Affirmed by published opinion. Judge TRAXLER wrote the opinion, in which Judge GREGORY and Judge THORNBURG joined.
OPINION
This case arises out of an alleged breach of contract between TechnoSteel, LLC (“TechnoSteel”) and Beers Construction Company (“Beers”). TechnoSteel appeals the district court’s order denying its petition to compel arbitration of its dispute with Beers pursuant to 9 U.S.C.A. § 4 (West 1999). Beers filed a motion to dismiss TechnoSteel’s appeal for lack of jurisdiction based upon the district court’s simultaneous decision granting Beer’s mo *153 tion to transfer the case pursuant to 28 U.S.C.A. § 1404(a) (West 1993) to the Northern District of Georgia for litigation.
We hold that the physical transfer of the litigation aspects of this case to the Northern District of Georgia does not divest this court of jurisdiction to review the district court’s immediately appealable decision to deny TechnoSteel’s petition to compel arbitration. Therefore, we have jurisdiction to hear TechnoSteel’s appeal from that portion of the district court’s order and we deny Beer’s motion to dismiss this appeal for lack of jurisdiction. We affirm, however, the district court’s decision denying TechnoSteel’s petition to compel arbitration under § 4 of the Arbitration Act.
I.
Health Management Associates d/b/a Hartsville HMA (the “Owner” or “Hospital”) awarded Beers the general contract to construct a hospital in Hartsville, South Carolina. Beers, in turn, subcontracted the project’s structural steel fabrication and erection to TechnoSteel. When a dispute arose concerning Tech-noSteel’s performance on the project and its entitlement to full payment, the parties disagreed as to whether the dispute was subject to arbitration or litigation and as to whether the proper forum was in Georgia or South Carolina. TechnoSteel filed a demand for arbitration against Beers with the American Arbitration Association, seeking arbitration in South Carolina, and litigation was commenced by the parties in both states.
This appeal arises out of the action originally commenced in South Carolina state court by TechnoSteel seeking to compel arbitration of the dispute, which was subsequently removed by Beers to the federal district court in South Carolina. After removal, TechnoSteel filed a petition to compel arbitration with the district court pursuant to § 4 of the Arbitration Act. See 9 U.S.C.A. § 4. Beers filed a motion to dismiss the case, or alternatively, to transfer the action pursuant to 28 U.S.C.A. § 1404(a) to the United States District Court for the Northern District of Georgia, asserting that it was the forum agreed upon by the parties in their subcontract.
On May 5, 2000, the district court denied TechnoSteel’s petition to compel arbitration based upon its interpretation of the parties’ contractual agreement and granted Beers’ motion to transfer the action to the Northern District of Georgia. On May 10, 2000, the transferred action was received and docketed in the Northern District of Georgia. TechnoSteel filed a notice of appeal from the district court’s denial of its petition to compel arbitration under § 4 of the Arbitration Act on May 18, 2000. 1
II.
We begin with Beers’ motion to dismiss TechnoSteel’s appeal for lack of jurisdiction. As noted, the district court denied TechnoSteel’s petition to compel arbitration of its construction dispute with Beers, filed under 9 U.S.C.A. § 4, and then transferred the balance of the action, specifically TechnoSteel’s causes of action for breach of contract and quantum meruit, to Georgia where similar litigation was pending. TechnoSteel does not appeal the portion of the district court’s order transferring the litigation to Georgia; such a *154 decision is interlocutory and not immediately appealable. 2 Rather, TechnoSteel seeks only to exercise its right under § 16 of the Arbitration Act to challenge the district court’s denial of arbitration, which is an immediately appealable decision. See 9 U.S.C.A. § 16(a)(1)(B) (West 1999) (“An appeal may be taken from .... an order ... denying a petition under section 4 of this title to order arbitration to proceed.”).
In its motion to dismiss, however, Beers draws no distinction between the review-ability of interlocutory decisions which are immediately appealable and those which are not. Relying on precedent which holds that a transferor circuit court loses jurisdiction to review interlocutory decisions of its district courts that are
not
immediately appealable once the file is physically transferred under § 1404(a),
see, e.g., Wilsork-Cook Med., Inc. v. Wilson,
A.
Generally, courts of appeal have jurisdiction over appeals from all “final decisions” of the district courts under 28 U.S.C.A. § 1291 (West 1993), including: limited types of interlocutory decisions specified under 28 U.S.C.A. § 1292(a) (West 1993); decisions certified for immediate appeal by the district court and accepted by the circuit court under 28 U.S.C.A. § 1292(b) (West 1993); decisions which are subject to immediate mandamus review under 28 U.S.C.A. § 1651 (West 1994); decisions, such as the one before us today, which are otherwise immediately reviewable by virtue of another congressional act; and decisions treated as final under the “collateral order” doctrine of
Cohen v. Beneficial Industrial Loan Corp.,
The directive of where such appeals must be taken is governed by 28 U.S.C.A. § 1294(1) (West 1993), which provides that:
appeals from reviewable decisions of the district and territorial courts shall be taken to the courts of appeals as follows: (1) From a district court of the United States to the court of appeals for the circuit embracing the district....
Id. (emphasis added). The statute seems clear enough. But, the issue of what constitutes a “reviewable decision” under § 1294(1) is less clear when viewed in the context of deciding whether a circuit court has jurisdiction to review a decision of a district court that was issued prior to or simultaneously with an order transferring a case or some portion of it to another circuit under § 1404(a). Several views have emerged.
*155
First, at least two circuits have held that “reviewable decisions” under § 1294(1) “applies to
all
‘reviewable’ decisions of the district courts, not just to those which are immediately appealable.”
McGeorge v. Continental Airlines, Inc.,
The Second Circuit, in contrast, held early on that “[t]he review of any order of the district court in a transferred cause, made before transfer,
is
within the jurisdiction of the court of appeals of the circuit to which the cause has been transferred.”
Magnetic Eng’g & Mfg. Co. v. Dings Mfg. Co.,
The D.C. Circuit, on the other hand, has considered the question of when a trans-feror circuit court retains jurisdiction over decisions that are immediately appealable.
See Hill v. Henderson,
We think Congress’s distinction between “final decisions” in § 1291 and “reviewable decisions” in § 1294 is consistent with our view that the appealability of the claim dismissal here flows to the transferee circuit. The Tenth Circuit seemingly understood “reviewable decisions” to encompass every ruling of a district court that might in due course ultimately pass under the scrutiny of an appellate court. But the term is susceptible to a narrower reading: decisions subject to review at the time they are entered, namely, (a) final decisions, (b) non-final decisions embraced by § 1292’s provision for review of certain types of interlocutory orders, (c) decisions treated as final under the “collateral order” doctrine of Cohen v. Beneficial Indus. Loan Corp.,337 U.S. 541 ,69 S.Ct. 1221 ,93 L.Ed. 1528 (1949), and (d) (perhaps) non-final decisions subject to immediate mandamus.
Id. at 675 (second emphasis added). 5 Thus, under the D.C. Circuit’s view, “reviewable decisions” under § 1294(1), which are limited to those issued by the transfer- or district court that are “subject to review at the time they are entered,” may only be appealed to the circuit court embracing the transferor district court, id. at 675, whereas all other pretransfer, interlocutory decisions “shift” or “flow” to the transferee circuit where they become appealable upon final judgment there, see id. at 675-77.
B.
Applying these precedents to the case before us, we note that the decision of our district court denying TechnoSteel’s petition to compel arbitration was immediately appealable, see 9 U.S.C.A. § 16(a)(1)(B), and that it was immediately appealable only to us, see 28 U.S.C.A. § 1294(1). The Eleventh Circuit Court of Appeals would not entertain an appeal from the South Carolina district court’s denial of TechnoSteel’s petition to compel arbitration. See 28 U.S.C.A. § 1294(1); Roofing & Sheet Metal Servs., 689 F.2d at *157 986 & n. 5. And, because the decision was immediately appealable, the time for appeal began to run in our circuit upon issuance of the decision. See Fed. R.App. P. 4(a)(1)(A).
Indeed, this does not appear to be in dispute. Rather, Beers asserts that, because § 1404(a) transfers are normally considered to be “plenary,”
see Chrysler,
We disagree. While it is true that courts have adhered to the general rule that a § 1404(a) transfer “contemplates a plenary transfer of the entire case,”
Chrysler,
1.
As an initial premise, we note that courts have not blindly applied the rules governing the transfer of jurisdiction to strip circuit courts of jurisdiction to review every decision issued by their district courts prior to transfer, nor have courts advanced the view proffered by Beers that a formal Rule 21 severance order is the only method by which jurisdiction over a particular decision can remain in the trans-feror circuit. Indeed, in the
Chrysler
case relied upon by Beers, the Tenth Circuit recognized that the reviewability of judgments entered under Rule 54(b) would remain in a transferor circuit court notwithstanding a § 1404(a) transfer.
Id.
at 1517 n. 7 (noting that “where the transferor court has entered partial judgment under Rule 54(b) prior to transfer, the court of appeals in the transferor circuit has jurisdiction to review the question, irrespective of whether other issues in the case have been transferred out-of-circuit”);
see also McGeorge,
Additionally, other circuits have specifically declined to impose the formal entry of judgment under Rule 54(b) or a Rule 21 severance order as a condition precedent to holding that reviewability of a particular decision remains in the transferor circuit. For example, the Third Circuit has noted that a transferor district court can effectively sever claims, even though it neglects to explicitly invoke Rule 21, and thereby preserve an appeal from such orders in its own circuit notwithstanding the completion of the physical transfer, so long as there is “a strong indication that the judge intended to effect a severance.”
White v. ABCO Eng’g Corp.,
The D.C. Circuit has held that a district court’s dismissal of plaintiffs’ claims against a defendant based upon a lack of personal jurisdiction was a “final” decision ripe for immediate appellate review by the transferor circuit court, even though the district court had
not
formally directed entry of final judgment under Rule 54(b) and had transferred the remainder of the case to the district court in Maryland.
See Reuber v. United States,
2.
The present situation is all the more clear from a jurisdictional standpoint. Under Rule 54(b), a district court order dismissing one of several claims or parties is
not
typically viewed as a “final decision” qualifying for immediate appeal unless the district court determines that “there is no just reason for delay” and enters final judgment as to the claim, thereby creating an immediately appealable or final decision. Fed.R.Civ.P. 54(b). Consequently, when the transferor district court enters partial judgment under Rule 54(b), the entry of judgment creates an immediately appealable decision which easily falls outside the normal “plenary transfer” principle of § 1404(a).
See Chrysler,
928 F.2d at
*159
1517 n. 7;
McGeorge,
In contrast, a “judgment” under Rule 54(a) of the Federal Rules of Civil Procedure is defined as “any order from which an appeal lies.” Fed.R.Civ.P. 54(a). It embraces “any ‘final decision’ from which an appeal is permitted under [§ ] 1291,” as well as “any appealable interlocutory order.” 10 Charles A. Wright, Arthur R. Miller & Mary Kay Kane,
Federal Practice and Procedure
§ 2651 (3d ed.1998);
NBA v. Minnesota Profl Basketball, Ltd. P’ship,
Because we are presented with a decision which is immediately appealable solely by operation of § 16(a)(1)(B) of the Arbitration Act, in contrast to partial judgments entered under Rule 54(b), the decision is appealable without need for any action by the parties or the court. In other words, when a transferor district court decision adjudicates fewer than all the claims or adjudicates the rights and liabilities of fewer than all the parties, but nonetheless creates a decision from which an immediate appeal lies by virtue of a separate statute (such as § 16 of the Arbitration Act), it has no less created an immediately appealable decision; but, it need not act to enter judgment under Rule 54(b) at all prior to transferring the file in order to preserve its reviewability in the transferor circuit court. Of course, such a decision equally falls outside the normal “plenary transfer” principle of § 1404 because, as in the case of a partial adjudica *160 tion entered as final under Rule 54(b), the district court has issued a decision which is effectively severed from the balance of the case and immediately appealable in the transferor circuit court. And, because the reviewability of the immediately appeal-able decision does not transfer with the physical file, at least not until the time for appeal expires under our rules, the timing of the physical transfer of the file to another district has no effect upon our jurisdiction to entertain the appeal.
3.
Finally, the practicalities of the situation also compel us to reject Beers’ attempt to extend the general rules concerning jurisdiction over pretransfer decisions which are not immediately appealable to decisions which are immediately appealable.
The transfer statute provides that “[f]or the convenience of parties and witnesses, in the interest of justice, a district court may transfer any civil action to any other district or division where it might have been brought.” 28 U.S.C.A. § 1404(a). Thus, “[a] section 1404(a) transfer merely involves a discretionary change to another district where the action could have been brought.”
Gower,
The general rule that the transfer of jurisdiction is plenary and occurs when the record is physically transferred to the transferee court is, therefore, premised upon the commonsense and workable principle that “some court should have jurisdiction over a case at all times.”
Wilson-Cook,
An interlocutory decision issued by a transferor district court that is not immediately appealable does not start any appeal clock running, nor does the subsequent transfer leave the aggrieved party with no remedy, as the party may act to preserve the ruling and the right to appeal from it upon final judgment in the transferee circuit court. Thus, the view that nonappealable, interlocutory decisions necessarily travel with the case when transferred, with jurisdiction transferring when the file is received by the transferee court, is an appropriate one.
In contrast, an interlocutory decision issued by a transferor district court which is immediately appealable does start the appeal clock running and starts it running in the transferor circuit court. Thus, hardly a reflection of the commonsense and workable rule that has been applied in the context of nonappealable, interlocutory decisions, extension of the principle to an immediately appealable decision of a trans-feror court operates only to deprive the transferor circuit court of jurisdiction over an appeal as of right from an immediately appealable decision issued by its district court even though the transferee circuit *161 court has, under § 1294(1), no jurisdiction to review the decision either.
Under Beers’ argument, in order to obtain direct appellate review of the denial of a petition to compel arbitration or other immediately appealable decision entered by a district court in our circuit prior to or concurrent with a § 1404 transfer, the aggrieved party would have to race to file an appeal in our court before the clerk of the district court could send the file to the transferee district court, eliminating any time for reflection by the losing party, as our thirty-day time period for filing an appeal in civil cases will be rendered meaningless. See Fed. R.App. P. 4(a)(1)(A). Or, if he loses the footrace, the party would be relegated to seeking re-transfer from the transferee district court in order to pursue the appeal, hopeful that he can file the motion, get the requested relief, and get the file physically re-transferred before the thirty-day time for appeal runs in the transferor circuit court. Neither the intent of § 1294(1), nor the general rules previously espoused by the courts regarding § 1404(a) transfers, dictates such a frantic appellate procedure. 8
In sum, we find no impediment to our exercising jurisdiction over TechnoSteel’s timely filed appeal from the district court’s decision. The district court’s decision denying the petition to compel arbitration, which is immediately appealable under 9 U.S.C.A. § 16, is subject to review in our circuit notwithstanding the concurrent § 1404(a) transfer of the balance of the action, rendering the fact that the transfer was complete before the appeal was actually filed irrelevant.
III.
Having determined that we have jurisdiction to entertain Techno Steel’s appeal from the district court’s denial of its petition to compel arbitration under § 4 of the Arbitration Act, we turn to the merits of TechnoSteel’s appeal. Section 4 provides that “[a] party aggrieved by the alleged failure, neglect, or refusal of another to arbitrate under a written agreement for arbitration may petition any United States district court ... for an order directing that such arbitration proceed in the manner provided for in the agreement .” 9 U.S.C.A. § 4. Techno Steel contends that its subcontract agreement with Beers mandated arbitration of the construction dispute between them. Beers disagrees.
The Federal Arbitration Act, 9 U.S.C.A. §§ 1-16 (West 1999) “does not mandate the arbitration of all claims, but merely the enforcement ... of privately negotiated arbitration agreements.”
Dean Witter Reynolds, Inc. v. Byrd,
Article 2 of the Subcontract Agreement between Beers and TechnoSteel incorporates “the Agreement between the Owner [the Hospital] and Contractor ..., [and] all Conditions to the Agreement between the Owner and Contractor” as part of its Subcontract Agreement. J.A. 30. Article 4.5.1 of the General Conditions of the Agreement between the Owner and Beers, in turn, provides that “[a]ny controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration.” J.A. 108. However, Article 5.3.1 of the General Conditions of the Agreement between the Owner and Beers also mandates that Beers “require each [of its] Subcontractor[s] ... to assume toward the Contractor all the obligations and responsibilities which the Contractor ... assumes toward the Owner” and, further, that:
[e]ach subcontract agreement ... shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights, remedies and redress against the Contractor that the contractor, by the Contract Documents, has against the Owner.
J.A. 110 (emphasis added). TechnoSteel contends that the dispute between it and Beers is required to be arbitrated pursuant to the incorporation of the arbitration terms of the Owner/Beers Contract into the Beers/TechnoSteel Subcontract Agreement. We disagree.
In the absence of any contrary provision contained within the Subcontract Agreement, the Subcontract Agreement would indeed have required, by virtue of its incorporation of the Owner/Beers Contract, that all controversies or claims between Beers and TechnoSteel be submitted for arbitration. However, while Article 4.5.1 of the General Conditions would, if read in isolation, impose an arbitration requirement upon the Subcontract Agreement, Article 5.3.1 of the General Conditions must be read as providing a Subcontractor with the right to demand arbitration “unless specifically provided otherwise in the subcontract agreement.” J .A. at 110 (emphasis added). TechnoSteel’s argument fails because the Subcontract Agreement between it and Beers provides otherwise.
Article 14 of the Subcontract Agreement governs claims and disputes which arise under the Agreement. Article 14.d provides that “[a]ny claim, dispute or other matter in question between the Contractor and the Subcontractor relating to this Agreement, or the Work performed hereunder, shall be governed by the laws of the State of Georgia.” J.A. 39. And, Article 14.h. of the Subcontract Agreement quite clearly provides that:
To the extent Contractor does not elect to arbitrate a claim or dispute hereunder, Contractor and Subcontractor each hereby agree that the claim or dispute shall be submitted for resolution to the United States District Court for the Northern District of Georgia or, if that court does not have subject matter jurisdiction, to the Superior Court of Fulton County, Georgia. Both parties hereby consent to and waive any objections to the jurisdiction and venue of these *163 courts, and stipulate that they shall be the sole fora for litigating disputes hereunder.
J.A. 40 (emphasis added). Thus, under the plain language of the Subcontract Agreement, the parties “otherwise” provided that disputes which arise under the Subcontract Agreement must be submitted to litigation in Georgia unless Beers elects arbitration.
Despite this contractual provision, however, TechnoSteel asserts that we should ignore the language of Article 14.h requiring the litigation of such disputes because, during negotiations, the parties agreed to delete a portion of Beers’ standard Subcontract Agreement, specifically Article 14.e. See J.A. 26. Article 14.e, had it been included in the final Subcontract Agreement, would have provided that:
All disputes or claims between Contractor and Subcontractor arising out of this Agreement, or the performance of any work hereunder, shall be decided by litigation unless the Contractor, at its sole opinion, advises the Subcontractor within 30 days of the dispute or claim arising that Contractor elects to have the dispute or claim decided or resolved by way of arbitration. In such event, the Contractor shall provide the Subcontractor written notice of its election, the Subcontractor shall be bound by the election, and the arbitration proceeding shall be conducted pursuant to the Construction Industry Arbitration Rules as issued by the American Arbitration Association then in effect. All such arbitration proceedings shall be held in Atlanta, Georgia, and judgment upon the arbitration award may be entered by any court having jurisdiction.
J.A. 39. By agreeing to delete this provision, TechnoSteel asserts, the parties intended to remove litigation as an accepted method of dispute resolution altogether and, instead, to have the arbitration provision of Article 4.5.1 of the General Conditions of the Owner/Beers Contract control the resolution of all disputes by virtue of its incorporation into the Subcontract Agreement. TechnoSteel further asserts that we should also ignore the seemingly unilateral right of Beers to demand arbitration, which quite clearly remained by virtue of the first clause of Article 14.h, because it was also contrary to the intent of the parties evidenced by the deletion of Article 14.e to preserve the mutual right to demand arbitration which would be afforded by the General Conditions.
We find TechnoSteel’s argument to be strained at best. While TechnoSteel argues that the parties intended to eliminate Beers’ ability to unilaterally request arbitration by virtue of its deletion of Article 14.e and to eliminate resort to litigation as a means of dispute resolution altogether, it offers no satisfactory explanation as to why the parties simultaneously neglected to seek any modifications to the clause requiring litigation found in Article 14.h. Beers, on the other hand, persuasively argues that the removal of Article 14.e from the Subcontract Agreement was consistent not only with the intent to eliminate Beers’ right to unilaterally demand arbitration, but arbitration altogether, thereby leaving litigation in Georgia as the sole method by which disputes arising out of the Subcontract Agreement would be resolved. 9
*164 In any event, under the plain language of the dispute resolution portion of the Subcontract Agreement, the parties agreed that “[t]o the extent Contractor does not elect to arbitrate a claim or dispute” under the agreement, all claims or disputes “shall be submitted for resolution to the United States District Court for the Northern District of Georgia or, if that court does not have subject matter jurisdiction, to the Superior Court of Fulton County, Georgia” and agreed that these courts “shall be the sole fora for litigating disputes hereunder.” J.A. 40. Accordingly, we agree with the district court’s conclusion that TechnoSteel failed to establish that an agreement to arbitrate claims and disputes under the Subcontract Agreement exists between Beers and TechnoSteel. We therefore affirm the district court’s order denying TechnoSteel’s petition to compel arbitration under § 4 of the Arbitration Act.
IV.
For the foregoing reasons, we deny Beers’ motion to dismiss TechnoSteel’s appeal for lack of jurisdiction and affirm the district court’s decision denying TechnoS-teel’s motion to compel arbitration.
AFFIRMED.
Notes
. At oral argument, the parties represented that the United States District Court for the Northern District of Georgia has granted Techno Steel’s motion to stay the proceedings pending this court's decision on appeal.
. Immediate challenges to a § 1404(a) transfer are limited to the filing of a petition for writ of mandamus with the transferor circuit court prior to the physical transfer of the file or, once the file is transferred, to the filing of a motion with the transferee district court to retransfer the case.
See Brock v. Entre Computer Ctrs., Inc.,
. Thus, in
McGeorge,
the Tenth Circuit refused to review an interlocutory decision issued by a district court in another circuit prior to the district court's transferring the balance of the action to a district court within the Tenth Circuit.
See
. See also 15A Charles A. Wright, Arthur R. Miller & Edward H. Cooper, Federal Practice and Procedure § 3914.12 (3d ed.1992) (noting the Tenth and Eleventh Circuit view that the transferee circuit court cannot review decision of a transferor court in another circuit, but opining that “it would be better to recognize that the rules assigning district courts to geographical circuits were not drafted for the purposes of denying review” of orders issued by a transferring court in another circuit).
. The D.C. Circuit ultimately refused to exercise jurisdiction over its district court’s interlocutory dismissal of one count of a plaintiff’s complaint after the case had been transferred to a district court outside the circuit because it was not immediately appealable.
See Hill,
. Like our circuit, the D.C. Circuit had previously refused to review transfer orders entered by a district court from another jurisdiction.
See In re Briscoe,
. Thus, unlike here, a party opposing an interlocutory decision which is not immediately appealable is not stripped of its right to appellate review by virtue of a § 1404(a) transfer. For transfer orders, the parly may petition the transferor circuit court for a writ of mandamus or, once transferred, move the transferee court to retransfer the case and secure appellate review of its decision in the transferee circuit.
See Brock,
. Obviously, the better practice would be for the district court to stay any transfer for the thirty-day appeal period and, if an appeal is filed, during the time the appeal from the denial of arbitration is pending in our court. According to representations made during oral argument, the same outcome was achieved in this case by obtaining a stay of the litigation in the transferee forum. However, á stay entered by our district court would be the better and easier course.'
. Under either argument, the reference to Beers' “election] to arbitrate a claim or dispute hereunder” in the first phrase of Article 14.h only calls into question whether Beers had the remaining right to demand arbitration unilaterally, not whether TechnoSteel ever had a right to do so. Because Beers did not attempt to unilaterally demand arbitration, we need not decide whether the parties' decision to delete Article 14.e indicates a mistaken failure to also delete the first phrase of Article 14.h.
