TC Contracting, Inc. v. 72-02 Northern Blvd. Realty Corp.TC Contracting, Inc. v. 72-02 Northern Blvd. Realty Corp.
Ordered that the judgment is affirmed, with costs.
“Courts are bound by an arbitrator’s factual findings, interpretation of the contract and judgment concerning remedies. A court cannot examine the merits of an arbitration award and substitute its judgment for that of the arbitrator simply because it believes its interpretation would be the better one. Indeed, even in circumstances where an arbitrator makes errors of law or fact, courts will not assume the role of overseers to conform the award to their sense of justice” (Matter of New York State Correctional Officers & Police Benevolent Assn. v State of New York, 94 NY2d 321, 326 [1999]). Nor may the reviewing court “re-weigh or re-examine the evidence” (Matter of McMahan & Co. [Dunn NewFund I], 230 AD2d 1, 5 [1997] [internal quotation marks omitted]).
However, in addition to the grounds listed in
The Supreme Court properly determined that the arbitration award did not violate a strong public policy, was not irrational, and did not clearly exceed a specifically enumerated limitation on the arbitrator’s power (see Matter of United Fedn. of Teachers, Local 2, AFT, AFL-CIO v Board of Educ. of City School Dist. of City of N.Y, 1 NY3d 72, 79 [2003]).
Rivera, J.P., Skelos, Angiolillo and Balkin, JJ., concur.