that of Alfa and Russian Technologies, could violate the non-compete clause of the Shareholders Agreement, and therefore that the Tribunal was not permitted to bind those companies to the conditional divestiture order. Storm’s arguments are meritless.
First, Storm is incorrect that Telenor sought only money damages in the arbitration. In its Proposed Findings of Fact and Conclusions of Law, Telenor requested an award “declaring that the non-competition clause has been violated, and that the violation will be cured if Altimo’s interests in Turkcell and UHT are divested within a reasonable time to be fixed by the Panel.” (Sills Decl. I, Ex. B at 68.) Thus, Telenor specifically requested essentially the relief *360 granted by the Tribunal, and Storm had a full and fair opportunity to argue against such relief during the arbitration proceedings.
Second, even if Telenor had not specifically requested equitable relief, the Tribunal was granted the power to order such relief by the broad language of the Arbitration Agreement, which provided the arbitrators with the authority to order any remedy that they found to be “just and equitable.” (Agreement § 12.01(a)(v).) Such broad language has been consistently upheld as valid and binding on parties by courts in this Circuit.
See, e.g., Millicom,
Storm also argues that the Award should be vacated because the alleged “draconian remedy” imposed by the Tribunal violates the Agreement’s right of first refusal clause. (Resp. Mem. 19.) Specifically, Storm alleges that “[ojrdering Storm to sell its shares to a third party is directly contrary to the parties’ intent in entering into the Shareholders Agreement because it would give Telenor an opportunity to take complete control of the company,” which Storm argues is in violation of the right of first refusal contained in the Agreement. (Id.) Therefore, Storm argues that the “only available remedy for any breach [of the non-compete clause] was money damages.” (Resp. Reply 9.)
Storm’s argument is unavailing. Even if the divestiture order results in Telenor’s complete control of Kyivstar, that result does not conflict with the Agreement’s right of first refusal clause. The right of first refusal clause merely provides any shareholder — including both Storm and Telenor — with the “first right and option to elect to purchase” the offered shares prior to their sale to a third party. (Agreement § 4.05.) The right of first refusal clause does not otherwise impose any restrictions on who may ultimately purchase those shares. Indeed, although Storm claims that the right of first refusal clause implicitly indicates that the parties did not “contemplatef ]” the possibility that Telenor or Storm might take “complete control” over Kyivstar (Resp. Mem. 19), the language of the clause itself directly contradicts Storm’s argument — according to the clause, “[i]f Telenor Mobile determines to Transfer all or any portion of its [Kyivstar shares] ... Storm shall be entitled to assign all or a portion of its right to purchase such [shares] ... to Alfa.” (Agreement § 4.05(f) (emphasis added).) Thus, the right of first refusal clause specifically considers the possibility that Tele-nor might sell all of its shares at some future time, and provides Storm with the option to transfer its right of first refusal to Alfa under such circumstances. If the intention behind the right of first refusal clause was to prevent complete ownership by either party, the Agreement would not have included a contingency that contemplates exactly that scenario.
More importantly, under the terms of the conditional divestiture order, Storm is not required to sell its Kyivstar shares at all. Instead, the alternative form of relief means that Storm will not have to sell its shares, as long as Alfa and Russian Technologies divest their interests in Turkcell and UHT. Thus, the right of first refusal clause is not even necessarily implicated by the conditional divestiture order.
In any event, even if the conditional divestiture order did conflict with other provisions of the Agreement, the Tribunal
*361
was fully authorized by the Arbitration Agreement to order whatever remedy it deemed “just and equitable” (Agreement § 12.01(a)(v)), regardless of whether the remedy imposed is consistent with the other terms of the Shareholders Agreement. While an arbitrator’s award must “draw its essence” from the parties’ agreement, and may not simply reflect the arbitrator’s “own brand of justice,”
Local 1199, Drug. Hosp. & Health Care Employees Union v. Brooks Drug Co.,
Storm’s alternative argument is similarly unpersuasive. Storm argues that the conditional divestiture order is “an attempt by the Tribunal to force Alfa and Russian Technologies, two non-signatories,” to divest their shares in Turkcell and UHT, and “thus effectively be bound by the Final Award.” (Resp. Mem. 19.) Specifically, Storm argues that because UHT is partially owned by Russian Technologies, a subsidiary of Alfa, and because Turkcell is partially owned by Alfa itself, Storm’s compliance with the conditional divestiture order is contingent, not on its own conduct, but on the conduct of Alfa and Russian Technologies. However, Storm misinterprets the basis for the conditional divestiture order; Alfa and Russian Technologies are “bound” to comply with the order, to the extent they can be said to be bound at all, not as non-signatories to the Agreement, but as affiliates of Storm.
The non-compete clause specifically provides that “no Shareholder or any of its Affiliates will, without the prior written consent of the Company and the other Shareholders, ... engage in Business in any region in Ukraine [or] ... own, or control, directly or indirectly, more than five percent (5%) of the voting capital stock” in a competing business. (Agreement § 6.02 (emphasis added).) Section 1.01 of the Agreement further defines “Affiliate” as “any other Person which directly or indirectly controls, or is under common control with, or is controlled by, such Person.” It is undisputed that UHT, a provider of “WiMax” wireless telecommunications services that compete with Kyivstar in Ukraine, 12 is partially owned by Russian Technologies, which in turn is a subsidiary *362 of Alfa, and it is undisputed that Alfa itself maintains partial ownership of Turkcell, another competing telecommunications provider in Ukraine. Furthermore, it is undisputed that Alfa was at the time of the execution of the Shareholders Agreement, and remains today, “[a]t the top of th[e] ownership pyramid” that includes both Storm and Russian Technologies. (Award at 2-3.) Indeed, as Storm’s indirect parent, Alfa was intimately involved in the contract negotiations between Storm and Telenor. 13 Therefore, Alfa is an “[a]ffiliate” of Storm as its indirect parent, and Russian Technologies is an affiliate of Storm as both Storm and Russian Technologies operate “under [the] common control” of Alfa. 14 Because the non-compete clause specifically prohibits Storm’s affiliates from owning more than 5% of a competing Ukrainian telecommunications company without prior consent, and because Alfa and Russian Technologies maintain such ownership without receiving such consent, Alfa and Russian Technologies were properly bound to comply with the divestiture order.
In any event, Storm’s claim that the Final Award improperly attempts to bind Alfa and Russian Technologies misconceives the Award. The Tribunal did not direct Alfa and Russian Technologies to do anything, and a judgment of this Court enforcing that Award would not be directed to Alfa or Russian Technologies, who are not parties to this action. Alfa and Russian Technologies may divest themselves of their investments in Turkcell and UHT or not, as they choose, without violating any directive of the arbitrators or of this Court. The Award binds Storm, by requiring it to sell its shares in Kyivstar— albeit only conditionally, in that Storm need not comply if certain actions are taken by its affiliates. That the arbitrators provided for an alternative contingency by which Storm and those who control it could bring Storm into compliance with the Agreement does not render their Award invalid, or constitute, overreaching, or mean that the Tribunal attempted to bind non-parties to the Arbitration Agreement. Indeed, the relief awarded by the arbitrators would appear to be precisely the kind of relief reasonable parties would have contemplated in imposing contractual obligations on Storm “or any of its Affiliates.” (Agreement § 6.02.)
In support of its argument that the conditional divestiture order constitutes an overreaching by the Tribunal, Storm engages in a detailed discussion of
Thomson-CSF, S.A. v. American Arbitration Association,
As the Tribunal noted, “[i]f Storm desired to limit the scope of the non-compete language, it could have negotiated a more limited application.” (Award at 60.) Indeed, the record shows that the non-compete clause was actively negotiated. In particular, as the Tribunal noted, Storm negotiated for, and received, an exemption from the non-compete clause for what was then Alfa’s, and is now Altimo’s, investment in Golden Telecom, Inc. (“Golden”). (Sills Decl. I, Ex. HH at 60; Agreement, Sched. 4.) It is undisputed that Storm itself does not have, and never had, an interest in Golden. (Pet. Mem. 20 n. 19.) Thus, it is clear from Storm’s insistence on this exemption that Storm was aware of the broad sweep of the non-compete clause, which limited certain investments not just by Storm, but by Alfa, Russian Technologies, and Storm’s other affiliates.
Having breached the Agreement by violating the non-compete clause, Storm must suffer the consequences for its violation, and the Tribunal was empowered by Storm and Telenor to impose those consequences. Accordingly, the divestiture order was not outside the scope of the arbitrators’ authority, and is entitled to recognition and enforcement by the Court. 15
b. Anti-Suit Injunction
Finally, Storm argues that the Tribunal acted in manifest disregard of the law and outside the scope of their powers by ordering an anti-suit injunction as part of the Final Award. Pursuant to the anti-suit injunction, Storm, “and anyone acting in concert with it,” is enjoined from instituting or prosecuting “any and all court actions concerning any disputes or controversies” related to the Agreement, “including all of the existing litiga-tions currently pending in the Ukraine.” (Award at 67.) In addition, the anti-suit injunction specifically enjoins the continuation of the pending E
&
Y actions.
(Id.
68.) Storm argues that the Tribunal disregarded controlling law by failing to consider the preconditions for an anti-suit injunction laid out in
China Trade & Dev. Corp. v. M.V. Choong Yong,
The anti-suit injunction at issue here involves a series of agreements between Kyivstar and two Ernst & Young entities for the provision of auditing services (the “E & Y Agreements”). (Zeballos Decl., Exs. P & Q.) According to Storm, Kyivstar was prohibited from entering into a contract for auditing services by the December 2005 order of the Ukrainian court, in which that court invalidated the procedures set forth in the Kyivstar Charter regarding election of members to the Ky-ivstar Board. (Id. Ex. R.) Pursuant to that order, Storm commenced an action in Ukraine seeking to invalidate the E & Y Agreements on the grounds that the Ky-ivstar executive who signed the E & Y Agreements lacked authority to do so. (Id. Ex. S at 3-4.) Shortly after the injunction issued in Storm’s E & Y action was vacated, two other actions ensued, each filed by Alpren against the same Ernst & Young entities. (Id. Exs. U & V.)
First, Storm argues that the Tribunal acted “without regard to ... controlling law” because the arbitrators did not consider the preconditions to entry of an anti-suit injunction, as laid out by the Circuit in
China Trade,
Storm misunderstands the relevant issue here. The proper inquiry is not when a court may enter an anti-suit injunction in order to protect its own jurisdiction. Rather, the proper inquiry is whether the parties agreed to give the arbitrators the power to enter such an injunction. Where, as here, arbitrators are given extremely broad authority to order any relief they deem “just and equitable” (Agreement § 12.01(a)(v)), the applicable test for arbi-tral jurisdiction is not whether the preconditions of
China Trade
are satisfied, but whether the arbitral award “touch[es] matters” within the contract.
ACE Capital Re Overseas Ltd. v. Central United Life Ins. Co.,
It is undisputed that the litigation being pursued by Storm and its affiliate Alpren has “halted Kyivstar’s efforts to have its 2006 financial statements audited and have prevented Kyivstar from providing financial information to” Telenor, thereby violating the Shareholders Agreement and causing severe economic repercussions to Kyivstar. (Pet. Mem. 23.) Specifically, it is undisputed that, due to the E & Y *365 actions, Kyivstar might be forced to default on certain debts totaling over $400 million, and its credit rating has been downgraded and might be suspended. (Award at 62-63.) Moreover, the purported basis for the E & Y actions is that Kyivstar was prohibited from entering into a contract for auditing services because Kyivstar’s officer was not authorized to sign the auditing contract. But, assuming arguendo that Kyivstar’s officer lacked such authority, it is undisputed that Kyivs-tar’s officer lacked that authority only because Kyivstar’s Charter violates Ukrainian law, and Kyivstar’s Charter in turn only violates Ukrainian law because Storm refuses both to participate in Kyivstar’s governance and to amend the Charter as ordered by the Ukrainian court, both of which constitute violations of the Shareholders Agreement. Thus, the E & Y actions are simply an aspect of Storm’s continued non-compliance with the Shareholders Agreement.
In addition, as the Tribunal noted that, “even though Storm maintains that the [E & Y actions do] not involve the violation of any obligation imposed by the Shareholders Agreement,” Storm’s conduct, at a minimum, violates the “good faith” obligation that is expressly incorporated into the Agreement. (Agreement § 2.05.) Section 2.05 of the Agreement is broadly worded, and requires Storm to act in good faith with respect to both Telenor and Kyivstar. By instituting litigation that prevents Kyivstar from successfully operating and threatens to severely debilitate its functioning, Storm has breached its good faith obligation under the Agreement.
Accordingly, the E & Y actions are “intimately related to issues ... submitted to the Tribunal,” and the anti-suit injunction was “fully within the broad scope of the Tribunal’s jurisdiction.” (Award at 64.) Indeed, when viewed through this lens, the anti-suit injunction is not simply “related” to those issues, but is a necessary and proper remedy to prevent Storm from subverting the Agreement again in the future. As the E & Y actions themselves are a violation of the Agreement, their continued prosecution also constitutes a continued violation of the Agreement. Therefore, the entry of an anti-suit injunction against Storm was a proper exercise of the arbitrators’ powers, and will not be disturbed by the Court.
However, the Court’s inquiry does not end there. The anti-suit injunction does not only prohibit Storm from pursuing the E & Y actions; it also binds “anyone acting in concert with it,” and specifically Alpren, from pursuing those actions.
(Id
68) Storm argues that, even if the Tribunal was authorized to enjoin Storm from pursuing its E
&
Y action pursuant to the broad powers of the Arbitration Agreement, it could not similarly bind Alpren because Alpren was not a signatory to the Arbitration Agreement. Storm claims that, in order for Alpren to be bound to the Arbitration Agreement, the Tribunal was required to find one of the conditions for binding a non-signatory to an arbitration clause satisfied, as laid out in
Thomson,
Storm’s argument is unpersuasive. As an initial matter, the Tribunal’s lack of specific findings is not a sufficient basis for a reviewing court to refuse to enforce an arbitral award.
See Porzig v. Dresdner, Kleinwort, Benson, North Am. LLC,
The potential “justification^]” for binding Alpren to the anti-suit injunction are more than “barely colorable” — they are eminently reasonable and persuasive. For example, the Tribunal could have found that Alpren was acting as the alter ego of Storm when it instituted its E & Y actions, thereby finding that Alpren was properly bound as a non-signatory to the Arbitration Agreement. According to
Thomson,
a non-signatory may be bound to an arbitration clause where “the corporate relationship between a parent and its subsidiary are sufficiently close as to justify piercing the corporate veil and holding one corporation legally accountable for the actions of the other.”
The Tribunal could have found this standard met here. The E & Y actions, instituted in violation of the Shareholders Agreement, clearly constitute a “wrong” that has caused an “unjust ... injury” to Telenor.
Id.
In addition, the Circuit has often held that “shell” companies are “mere instrumantalit[ies]” of their parents for purposes of piercing the corporate veil.
Id.; see id.
(“The critical question is whether the corporation is a ‘shell’ being used by the individual shareowners to advance [their own interests].”);
Walter E. Heller & Co. v. Video Innovations, Inc.,
Furthermore, as both the Tribunal and this Court have found, Alpren and Storm have identical interests in this litigation, and have proceeded in the Ukrainian courts to further those interests through collusive and vexatious litigation. For example, Alpren only instituted its E & Y actions after Storm’s E & Y action failed to succeed, thereby showing that Alpren’s E & Y actions are merely a transparent
*367
attempt by Alpren to further Storm’s interests. Thus, it is clear that Alpren and Storm “do not deal at arms length with each other,”
Thomson,
Although Storm argues that the Tribunal could not make a proper veil-piercing determination during the arbitration proceedings because “the evidentiary record [is] undeveloped on matters that would be critical to an expeditious alter ego analysis” (Resp. Mem. 21), the evidentiary record is more than ample to make such a determination. The evidence of collusion between Alpren and Storm is substantial, and has been recounted several times both by this Court and the Tribunal. Indeed, the Tribunal may have simply found that it was not necessary to make a specific veil piercing determination, as it had previously determined that Alpren and Storm had identical interests which they had pursued through the collusive Ukrainian litigation. In addition, it is undisputed that there is significant overlap between the corporate ownership and management of Altimo, Al-pren’s parent, and Storm. For example, Klymenko is both Storm’s general director
and
Altimo’s Vice-President, and the corporate ownership of Storm overlaps with that of Alpren by virtue of Alpren’s status as Altimo’s subsidiary. Accordingly, “the totality of the circumstances” reveals that Alpren and Storm had identical interests and have only acted in concert with each other to pursue those interests,
Thomson,
In addition to the veil piercing determination, the Tribunal could have determined that an anti-suit injunction, such as this one, whose purpose is enjoining litigation being pursued in derogation of an arbitration agreement — whether that litigation is being pursued by the parties to the arbitration or by third parties — is not an inappropriate, or even unusual, remedy.
See Storm,
Accordingly, entry of the anti-suit injunction neither constituted manifest disregard of the law, nor was outside the scope of the arbitrators’ authority.
3. Remaining Statutory Grounds
Finally, Storm argues that the Award should be vacated because there exists “an incapacity that renders the arbitration agreement void,” and because Storm was “unable to present [its] case” to the Tribunal. (Resp. Mem. 12 n. 8, citing Conven *368 tion Art. V(l)(a)-(b).) Storm devotes a grand total of one footnote to both these arguments, reflecting their complete lack of merit.
Article V(l) (a) of the New York Convention provides that “[r]ecogition and enforcement may be refused” where “[t]he parties to the agreement ... were, under the law applicable to them, under some incapacity” pursuant to “the law to which the parties have subjected it.” Storm argues that the Ukrainian decisions “render the Shareholders Agreement void
ab ini-tio,”
and therefore that the Award should be vacated because the Arbitration Agreement is incapable of enforcement.
(Id.)
What Storm neglects to mention, however, is that Article V(l)(a) only applies where the agreement is incapable of being enforced
“under the law to which the parties have subjected it.
” Convention, Art. V(1)(a) (emphasis added).
See Arbitration Between Overseas Cosmos, Inc. and NR Vessel Corp.,
No. 97 Civ. 5898,
Storm’s final attempt to vacate the Award is equally futile. Despite the voluminous record, including the reception into evidence of statements of eleven witnesses presented by Storm during the arbitration proceedings, Storm contends that the Award should be vacated because the Ukrainian order obtained by Storm against itself purporting to enjoin its participation in the arbitration rendered Storm unable to present its case, requiring vacatur under Article V(l)(b) of the Convention.
Article V(l) (b) of the New York Convention provides that “[Recognition and enforcement may be refused ... [upon] proof that ... [t]he party against whom the award is invoked was ... unable to present his case.” The governing standard under Article V(l)(b) of the Convention is the forum state’s standard of due process.
See Parsons,
It is clear from the Final Award, as well as the Partial Final Award, that Storm was afforded an ample opportunity to be heard regarding all of the issues in the arbitration, and that it took full advantage of that opportunity. (See Sills Deck II, Ex. HH at 19-20.) Although Storm physically withdrew from one hearing before the Tribunal, its purported basis for that withdrawal was its claim that remaining in the proceeding would have violated the Ukrainian injunction. However, because Storm had, in effect, obtained that injunction against itself, the injunction did not provide an adequate or proper basis for not proceeding with the arbitration. (See Sills Deck II, Ex. 191 at 34.) Once again, a contrary holding would reward Storm for its patently improper conduct before the Ukrainian courts.
Moreover, even after Storm physically withdrew, the Tribunal proceeded with *369 scrupulous care for Storm’s rights. It stated on the record that no default would be entered against Storm, and that Tele-nor remained obligated to carry its burden of proof. (See Sills Decl. II, Ex. 189 at 33.) In fact, in connection with the December 18 hearing, the Tribunal admitted into the record, and considered, four additional witness statements and numerous documents offered by Storm, although neither they nor any other of Storm’s eleven witnesses were ever produced for cross-examination. The Tribunal likewise considered Storm’s pre-hearing brief on the merits, and directed the parties to submit further briefs on certain of the issues raised by Storm. Indeed, in its presentation to the Court, Storm nowhere refers to any evidence or arguments it was supposedly barred from presenting to the Tribunal. Despite its professed need to comply with the Ukrainian injunction, Storm in fact submitted additional briefing after the hearing from which it had voluntarily absented itself. (See Sills Decl. I, Exs. K, Q, & S; id. Ex. HH at 32-33.)
Thus, Storm had a “meaningful” opportunity to present its case,
Tradeway,
CONCLUSION
Storm and its corporate owners deliberately entered a carefully-negotiated agreement with Telenor. Central to the bargain was an arbitration clause providing for the resolution of disputes in a fair, neutral international arbitration forum. Storm provided every conceivable assurance to Telenor that its signatory officers were empowered to bind it to that agreement. When Storm breached the agreement, it was provided with precisely the fair and impartial hearing it had bargained for, by a distinguished panel of arbitrators, despite making repeated efforts to renege on its agreement and to torpedo the proceeding by collusive and vexatious litigation. The arbitral Tribunal carefully considered Storm’s every argument, and by unanimous vote — including the vote of the arbitrator Storm itself had appointed — decisively rejected those arguments and correctly awarded appropriate relief to Tele-nor.
Accordingly, for the foregoing reasons, Storm’s motion is denied, and Telenor’s petition for enforcement of the Final Award is granted. Storm is hereby ordered to comply with the directives of the Final Award.
SO ORDERED.
Notes
. Though the Agreement is nominally between Storm and Telenor, Storm is merely a holding company with no business other than holding the shares of Kyivstar for its ultimate corporate parent Altimo, which owns 50.1% of Storm through Hardlake, a Cyprus entity that is 100% owned by Altimo, and the remaining 49.9% through Alpren Limited, which is also 100% owned by Altimo. (See Zeballos Decl. Ex. H at 2.)
. The Agreement was first drafted in 2002 and customary certificates were also exchanged at that time (id. ¶ 31), but final execution of the Agreement was delayed by the parties’ dispute over potential liability for material breach. (Id. ¶ 37.) The final agreement, including the Arbitration Agreement, was identical to the 2002 draft in all respects except for the material breach term, which was amended pursuant to a request by Storm. (Award at 12-13.)
. The High Commercial Court found that the Kyivstar Charter was invalid due to the failure of Kyivstar to comply with Ukrainian laws regarding, inter alia, shareholders’ rights and the election of Board members. (Zeballos Decl. Ex. R.)
. Telenor argues that Storm only appealed the trial court's decision because an "appeal gives a special enforceable status, at least as a formal matter of Ukrainian law, to the judgment.” (12/11/06 Tr. 61.)
. Altimo and Alpren appealed the Court's order to the Second Circuit. That appeal is currently pending.
. The Tribunal found that the result of the E & Y actions has been an "immediate adverse impact in Telenor ASA share price,” and a possible default by Kyivstar on certain bond obligations totaling over $400 million. (Award at 62-63.)
. Petitions to confirm arbitral awards are treated as motions.
See
9 U.S.C. § 6 (“Any application to the court ... shall be made and heard in the manner provided by law for the making and hearing of motions .... ”);
see, e.g., IFC Interconsult, AG v. Safeguard Int’l Partners, LLC,
. After the motions were fully briefed, Storm informed the Court that, "in response to an application made by Storm,” a Ukrainian court had issued a decision refusing to recognize the Final Award, essentially for the same reasons Storm argues for non-recognition here. (Letter from Pieter Von Tol to the Court, dated Oct. 23, 2007, at 1.) However, Storm concedes that the Ukrainian judgment is not binding on this Court, and does not "in any way ... limit this Court’s ability to decide Telenor Mobile’s pending petition to confirm or Storm's motion to vacate the Final Award.”
(Id.)
Indeed, even if Storm had not conceded the point, the only court with authority to vacate an international arbitration award is one at the seat of arbitration,
see Karaha Bodas Co. v. Perusahaan Pertambangan Minyak Dan Gas Bumi Negara,
. The Tribunal also found the Ukrainian decisions to be non-binding because those decisions did not "adequately address[ ] the sever-ability of the arbitration clause from the rest of the Shareholders Agreement” (Award at 24), and because those decisions "ha[d] no res judicata or collateral estoppel effect on Telenor” as a result of Telenor’s non-participation in the underlying litigation
(id.
42). Because the Court finds that the collusive nature of the Ukrainian litigation was a sufficient ground for the Tribunal to reject the Ukrainian decisions as non-binding, it is unnecessary to determine whether the Tribunal’s alternative grounds were similarly sufficient. See
Wallace v. Buttar,
. Nilov also had actual authority to bind Storm to the arbitration agreement simply by virtue of his status as Storm's General Director.
See Seetransport,
. The Tribunal also found that Nilov had actual authority to bind Storm to the 2004 Shareholders Agreement as well. The Tribunal’s findings on that issue were well-reasoned and thorough (see Award at 45-48), and are adopted by the Court.
. Storm argued to the Tribunal that WiMax services do not fall within the scope of the non-compete clause, but that question was resolved against Storm by the Tribunal (Award at 58-61), and Storm has not asked the Court to review that resolution here.
. See Award at 5 ("On April 29, 2002, the Alfa and Telenor representatives entered into a Letter Agreement that set out the expected arrangement between Telenor and Storm ...."); id. (noting that the Agreement allowed Storm and Alfa the right to jointly appoint four directors to Kyivstar’s board); id. at 7 (discussing Storm’s insistence during contract negotiations that Telenor sell certain shares to Alfa or an Alfa affiliate).
. See Award at 59 ("[A] plain reading of the definition of ‘Affiliate’ includes the various entities that directly or indirectly have a controlling interest in Storm, and ... this includes Alfa"); id. (noting that Alfa secured its ownership in UHT "acting through its subsid-iaty Russian Technologies”).
. Storm also suggests that the divestiture order is "in manifest disregard of the law” and that it “cannot be enforced on public policy grounds because it compels a violation of the law,” but cites no case law in support of either argument. (Resp. Mem. 22.) These throwaway suggestions are simply another last-ditch attempt by Storm to vacate the Award. As discussed supra, the divestiture order does not ignore any controlling law, but instead was a proper exercise of the arbitrators’ power bestowed upon them by the Agreement. Therefore, the manifest disregard standard does not apply here. Furthermore, Storm’s public policy argument is unpersuasive for the same reasons discussed in Part II.B.l, supra.
. An arbitral award may be vacated under Article V(l)(e) of the Convention where it "has been set aside or suspended by a competent authority of the country in which, or under the law of which, that award was made.” Storm did not invoke this ground in its motion to vacate, presumably because no court or other "authority” had rendered a decision on the Award prior to the briefing of its motion. Although a Ukrainian court recently issued a decision refusing to recognize the Final Award,
see
n. 8,
supra,
Storm may not rely on that decision for vacatur of the Award pursuant to Article V(l)(e), as the Award was made, not in Ukraine under Ukrainian law, but in the United States under New York law. Thus, the Ukrainian court's decision to set aside the Award is irrelevant to Article V(l)(e), and Storm cannot rely on that decision for vacatur here.
See, e.g., Karaha Bodas,
