55 Ind. 496 | Ind. | 1876
Samuel Goddard, Samuel Goddard, Jr., and Thomas Goddard, partners under the name and style of Goddard & Sons, brought this- complaint against Charles H. Talbott, Edward Van Kuren, Henry Helm, Conrad Russe, Victor Plogsterth, George W. Hill and David D. Long, to foreclose a mechanic’s lien against property owned by Charles H. Talbott. George W. -Hill and David D. Long, partners under the style of Hill & Long, brought their cross-complaint, in the same proceedings, against Talbott, Van Kuren, Helm, Russe and Plogsterth, their codefendants, to foreclose a mechanic’s lien upon the same property. The pleadings need not he stated, as no question arises upon them. The names of the parties, and the respective demands they claim, will sufficiently appear in the following special findings by the court:
“1st. That on and prior to the 1st day of July, 1873, the defendant Charles IT. Talbott was the owner of the following real estate, in Marion county, in the State of Indiana, to wit: Lot number six, and six feet and three
“2d. That on or about the 1st day of July, 1873, the said Charles H. Talbott, being then the owner of said real estate, entered into a contract with the defendant Van Kuren, to construct a new, two-story, brick dwelling-house, and stable, on said real estate, the said VanKuren agreeing to furnish all the materials, and construct said house, for a certain price agreed upon between the said Talbott and the said Van Kuren, to be paid by the said Talbott, to the said Van Kuren, as the work on said house and stable progressed.
“ 3d. That the plaintiffs furnished stone materials, that were used in the construction of said dwelling-house, of the value of three hundred and sixteen dollars and four cents; said stone was furnished at the request, and on the ordei’, of said Van Kuren, the contractor with said Talbott, and used in the said dwelling-house; and the said plaintiffs, before the expiration of sixty days after the completion of said house, to wit, before said house was completed, filed their notice of intention to hold a lien, for the value of said materials, on said real estate, and on the house erected thereon, in the recorder’s office of Marion county, and caused the same to be recorded, in all things as alleged in the complaint.
“4th. That the plaintiffs have not been paid for said materials, so used in said house, or for any part thereof; and said Talbott has fully paid the said Van Kuren, for all of the work done, and for said materials furnished and used in the construction of said house, in all things according to the terms of the contract between the said Talbott and Van Kuren, and that such payment was made by said Talbott, to said Van Kuren, before the notice of the plaintiffs was filed in the recorder’s office, as before stated.
“6th. That said Van Kuren is a carpenter and builder, and was, at the time he was engaged in constructing the said dwelling-house and stable of the defendant, engaged in constructing twelve other'and different buildings, for other and different parties, in said city of Indianapolis, under contracts with said parties to construct said buildings and furnish all the materials therefor; and at the time of the making of the contract with the defendant Talbott, the said Van Kuren was indebted to the said cross-complainants, Hill & Long, on general account, for lumber and materials, in the sum of three thousand dollars. That during the progress of the work upon the defendant Talbott’s house, and during the time the cross-complainants were furnishing the lumber in their complaint mentioned, they were furnishing other lumber and materials for the other and different buildings so being erected by said Van Kuren; that all of the lumber, so furnished by the cross«eomplainants and used in the defendant Talbott’s dwelling-house .and stable, together with the lumber furnished for the other buildings being erected at the same time by the
“ 7th. On the 1st day of July, 1873, the said Hill & Long had a settlement of their general account, and Van Kuren, being indebted to said Hill & Long, in about the sum of three thousand dollars, made his three several notes to said Hill & Long for about the sum of one thousand dollars, payable, respectively, in forty-five, sixty and seventy-five days, each. No lumber furnished and used'in the defendant Talbott’s house was included in the amount of said notes. On the 1st day of August, 1873, the said Hill & Long and the said Van Kuren had another settlement, and the said Van Kuren was at that time indebted to the said Hill & Long, in the further sum of twenty-eight hundred dollars, for which the said Van Kuren executed his note or notes, payable to the said Hill & Long, and the value of the lumber furnished to the said Van Kuren, and used in the construction of the house of the defendant Talbott, during the month of July, was included in said note or notes, so made on the 1st day of August, 1873. The said notes so made, both on the 1st day of July and on the 1st day of August, 1873, were payable in a bank in the State of Indiana, and were by said Hill & Long endorsed and negotiated.
“ 8th. That on the 6th day of July, 1873, the defendant Talbott paid the said Van Kuren the sum of six hundred dollars, and on the 13th day of July the further sum of six hundred dollars, and on the 19th day of July, the further sum of three hundred dollars, and on the 26th day of July, the further sum of two hundred dollars, and on the 2d day of August, the further sum of three hundred and
“9th. That on the 6th day of July, Van Kuren paid at the bank, on one of the notes before that time given by Hill & Long, the sum of eight hundred dollars, and on the 24th day of July, he paid at the bank, on said notes, the further sum of eleven hundred dollars, and afterwards, and prior to the 20th day of September, he paid Hill & Long, on said notes, a further sum of fifteen hundred dollars. That the said payments were made on notes transferred and held by the bank, as before stated, and neither Hill & Long nor the bank had any knowledge from whom the money was received by Van Kuren. That a part of the money was procured from Talbott, but how much is not disclosed by the evidence, and the said payments were applied to the extinguishment of the indebtedness of Van Kuren to Hill & Long, which had accrued before they commenced furnishing any lumber to be used in constructing the house of Talbott.
“ 10th. The residue arising on said notes, after allowing credits for the payments aforesaid, has [not] been paid by said Van Kuren, and that said Hill and Long, before the commencement of this suit, were compelled, as endorsers, to take up said notes, and pay the balance owing on the same to said bank by which they have been discounted.
“ 11th. As conclusions of law, arising on the foregoing facts, the court finds, that the plaintiffs, Samuel Goddard,
“ 12th. As further conclusion of law, arising on the foregoing facts, the court finds that the cross-complainants, Hill & Long, are entitled to have and receive, of the defendant Talbott, the sum of nine hundred and seventy-four dollars and thirteen cents, and that they have and hold a lien upon the real estate and the buildings thereon, described in their cross-complaint and set out in the findings herein, to secure the payme nt of said sum of money, and that they are entitled to a decree for the foreclosure and enforcement of said lien.”
The appellant excepted to each and all of the conclusions of law, as found by the court. The court rendered judgment in accordance with the findings of facts and conclusions of law, above stated, and the appellant appealed to the court in general term, wherein the judgment at special term was in all things affirmed. From the general term he appealed to this court.
It is contended by the appellant that the facts, as found by the court, do not show that the materials furnished by the claimants were furnished for the particular building against which the lien is sought to be established; that it is not sufficient to show that the materials were furnished and used in the building, but that it must appear -that they were furnished for the building, and with the view of securing a lien thereon.,
This point was directly presented to this court in the case of The City of Crawfordsville v. Barr, 45 Ind. 258, wherein it was held, Osborn, J., delivering the opinion of the court, that, “Where materials are furnished for a building, they are furnished on the credit of the building,
The case of Barker v. Buell, 35 Ind. 297, in a single sentence spoken by the court, but not in reference to the questions involved in this case, might seem to favor the appellees; but the main point contested in that case was the sufficiency of the notice to the defendant. It does not support the appellees, and is not in serious conflict with the subsequent decisions of the question before us. Colter v. Frese, 45 Ind. 96, also cited by the appellees, supports our ruling in the present case. It was therein held, that “those performing labor on, or furnishing materials for, the building are entitled to a lien, as provided for.” hTor does this case support the views of the appellees in any respect.
The following authorities, from sister States, are in full harmony with the decisions of this court upon the same question. Cotes v. Shorey, 8 Iowa, 416; Chapin v. The Persse and Brooks Paper Works, 30 Conn. 461; Hill v. Bishop, 25 Ill. 349; Beckel v. Petticrew, 6 Ohio State, 247; Esslinger v. Huebner, 22 Wis. 632; Gorgas v. Douglas, 6 S. & R. 512.
We must hold the law as settled in this State, that to entitle a material man to a lien upon any building, he must show that the materials were furnished for the particular building upon which he seeks to obtain a lien. It
The question remains to be examined, whether the facts found in the case before us bring the rights of the parties within this rule of law. As to Goddard & Sons, the facts show that they furnished materials to the builder, which were used in the construction of the appellant’s building, but they do not show that they were furnished for that particular building. In our opinion, they have not established their lien. With reference to Hill & Long, the facts also show that they furnished materials to the builder, which were used in the construction of the appellant’s house; and show that the same builder, at the same time, was engaged in the erection of twelve other different buildings, for other parties, in the same city, for which Hill & Long were also furnishing materials; that the materials for the several buildings were delivered to the builder, on a general account; that Hill & Long kept a memorandum account of the different houses where said materials were delivered, as ordered by the builder in each instance. As the materials were all delivered to the builder, on a general account between him and the furnishers, it does not appear
No error having been assigned against the judgment of the Q-oddards, the judgment as to Hill & Long is reversed, with costs. Cause remanded for further proceedings in accordance with this opinion.
Petition for a rehearing overruled at the May Term, 1877.