Taulbee v. Moore

106 Ky. 749 | Ky. Ct. App. | 1899

JUDGE BURNAM

delivered the opinion op the court.

This suit was instituted by appellee to recover a balance of $258.68 alleged to be due upon a contract made with appellant to build an addition to his house at an agreed price of $458.68, $200 having been paid in cash.

Appellant, in his original answer to appellee’s claim, said that the work was not done in a workmanlike manner, and alleged that it was a part of the parol contract between them that the brickwork was to be executed so as to leave the inside surface of the walls as smooth as the outside; *752that the joints were all to be struck and pointed, so as not to require plastering, and that appellee had violated this provision of the contract, and left the inside surface of the wall so rough and unsightly as to require it to be plastered, which would cost him at least forty dollars; that he had been damaged in the sum of twenty-five dollars by reason of the lintels put in the building not being of good material; that the guttering had been changed, so as to cause him to spent three dollars; that appellee failed to make a valley in the roof, which caused the water to run down into the building, to his damage in at least the sum of ten dollars, and that he had allowed rubbish to fall into his cellar, to his damage of two dollars and fifty cents; that appellee was indebted to him for forty-five dollars for medical services rendered to one Hill, at his special instance and request, and for an account due the firm of Taulbee & Hayden, which had been assigned to him, for twenty-nine dollars; and by an amended petition appellant alleged that it would cost him at least $300 additional expense to take down the brick walls erected by appellee and rebuild them with struck joints on the inside, as provided by the contract, — all of which .he pleads by way of set-off and counterclaim against appellee.

The trial resulted in a verdict and judgment for appellee for the amount sued for, which we are asked to reverse on account of several alleged errors to appellant’s prejudice.

It is contended that the court erred in permitting appellee to state to the jury that the work was done according to the contract.

As the contract was a verbal one, and the parties differ essentially as to its terms, it seems to us, after giving his version of it, appellee was entitled to state *753to the jury that the work had been performed in accordance therewith.

Another ground relied on is that the trial court erred in refusing to allow appellant to introduce his son as a witness to testify to facts which should have been properly introduced in chief after appellee had closed his testimony.

The only reason assigned why this witness was not introduced at the proper time is that counsel for appellant did not know what his testimony would be at that time. This is a matter that rests very largely in the discretion of the trial judge, and will not be interfered with here unless it is manifest that there has been a palpable abuse of discretion, which fact does not sufficiently appear from the testimony in the record.

But the chief ground of complaint is that the trial court erred, to appellant’s prejudice, in the instruction as to the measure of damages which reads as follows:

“The measure of damages in the case is the difference, if any, between the value of the building constructed as it is and what it would have been if it had been constructed according to the contract.”

Appellant insists that it was the duty of the court to have told the jury “that, if they believed from the evidence that plaintiff was to so construct the building as to make the inside of the wall as smooth as the outside, and of first-class material, and had not done so, that they should find for appellant, and fix the damages at such a sum as they believed from the evidence would be necessary to take away said walls and replace them by walls of first-class material and workmanship, and as smooth on the inside as on the outside.”

There is no testimony in this case which conduces *754to show that the walls erected by appellee for appellant were not a reasonably good job, and fitted for the purpose for which they were intended. There were no plans or specifications for appellee’s guidance in their construction, and they seem in the main to conform to the designs testified to by both parties. The proof shows that it is impracticable to build a brick wall only one brick thick so as to leave the surface on both sides perfectly straight and smooth. The usual building brick is twice as long as it is wide, and it is therefore manifest that when laid laterally in the wall there is bound to be a space between them for mortar to hold them together, and that bricks laid in this way will necessarily project a little further on one side than header courses of the same size brick. This difficulty can be easily’overcome in thicker walls, but it is not apparent how it could be accomplished in a wall only nine inches thick. Besides, the testimony shows that appellant paid $200 on the job, after the greater part of the brickwork had been completed, without objection to the manner in> which it was being done.

We do not think the measure of damages contended for by appellant is a sound or just one. “The rule of law is that, where a party sustains loss by reason of a breach of contract that he is, so far as money can do it, entitled to be placed in the same situation with respect to damages as if the contract had been performed, and that these damages should be limited to such as may be reasonably supposed to. have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it.” (See Lawson on Contracts, p. 250.)

If appellant is right in his theory', appellee might be mulcted in damages in a sum equal to the entire contract price agreed to be paid to him for the job of work on ac*755count of a comparatively inconsequential failure to literally comply therewith, and which did not affect the real value of the work done by him. Whilst it may be true that if a contractor should disregard the plans and specifications under which a building was to be erected, and erect one substantially dissimilar, the owner might refuse to receive or pay for the property, but where there has been, as in this case, a substantial compliance, it seems to us that the true criterion of damages is that laid down by the court.

We think the instructions offered by appellant were objectionable, for the reason that they gave undue prominence to certain portions of the testimony. Besides, as the jury found that appellant was not damaged at all in the erection of the building, it does not appear that he was prejudiced by a mere error in the standard for the measurement of damages; and, after a careful consideration of the case, we are disposed to think that there was no error to appellant’s prejudice in the instructions given the jury.

For reasons given, the judgment is affirmed.