ORDER
This matter is before the Court on the Motion to Dismiss Plaintiffs’ First, Third, Fourth and Fifth Claims for Relief [Docket No; 10] filed by defendants Nextel West Corp., Nextel Finance Company, Nextel Communications, Inc., and Sprint Communications, Inc. (“Sprint”) (collectively, “Nextel”). The Court has jurisdiction pursuant to 28 U.S.C. § 1332.
I. BACKGROUND
■ The complaint sets forth the following allegations, which, for the purpose of ruling on the instant motion to dismiss, the Court takes as true. See Alvarado v. KÓB-TV, LLC,
Plaintiff TBM Land Conservancy, Inc. (“TBM”) brings claims related to Nextel’s termination of a “Communications Site Lease Agreement” (the “Site Lease”). TBM and one of Nextel’s predecessor entities executed the Site Lease in March 1997. Docket No. 3 at 1-2, ¶¶ 1, 2, 7-8. The Site Lease granted Nextel
Section 11.1 of the Site Lease' provides, in pertinent part, that Nextel may terminate the Site Lease without further liability “after the initial five (5) year term, if [Nextel] determines that the Premises are
II. STANDARD OF REVIEW
The Court’s function on a Rule 12(b)(6) motion for failure to state a claim upon which relief can be granted is not to weigh potential evidence that the parties might present at trial, but to assess whether the plaintiffs complaint alone is sufficient to plausibly state a claim. Fed. R. Civ. P. 12(b)(6); Dubbs v. Head Start, Inc.,
The “plausibility” standard requires that relief must plausibly follow from the facts alleged, not that the facts themselves are plausible. Bryson v. Gonzales,
III. ANALYSIS
A. Breach of Contract
Nextel argues that TBM has not stated a claim for breach of contract because the Site Lease gives Nextel the right
The parties agree that Nextel’s letter dated August 27, 2013 accurately reflects Nextel’s reasons for terminating the Site Lease.
The August 27, 2013 letter states, in relevant part:
The Site’s older 2G (second generation) iDEN technology performed well in the past for the voice and direct connect radio communications for which it was designed. However, today’s customers demand data-centric multi-media communi'cations, including simultaneous operation of multiple applications, all *of . which requires [sic] the 3G and 4G speeds of the newer CDMA, EVDO, WiMax, LTE .and Network Vision technologies. Nextel; has determined that the features and functionality offered by these new technologies being deployed at other site locations by Sprint renders this Nextel iDEN site technologically ■ obsolete.
Docket No: 10-3 at 2.
The relevant provision" of the Site Agreement grants Nextel the right to terminate its lease without penalty “if [Nextel] determines that the Premises‘are not appropriate for its operations for technological- reasons, including, without limitation, signal interference.” Docket No. 10-1 at 5. TBM argues that the. Site Lease requires Nextel to make a determination “that the groundr — just the ground” covered by the Site Lease was inappropriate for Nextel’s operations for technological reasons. Docket No. 14 at 6 (emphasis in original). Nextel responds that a number of courts have considered substantially identical claims.and have held that, under language similar to that-contained , in the Site Lease, Nextel’s determination that .the technology installed on the .relevant site was no longer needed to operate its communications network was sufficient to terminate the agreement. The cases that Nextel.. cites, Seachase Condominium Owner’s. Ass’n, Inc. v. Nextel WIP Lease Corp.,
Two courts have considered Nextel agreements that, like the Site Lease, permit Nextel to terminate for technological (and not economic) reasons. In Lofty Enters., Inc. v. Nextel Commc’ns of the Mid-Atl., Inc.,
In Pub. Storage v. Sprint ‘Corp.,
The Court finds Pub. Storage’s reasoning persuasive. The Site Lease provided Nextel with the discretion, after the expiration of the initial five-year term, to terminate, the lease for .any “technological ■reason” that it determined made the Site inappropriate for the operation of its network. While such discretion was not unfettered, after plaintiff asked that Nextel justify its grounds, for terminating the lease, Nextel provided its reason. As reflected in the August 27,2013 letter, Docket No. 10-3 at 2, Nextel’s operations evolved away from the technology installed on the Site and Nextel had access to other facilities that were sufficient to satisfy its needs. Plaintiff interprets this explanation as admitting that the reason that Nextel terminated the lease was “because the Nextel facilities situated on the Ground Lease were duplicative of facilities operated by Sprint.” Docket Ño. 14 at 9. Accepting this interpretation as correct, the Court finds that it satisfies the “technological reason” requirement of the contract.
Neither party defines the word “technological.” Merriam-Webster’s Dictionary defines “technological” as “of, relating to, or characterized by technology.”
Even if the Court found that the phrase “technological -reasons” was ambiguous and considered plaintiffs extrinsic evidence that the parties eliminated “economic reasons” from the termination provision, the result would be the same. The dividing line between technology and economics is blurry in the wireless communications industry, but the redundancy that Nextel cited had its origins in the integration of Nextel and Sprint’s networks. Here, as in Pub. Storage, “since other sites housing technologically-appropriate ' infrastructure already provided coverage in the affected areas,” the Site was no longer “appropriate for [Nextel’s] operations.. .for technological reasons.” Pub. Storage,
Because the Court has determined that Nextel has provided a “technological reason” for terminating the lease, Plaintiff has failed to state a plausible claim for breach of contract.
B. Implied Covenant of Good Faith and Fair Dealing
“Colorado, like the majority of jurisdictions, recognizes that every contract contains an implied duty of good faith and fair dealing,” Amoco Oil Co. v. Ervin,
Nextel argues that TBM’s claim for breach of the implied covenant of good faith and fair dealing should be dismissed because TBM seeks to “write into the Site Lease ... a requirement that Nextel West ‘produce technological evidenee/data which would establish... that the Site was/is no longer appropriate for its operations for technological reasons.” Docket No. 10 at 9. The Court agrees. Plaintiffs good faith and fair dealing claim is premised on Nextel’s failure, after repeated requests, to provide “evidence/data” that supports its
IV. CONCLUSION
For the foregoing reasons, it is
ORDERED that defendants , Nextel West Corp., Nextel Finance, Company, Nextel Communications, Inc., and Sprint Communications Inc.’s Motion to Dismiss Plaintiff’s First, Third, Fourth, and Fifth Claims for Relief [Docket No. 10] is Granted, it is further
ORDERED that plaintiff TBM‘ Land Conservancy, Inc.’s first, third, fourth, and fifth claims for relief are dismissed with prejudice. Plaintiff’s second claim remains pending.
Notes
. For ease of reference, although. TBM at times refers to actions taken by Nextel's predecessor entity, OneComm Corporation, N.A., the Court will refer to all such actions as if they had been performed by Nextel. See Docket No. 3 at 2, ¶ 8. . .
. Nextel removed this action on January 20, 2015. Docket No. 1.
. Nexteí attaches the August 27, 2013 letter in its entirety to its motion to dismiss. See Docket No. 10-3. The letter, which the complaint relies on, is properly considered in resolving Nextel’s Rule 12(b)(6) motion. See Utah Gospel Mission v. Salt Lake City Corp.,
. Attached to defendants' motion as Exhibit E. See Docket No; 10-5.
. Although it is not relevant to the Court’s analysis of Nextel’s motion to dismiss, TBM states that, when it negotiated the Site Lease with Nextel, it insisted on removing Nextel’s right- to terminate for "economic reasons" from Nextel’s standard agreement as a condition of entering into the contract. Docket No. 14 at 5-6.
. Technological, Merriain-Webster’s Dictionary Online, http://www.merriam-webster. com/dictionary/technological (last visited September 8, 2015).
. Nextel argues, and TBM does not dispute, that if plaintiff’s breach of contract claim fails, its claims for tortious interference and ’ attorneys’ fees fail as well. See Docket No. 10 at 9-11. Accordingly, Nextel’s motion will be granted as to those claims.
