106 Ky. 749 | Ky. Ct. App. | 1899
delivered the opinion op the court.
This suit was instituted by appellee to recover a balance of $258.68 alleged to be due upon a contract made with appellant to build an addition to his house at an agreed price of $458.68, $200 having been paid in cash.
Appellant, in his original answer to appellee’s claim, said that the work was not done in a workmanlike manner, and alleged that it was a part of the parol contract between them that the brickwork was to be executed so as to leave the inside surface of the walls as smooth as the outside;
The trial resulted in a verdict and judgment for appellee for the amount sued for, which we are asked to reverse on account of several alleged errors to appellant’s prejudice.
It is contended that the court erred in permitting appellee to state to the jury that the work was done according to the contract.
As the contract was a verbal one, and the parties differ essentially as to its terms, it seems to us, after giving his version of it, appellee was entitled to state
Another ground relied on is that the trial court erred in refusing to allow appellant to introduce his son as a witness to testify to facts which should have been properly introduced in chief after appellee had closed his testimony.
The only reason assigned why this witness was not introduced at the proper time is that counsel for appellant did not know what his testimony would be at that time. This is a matter that rests very largely in the discretion of the trial judge, and will not be interfered with here unless it is manifest that there has been a palpable abuse of discretion, which fact does not sufficiently appear from the testimony in the record.
But the chief ground of complaint is that the trial court erred, to appellant’s prejudice, in the instruction as to the measure of damages which reads as follows:
“The measure of damages in the case is the difference, if any, between the value of the building constructed as it is and what it would have been if it had been constructed according to the contract.”
Appellant insists that it was the duty of the court to have told the jury “that, if they believed from the evidence that plaintiff was to so construct the building as to make the inside of the wall as smooth as the outside, and of first-class material, and had not done so, that they should find for appellant, and fix the damages at such a sum as they believed from the evidence would be necessary to take away said walls and replace them by walls of first-class material and workmanship, and as smooth on the inside as on the outside.”
There is no testimony in this case which conduces
We do not think the measure of damages contended for by appellant is a sound or just one. “The rule of law is that, where a party sustains loss by reason of a breach of contract that he is, so far as money can do it, entitled to be placed in the same situation with respect to damages as if the contract had been performed, and that these damages should be limited to such as may be reasonably supposed to. have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it.” (See Lawson on Contracts, p. 250.)
If appellant is right in his theory', appellee might be mulcted in damages in a sum equal to the entire contract price agreed to be paid to him for the job of work on ac
We think the instructions offered by appellant were objectionable, for the reason that they gave undue prominence to certain portions of the testimony. Besides, as the jury found that appellant was not damaged at all in the erection of the building, it does not appear that he was prejudiced by a mere error in the standard for the measurement of damages; and, after a careful consideration of the case, we are disposed to think that there was no error to appellant’s prejudice in the instructions given the jury.
For reasons given, the judgment is affirmed.