6 Utah 363 | Utah | 1890
Lead Opinion
Tbe appellant filed bis complaint in tbe district court, in wbicb be alleged, in substance, that tbe respondent was tbe owner of tbe lot described; that he made a contract with one Y. H. Harding to erect a building thereon; that, in pursuance of a contract with the latter, appellant performed labor on tbe building to tbe amount of $207, no part of wbicb bad been paid; that he served on respondent notice of tbe amount due him as such sub-contractor, and also filed for record bis claim, as required by tbe statute. The usual prayer was added, and tbe action was commenced within ninety days after tbe claim was filed for record. Tbe court sustained a demurrer to tbe complaint, because it did not contain an averment of any amount due on tbe contract with the owner at tbe time tbe alleged lien of tbe plaintiff attached. This ruling tbe appellant assigns as error.
To decide the question raised, it is necessary to construe certain provisions of Chapter 1 of the Compiled Laws of Utah of 1888 defining mechanics’ liens, and providing for their enforcement. Section 3806 of that chapter is as follows : “ Every person performing labor upon or furnishing materials to be used in the construction * * * of any * * * building lias a lien upon the same for the work or labor done or materials furnished, * * * whether done or furnished at the instance of the owner of the building * * * or his agent, but the aggregate amount of such liens must not exceed the amount which the owner would be otherwise liable to pay.” The provisions of this section, giving the person performing the labor or furnishing the materials a lien, whether the same is done or performed at the instance of the owner or his agent, manifests an intention to confine the lien to such persons as have express or implied contracts with the owner; or, in other words, an intention not to include in its provisions a lien in favor of a sub-contractor or in favor of persons performing- labor or furnishing materials at the instance of such sub-contractor. The language of the last clause of the section, viz., “ but the aggregate amount of such liens must not exceed the amount which the owner
If the owner may pay the contractor in advance the full amount of the contract, he may in that way defeat the subcontractor’s lien, because, as we have seen, the owner cannot be compelled to pay more than that amount. While the owner may pay the contractor for labor when performed and materials when delivered, as payment therefor becomes due before the subcontractor or other person at his instance commenced work or the delivery of materials, he cannot by payment in advance, or by payment of any kind to the contractor after the subcontractor commences work or the delivery of materials, defeat or diminish the amount of the subcontractor’s lien, or the amount of the lien of any person performing labor or furnishing materials at his instance. When the contractor has performed the labor or delivered the materials, and is entitled to his pay therefor, the owner ought to pay him, if the right of the subcontractor has not intervened. The owner of premises, contracting with a builder for the erection of a house thereon, is required to anticipate the rights of subcontractors, and persons performing labor and furnishing-materials at their instance, before paying the contractor in advance. The owner is presumed to observe the presence of subcontractors and other persons performing labor upon his building, or delivering materials therefor; and the law requires him to know that he cannot defeat or diminish any lien in their favor by any payment to the contractor-in advance, or by any payment he may make to him after the subcontractor or other person doing work or furnishing-materials at his instance has commenced work or the de
The lien is maintained by the service of notice within thirty days after the work or the delivery of materials commences, but the work may be done and the materials delivered before that time; and if the owner may make payment to the contractor during that time, and in that way the sub-contractor may be deprived of his lien, the service would be an idle performance. The legislature could not have intended a construction that would probably be attended with such consequences. Section 3,810 of the same chapter prefers the lien given in the chapter to any other that may have attached or been created subsequent to the time when the building, improvement or structure was commenced; also to any such lien of which the lienholder had no notice, and which was unrecorded at the time the-building was commenced. This section requires other
We are of the opinion that the aggregate amount of liens of the contractor, sub-contractor, and of the persons performing labor and furnishing materials at the latter’s request, cannot exceed the amount of the contract with the owner; that the owner may continue to pay the contractor for labor done and materials furnished, as payment therefor becomes due, until the sub-contractor commences work, or the delivery of materials; and that the owner can make no other payments that will affect the amount of the subcontractor’s lien, or the lien of other persons performing labor on the building, or delivering materials therefor, at his request; and that the amount of the sub-contractor’s lien, and the lien of those performing labor and delivering materials at his request, cannot exceed the amount of the contract with the owner, after deducting from that the amount paid by the latter upon such contract, for labor performed and materials furnished, as before stated. We hold that the complaint should contain an allegation of the amount of the contract with the owner, less any payment for labor performed and materials furnished under the same, made before the plaintiff commenced work or the delivery of materials on his sub-contract. For the reasons stated, the judgment of the court below is affirmed.
Concurrence Opinion
I concur in tbe affirmance of tbe judgment in this case. But I do not concur in tbe construction of tbe lien law of tbis territory, as stated in tbe opinion of tbe chief justice; for I tbink tbat tbe sub-contractor is entitled to claim a lien for tbe work and labor and material furnished by him for the amount due tbe contractor at tbe time be commenced furnishing the materials or doing tbe work, or tbat should subsequently become due, and for no more, and tbis right to a lien is waived if tbe sub-contractor does not give tbe notice required by tbe statute.