J.R. Miller entered into an oral agreement with one A.D. Adams for the said Adams to repair the roof on a certain building in the town of Minden, La. The agreement or contract consisted of Mr. Miller instructing Mr. Adams to repair the roof. There was no definite agreement as to price or as to the time in which the work was to be completed. Adams purchased from the plaintiff herein the material which was used in making the repairs; the bill, amounting to $291.93, having been purchased and delivered on the following dates:
1932 Jan. 9 Inv. 1703-R $ 52.50 $ 52.50On October 10, 1932, following the last delivery on August 12, 1932, plaintiff filed a lien against said building with the clerk of the court of Webster parish, La., in accordance with the provisions of Act No.Jan. 14 Inv. 1724-R 51.00 51.00
Jan. 25 Inv. 1748-R 122.63 122.63
Feb. 13 Inv. 1768-R 20.20 20.20
Mar. 21 Inv. 1833-R 33.60 33.60
Aug. 12 Inv. 1985-R 12.00 12.00 _______ ______ Balance due Taylor-Seidenback Company, Inc. $291.93 $291.93
On May 15th following, plaintiff filed this suit against the owner of the building, J.R. Miller, praying for judgment and for recognition of its lien as a furnisher of material. On trial below there was judgment in favor of plaintiff, and defendant has perfected an appeal to this court.
Several exceptions were filed in the court below, none of which is urged here. The defense urged is, first, that the lien is without effect, due to the failure of the clerk to record it until the 14th of November, which was ninety-four days after the date the last material was furnished; and, second, that the job was completed on March 21st, and the material furnished on August 12th was for patching defects in the former completed job, and was no part of the original job or contract; therefore, the lien was filed more than sixty days after the material was furnished and the job completed.
Section 12 of Act No.
The first defense urged is without merit. When plaintiff filed its lien on October 10, 1932, it did all the law required of it and all it could possibly do. It was not within plaintiff's power to actually record the instrument. The filing of the instrument by it within sixty days after the last material was furnished was all that is required by the act creating the lien. Shreveport Long Leaf Lumber Company, Inc., v. Spurlock,
The second defense urged here, under the ruling of this court in the cases of Shreveport Long Leaf Lumber Company, Incorporated, v. Spurlock, cited supra, Cox et al. v. Rockhold,
It is difficult to see how Mr. Adams could be made a contractor in this case. Under the testimony, there was never any contract between him and Mr. Miller. He was in reality an agent and employee of the owner, Mr. Miller, who was repairing his own roof. Be that as it may, the question is not raised, and, for the purpose of a decision in this case, we can assume that Adams was a contractor. The preponderance of the testimony, and without contradiction, is that the last material which was delivered by plaintiff on August 12, 1932, was necessary to complete the job of repairing the roof and was used for that purpose. *Page 844
The lien was properly filed by plaintiff fiftynine days later and within the time allowed by section 12 of Act No.
We find no error in the judgment of the lower court, and it is affirmed, with costs.
