In 1969 the plaintiff entered into two franchise agreements with the defendant under which the plaintiff undertook to operate an International House of Pancakes in Springfield and one in Natick. Disputes arose as to the amounts due to the defendant, and another agreement was signed by the parties on March 15, 1974. That agreement provided for the concurrent execution by the plaintiff of two consent judgments permitting the defendant to repossess the franchises upon default by the plaintiff in his obligations of payment. The defendant, however, agreed not to use the consent judgments unless the franchisee (plaintiff) should fail to cure any default within ten days after receipt of written notice. After the defendant attempted to enforce one of the consent judgments, the plaintiff brought suit to restrain their use. The defendant filed a counterclaim for a balance owing from the plaintiff for open account indebtedness and a balance due under a note executed at the time of the March 15, 1974, agreement.
After hearings before a master, the trial judge entered a judgment dismissing the plaintiff’s complaint and awarding the defendant damages on its counterclaim. The injunctive aspects of this case have become moot, and the questions remaining relate to damages.
The plaintiff’s appeal purports to raise four issues for review. Two relate to a claim that the defendant failed to give the plaintiff proper notice under paragraph 8 of the March 15 agreement, as set forth in the margin.
1. We do not need to decide whether under the circumstances of this case the notice provisions were complied with or, as found by the master, waived. Even if the plaintiff is correct that he never received the notices required under the March 15, 1974, agreement,
The plaintiff has indeed been damaged but the findings establish that the damage was not caused by the
2. The plaintiff also argues that the judgment on the defendant’s counterclaim was incorrect because the plaintiff was entitled to a credit under a class action settlement in a Federal court. However, the plaintiff bases this argument on findings of the master contained in a supplemental report. That report was never adopted by the trial judge and hence those findings of the master are entitled to “no weight whatever.” Peteros v. Peteros,
Judgment affirmed.
Notes
Paragraph 8 reads in part as follows: “It is agreed and understood between the parties that the consent judgments for possession of each of the units referred to above shall not be used by the Fran
The notice as to the Natick franchise dated January 27, 1975, which was given after the plaintiff brought this action, may have been in proper form, but we do not need to discuss the nature and effect of this notice in view of our holding as to damages.
The order of reference to the master was in the usual form and did not require him to report the evidence. After the filing of the plaintiff’s notice of appeal, at a time when it was far too late, the defendant moved to amend the order of reference and to file a transcript with the record on appeal. The judge incorrectly allowed the motion. Cook v. Scheffreen,
The plaintiff argues that the giving of notice was a condition precedent to the defendant’s use of the consent judgments and that the plaintiff’s inability to cure his default is irrelevant. It is true that the inability to cure the default is irrelevant to the issue whether Taylor had the right to receive notice and, if the giving of notice is a condition and not merely a promise, a question we do not decide, such inability would also be irrelevant to the issue whether the defendant’s failure to give proper notice would excuse the plaintiff from some performance on his part. 5 Williston, Contracts § 675, at 187 (3d ed. 1961). See Spooner v. General Acc. Fire & Life Assur. Corp.,
