169 Ind. 172 | Ind. | 1907
Appellants constructed a sewer system within and for the corporate town of New Castle, and upon completion of the same brought this action to compel payment of the contract price and for certain extra work done upon special orders. Appellee answered by general denial, and also filed a cross-complaint, alleging a disagreement as to the amount due, and asking for an accounting, to which appellants answered in denial. A trial was had upon the issues so joined, a special finding of facts made by the court, and conclusions of law stated in favor of appellants in accordance with the facts found. A judgment was rendered for the sum so found due. The judgment further provided for payment out of assessments to be made against the property benefited, required appellee to cause the proper assessments to be made and collected and to issue and sell bonds to provide funds for the payment of such sum, and exempted appellee from any personal liability, except for the costs of the action.
It is alleged upon this appeal that the court below erred in overruling appellants’ demurrer to the cross-complaint, in each conclusion of law stated, and in overruling the motion for a new trial.
The special findings of the court contained, among other facts-, in substance, the following: That upon competitive bids appellants were duly awarded the contract to construct the sewer, and entered into a written agreement with appellee for the performance of the work, whereby appellants were to receive and accept
“as full compensation for all work, labor and material used in the construction of said sewers, and all things specified and required in the plans, specifications and profiles thereof, the sum of $1.14 per lineal foot of said sewers, measuring only the center line of said sewers including all branches and tributaries shown on the plans, profiles and specifications after completion, and not measuring service connections or any other lines specified and named in said specifications, it being the intention of this contract that the price aforesaid shall be taken and received as full and complete compensation for the full completion of said sewers, together with all the requirements and incidents thereto specified in the plans, specifications and profiles thereof.”
It was further provided in the contract:
“The contractors shall do such extra work in connection with their contract as the engineer may, in writing, specially direct, and in a first-class manner, but no claim for extra work shall be allowed unless the same is done in pursuance of a written order, as aforesaid, to do the work as such, and the claim presented at the first estimate after the work is done. Payment therefor shall be made according to the schedule of prices herein contained, as far as applicable. Extra work not coming under the classifications of the schedule prices shall be paid on a basis of ten per cent in advance of the actual cost of labor and materials as determined by the engineer.”
Appellants were duly directed to make certain additions, extensions and tributaries to the sewer system as originally
The amount due for 35,021 feet of sewer under the original contract at $1.14 per lineal foot was $39,923.94, and for extra manholes, basins and inlets on said line $2,005, from which $456 was deducted for flush tanks and lamp-post holes omitted, making the total sum due under original contract $41,472.94. In addition to this the sum of $11,967.70 was found due for extra work and materials particularly specified and computed at the rates fixed in appellants’ bid so far as applicable. The sum of $355 was allowed for hauling dirt, $7,980 for paving street, and on the amount of $3,991.20, the cost of furnishing and laying certain tile, the court allowed ten per cent additional, making $399.12, and deducted $1,000 as agreed upon between the parties in consideration of appellee’s assumption of the duty of appellants to repair certain streets, leaving the total sum of $61,174.76 due appellants for the aggregate work. The work was completed January 1, 1903, and interest at six per cent was allowed from that date, amounting to $4,690.05, making the total sum to which appellants were found to be entitled $65,864.81.
No error having been made to appear, the judgment is affirmed.