MEMORANDUM AND ORDER
This case arises out of a troubled construction contract between TADCO Construction Corporation (“TADCO”) and the Dormitory Authority of the State of New York (“DASNY”) to build a new dormitory facility on Staten Island. Plaintiff TADCO alleges multiple breach of contract claims against DASNY, and further alleges a due process violation under 42 U.S.C. § 1983
Background
(1)
Contractual Disputes between TADCO and DASNY
a. Project Delays
The following facts are drawn from plaintiffs pleadings and, for purposes of this motion, are presumed to be true. In May 2005, defendant DASNY began soliciting bids for a new ten-bed residence building for the Staten Island Developmental Disabilities Services Office (the “project”). Compl. ¶ 14. The project was structured as a “multi-prime” project, meaning that four prime contractors would perform discrete segments of the project under the direct supervision of DASNY. Id. at ¶¶ 15-16. Four separate prime contracts were therefore awarded: one for general construction work, one for mechanical work, one for electrical work and one for plumbing work. Id.
Plaintiff TADCO, a general construction contractor, bid on and was awarded the contract for general construction work (the “contract”) around June 15, 2005. Id. at ¶¶ 17, 23. Prior to the instant dispute, TADCO had often been awarded state and municipal public works contracts and had previously worked with DASNY several times. Id. at ¶ 13. The contract specified that the project was to be completed by September 29, 2006. See Compl., Ex. A at 2 (contract between TADCO and DASNY).
However, the project was plagued with delays and problems from the outset. Plaintiffs generally attribute these delays to DASNY’s funding problems and DAS-NY’s poor management of the other prime contractors. Id. at ¶¶ 19-24. More specifically, TADCO points to several delays that were caused by events outside of its control and within DASNY’s control. First, plaintiffs allege that their commencement of the project was delayed by approximately five months when DASNY unexpectedly required TADCO to perform some up-front work not included in the plans and specifications, including building a construction fence around the jobsite, id. at ¶¶ 25-29, and probing and underground radar work to locate existing utility lines, id. at ¶¶ 30-34. As a result of requiring this extra work, DASNY agreed to extend the completion date of the project by six weeks, from September 29, 2006, to November 15, 2006. Id. at ¶ 35. Then, a major design defect in the framing of the building set back TADCO’s progress on the project further throughout June and July 2006. Id. at ¶ 41.
Further delays ensued as a result of the slow progress of the mechanical, electrical and plumbing work contractors (collectively, the “MEP contractors”).
Id.
at ¶¶ 42-50. TADCO believed the MEP contractors’ deficient performance was the fault of poor supervision and direction on the part
At the same time these MEP delays were occurring, a dispute erupted between DASNY and TADCO regarding a contract provision that required TADCO to backfill open trenches at the jobsite with soil taken from on-site. Id. at ¶ 62. At some point, apparently during the summer of 2006 (the complaint specifies only “prior to September 2006”), TADCO discovered that the soil at the site was not suitable for use as backfill because of its high moisture content. Id. at ¶ 63. TADCO attributed its late discovery of this moisture problem to DASNY’s failure to provide TADCO with any soil boring logs or geotechnical data. Id. at ¶ 64. Therefore, it asked DASNY to resolve the problem during fall of 2006. However, according to TADCO, DASNY was simply non-responsive. Id. at ¶¶ 66-73.
b. Thomas DeMartino’s Arrests
In November, this unresolved backfill problem provoked a disagreement between an employee of DASNY and an employee of TADCO. One of DASNY’s field representatives and now a named defendant, Tyrone Middleton, ordered DeMartino, TADCO’s onsite project superintendent, to cover the open trenches at the jobsite with wood planks on November 9, 2006. Id. at ¶¶ 75-76. DeMartino refused, explaining that this work was not specified in the contract and would require extra labor, materials, supplies and equipment. Id. at ¶¶ 77-78. Middleton responded this same day by lodging a criminal complaint against DeMartino with the state police officers assigned to the facility, claiming that DeMartino was trespassing. Id. at ¶¶ 80, 134. The complaint additionally alleges that Pat Cinelli, the Director of DASNY’s Statewide Utilities Unit, and/or Jack Kemp, the Chief of Construction Contracts for DASNY, “approved of and authorized” Middleton’s actions in having DeMartino arrested. Id. at ¶ 139. As a result of Middleton’s complaint, DeMartino was arrested, taken to the local precinct and issued a criminal summons for trespassing. Id. at ¶ 82.
Apparently, however, this arrest did not dissuade DeMartino from returning to the job site. In early January 2007, Middleton or some other DASNY personnel lodged a second criminal complaint against DeMartino, who was once again arrested for trespassing at the job site. Id. at ¶¶ 84-86. DeMartino spent one night in jail and was subsequently charged with criminal trespassing. Both of the trespassing charges were subsequently dismissed in their entirety. Id. at ¶¶ 83, 87.
c. Disputed Work
Throughout the course of TADCO’s performance under the contract, DASNY repeatedly directed TADCO to perform “charge order” work, i.e., work not included within the contract fee negotiated.
Id.
at ¶¶ 88-89. DASNY at times used the “disputed work clause” in the contract to force TADCO to perform this work by claiming the work was “disputed.”
Id.
TADCO believed the contract entitled it to
d. Termination of the Contract
At the time TADCO filed the state court lawsuit against DASNY, it estimates that it had completed over eighty-five percent of its work on the project. Id. at ¶ 95. However, TADCO asserts that, although it was willing and able to complete the project, it could not move forward without DASNY resolving the soil problem and problems with the MEP contractors, or responding to several requests for information that TADCO had submitted to DASNY. Id. at ¶¶ 96-99. TADCO’s president reiterated this position in a letter to Jack Kemp, DASNY’s Chief of Construction, on January 2, 2007. Id. at ¶ 99.
DASNY, however, believed that TADCO had failed to perform its obligations under the contract and did not demonstrate the ability to complete the work. Id. at ¶ 103. Although the parties exchanged several letters apparently attempting to come to some agreement, DASNY ultimately chose to terminate the contract with TADCO on January 17, 2007. Id. at ¶¶ 100-07. TAD-CO believes this termination was wrongful. As evidence, it points to the results of an investigation by First Sealord Surety, Inc., the bonding company that issued the performance and payment bonds on the project. Id. at ¶ 108. First Sealord Company’s independent investigation report of March 28, 2007 concluded that “DASNY’s election to terminate TADCO was unjustified and improper.” Id. At the time of termination, DASNY reportedly owed TADCO $79,485.00 for completed contract work and $45,402.31 in retainage, in addition to the money it owed for TADCO’s extra work, none of which has been paid to TADCO. Id. at ¶ 110-11.
Around the same time the contract was terminated, TADCO asserts that James Gray, DASNY’s Managing Director of Construction, Jack Kemp and/or other persons associated with DASNY made false and “defamatory allegations concerning TADCO’s purported failure to perform its obligations under the Contract and to complete the Project,” to the MEP contractors, TADCO’s subcontractors and others within the construction industry. Compl. ¶ 109.
(2)
The Current Action
On the basis of the above facts, TADCO and DeMartino brought the current action in federal court on January 7, 2008. The complaint alleges thirty-nine causes of action, which can generally be grouped as: (1) violations of the Due Process clause under the Fifth and Fourteenth Amendments and 42 U.S.C. § 1983 against DAS-NY, Gray, Kemp and John Does (1st Cause of Action); (2) malicious prosecution, abuse of criminal process and false arrest under the Fourth, Fifth and Fourteenth Amendments and 42 U.S.C. § 1983 against DASNY, Middleton, Cinelli, Kemp and John Doe (2nd-7th Causes of Action); (3) malicious prosecution, abuse of criminal process and false arrest under New York law (34th-39th Causes of Action); (4) wrongful termination of the contract against DASNY (8th Cause of Action); (5) twenty-one breach of contract claims against DASNY (9th-30th Causes of Ac
Defendants have moved under Fed. Rule Civ. Proc. 12(b)(6) to dismiss TAD-CO’s § 1983 due process claim and De-Martino’s federal and state false arrest, malicious prosecution and abuse of process claims (lst>-7th and 34-39th Causes of Action). They first argue that TADCO has not stated a claim that rises to the level of a due process violation and instead is impermissibly attempting to constitutionalize a state law contract claim. With respect to DeMartino’s claims, defendants primarily argue that DASNY had exercised its contractual right to bar DeMartino from the job site and, therefore, DeMartino was in fact trespassing on both the occasions he was arrested. Accordingly, defendants request that all of plaintiffs’ federal claims be dismissed. Although defendants are not at this time challenging the adequacy of TADCO’s state law claims (8th-33rd Causes of Action), they suggest that the court should decline to exercise supplemental jurisdiction over these claims.
TADCO, who is still represented by counsel, has submitted a Memorandum of Law in Opposition to Defendant’s Motion to Dismiss (hereinafter “Pl.’s Mem.”). However, DeMartino, who is now proceeding pro se after TADCO’s counsel withdrew from his representation in October 2008, has submitted no opposition. See Pl.’s Mem. at 18 n. 1. The implications of DeMartino’s failure to respond are discussed infra.
Discussion
(1)
Treatment as a Motion to Dismiss and Standards Governing Motions to Dismiss
Preliminarily, it must be determined whether to treat the instant motion as a motion to dismiss or to convert it into one for summary judgment, given that both parties have submitted some materials outside the pleadings. “When matters outside the pleadings are presented in response to a 12(b)(6) motion, a district court must either exclude the additional material and decide the motion on the complaint alone or convert the motion to one for summary judgment under Fed.R.Civ.P. 56 and afford all parties the opportunity to present supporting materials.”
Friedl v. City of New York,
At this stage, defendants’ 12(b)(6) motion will not be converted into a motion for summary judgment, as defendants have not urged the court to consider its motion as one for summary judgment in the alternative, defendants have not filed an answer and it appears from the documents presented that key facts are yet to be discovered.
See id.
(declining to convert 12(b)(6) motion into motion for summary judgment where no answer had been filed and discovery was not yet complete);
cf. Pani v. Empire Blue Cross Blue Shield,
Nevertheless, one document outside of the pleadings will be considered in ruling on this motion. Although plaintiffs’ complaint attached only a short governing contract, the contract signed between DASNY and TADCO incorporates by reference a longer document containing the contract’s General Conditions and Specifications and Drawings, which defendants have appended to their motion.
See
Decl. of Joel Graber (“Graber Decl.”), Ex. B. The General Conditions, although not part of plaintiffs’ pleadings, are integral to plaintiffs’ complaint, as plaintiffs rely on them to state,
inter alia,
claims that the contract was improperly terminated, that TADCO had a right to payment for the value of extra work it performed and that defendants had no contractual right to exclude DeMartino from the job site.
See Meyer Pincus & Assocs., P.C. v. Oppenheimer & Co.,
As this motion is being treated as a motion to dismiss under Rule 12(b)(6), the critical inquiry with respect to each of plaintiffs’ claims is whether the complaint contains “enough facts to state a claim to relief that is plausible on its face.”
Bell Atl. v. Twombly,
(2)
Claims Under Section 1983
All of plaintiffs’ federal law claims are brought pursuant to 42 U.S.C. § 1983, which provides:
Every person who, under color of any statute, ordinance, regulation, custom, or usage, of any State ... subjects, or causes to be subjected, any citizen of the United States or other person within the jurisdiction thereof to the deprivation of any rights, privileges, or immunities secured by the Constitution and laws, shall be liable to the party injured in an action at law, suit in equity, or other proper proceeding for redress ...”
This section does not, however, itself create substantive rights, but “merely provides a method for vindicating federal rights elsewhere conferred.”
Rateau v. City of New York,
06-CV4751,
As for the second requirement, defendants do not challenge plaintiffs’ claim that DASNY and its employees were acting under color of state law. 2 They do, however, vigorously challenge whether plaintiffs have adequately alleged any violation of their constitutional rights. TADCO’s and DeMartino’s claimed constitutional violations will be examined in turn.
(3)
TADCO’s Due Process Claim
TADCO first asserts a claim, under 42 U.S.C. § 1983, that defendants violated its right to due process under the Fifth and Fourteenth Amendments. In order “to survive a motion to dismiss, a due process claim under section 1983 must allege the deprivation of a constitutionally protected interest.”
Abramson v. Pataki,
a. Property Interest
First, TADCO asserts a property interest in its right to timely payment, which it claims DASNY violated by its delay in processing TADCO’s charge orders and by its failure to pay for work performed by TADCO. In support of this claimed property interest, TADCO cites
Signet Construction Corp. v. Borg,
However, reference to
Signet
alone ignores some of the nuances since developed by the Second Circuit in this area. In particular, in
S & D Maintenance Co. v. Goldin,
Similarly, in
Christ Gatzonis Electrical Contractor, Inc. v. New York School Construction Authority,
the Second Circuit again made clear that a contractor’s property interest in timely payment “arises only where there exists a contractual or state law entitlement to prompt payment.”
Turning to the instant case, the contract and statutory provisions involved similarly do not create the kind of clear entitlement to prompt payment that amounts to a cognizable property interest. TADCO does not itself point to any contractual or statutory provision that it believes creates such an entitlement, and an independent examination of the contract provisions reveals substantial flexibility in payment built into the contract. The contract provides no requirement of prompt payment where the contract is terminated for cause, Def.’s Ex. B at § 10.01; upon termination for convenience, it provides that: “The Owner shall pay the Contractor for Project Work performed ... and accepted by the Owner ....” Id. at § 10.02 (emphasis added). Another contract condition states that the Owner “may make a partial payment to the contractor” during the performance of the contract, but does not appear to require it. Id. § 17.01(A). Instead, the contract requires that:
The Owner, when all the Work is substantially complete, shall pay to the Contractor the balance due ... less:
1. two (2) times the value of any remaining items of Work to be completed or corrected; and
2. an amount necessary to satisfy any and all claims, liens or judgments against the Contractor.
Id. § 17.01(D). This last provision again allows the Owner several grounds on which to withhold payment.
Plaintiffs are also alleging a right to prompt payment for hundreds of thousands of dollars of “charge work,” which DASNY ordered them to complete as “disputed work” under the contractual provisions. Compl. at ¶ 88-89. Per the terms of the contract’s “Claims for Extra Work” provision, however, it appears that the Owner is provided leeway in determining whether this disputed work is to be paid for and in valuing such work. See Def. Ex. B. § 11.01. Moreover, the contract’s section on “Withholding of Payments” gives the owner further authority to withhold payments for a variety of reasons. See id. at § 17.04.
Based on this examination of the contract, the terms here appear comparable to the ones in
Gatzonis,
Nor can any statutory provision be discerned that creates such a right. Timely payment under the contract, per its terms, is governed by New York Public Authority Law § 2280.
See
Def. Ex. B § 17.01(F). That law, however, does not create a clear entitlement to prompt payment, but rather mandates that interest be paid by any public authority that does not promptly pay its contractors according to its established policy.
See
N.Y. Pub. Auth. Law § 2280.2-7. Ultimately, then, what exists here is not any “clear entitlement” to prompt payment of the sort that creates a due process property right.
Cf. S&D Maint.,
b. Liberty Interest
However, the inquiry into whether or not TADCO has stated a cognizable due process violation does not end with the determination that it has no property right to prompt payment. TADCO’s complaint also sets forth a claim of a constitutionally protected liberty interest in its “reputation for integrity and professional competence as a general contractor and its status as a responsible bidder on public works projects.” Compl. ¶ 113. This type of § 1983 liberty interest claim is commonly referred to as a “stigma-plus” claim, and “requires a plaintiff to allege (1) the utterance of a statement about her that is injurious to her reputation, that is capable of being proved false, and that he or she claims is false [the ‘stigma’], and (2) some tangible and material state-imposed burden ... in addition to the stigmatizing statement [the ‘plus’].”
Velez v. Levy,
To satisfy the “stigma” prong of its due process liberty claim, TADCO must show: (1) that the statements complained of were
“Not every derogatory statement made about an employee who loses his or her job imposes sufficient stigma to implicate the liberty interest —”
O’Neill v. City of Auburn,
This standard sets a high bar for the type of reputational damage that must be alleged in order to adequately plead stigma. It is clear that “vague statements of unspecified incompetence” do not suffice; on the other hand, “extensively detailed lists of ... supposed professional failings” do.
See Donato,
Moreover, conclusory allegations that a plaintiffs reputation has been damaged, that a plaintiffs career has been destroyed or that a substantial roadblock has been placed in a plaintiffs ability to continue its profession are insufficient to withstand a motion to dismiss.
See Srinivas v. Picard,
TADCO’s pleadings fail to show that DASNY made any statements about it that go to the heart of its professional competence,
see O’Neill,
In TADCO’s Memorandum of Law in Opposition to the Motion to Dismiss, it adds to its allegations of defamation the contents of a letter sent from James Gray, DASNY’s Managing Director of Construction, to TADCO on January 10, 2007, a copy of which is annexed to defendants’ motion papers. See Graber Deck, Ex. C. Defendants argue that the contents of this letter should not be considered because such amendment of the pleadings through responsive papers is impermissible. Moreover, it is independently noted that if such evidence were considered at this stage, this court would be required to convert defendant’s motion into one for summary judgment. See Fed.R.Civ.P. 12(d). However, even if the contents of this letter were considered, they would not appreciably add to TADCO’s pleading of a stigma. The letter contains statements that “Tadco is in violation of its contractual obligation,” that “Tadco has failed to demonstrate the ability to complete the work” and that “Tadco continues to delay the project.” See Def. Ex. C at 1. None of these allegations go to the heart of TADCO’s professional competence any more so than the vague statements alleged in TADCO’s complaint.
The second statement — that TAD-CO has failed to demonstrate the ability to
In addition to TADCO’s failure to plead sufficiently stigmatizing statements, it has not adequately alleged that DASNY’s statements “seriously hindered [its] ability to find work in [its] field.”
See Piccoli,
Accordingly, TADCO has failed to adequately allege the stigma required to establish a stigma-plus liberty interest deserving of due process protection. Although it is clear that TADCO and DASNY substantially disagree about who should shoulder the blame for delays in the project and about the amount of money DASNY owes to TADCO, these disagreements are the proper subject of TADCO’s state law breach of contract claims. Having determined that TADCO has alleged neither a liberty nor property interest upon which its § 1983 due process claim can stand, this claim must be dismissed. 5
(3)
Claims of Thomas DeMartino
Plaintiffs have alleged a second set of constitutional claims under 42 U.S.C. § 1983 for malicious prosecution, abuse of criminal process and false arrest under the Fourth, Fifth and Fourteenth Amendments, against DASNY, Middleton, Cinelli, Kemp and John Doe, for the trespassing charges against DeMartino arising from his November 9, 2006 and January 2007 arrests. They have further made identical allegations under state law. Defendants move to dismiss all of these claims, arguing (1) that the state law causes of action with respect to the first trespassing arrest are barred by the applicable statute of limitations, and (2) that DeMartino has not sufficiently pled any of these claims.
As defendants point out, DeMartino, now representing himself pro se, has not filed any opposition to defendants’ motion to dismiss. Therefore, defendants conclude that “DeMartino has determined not to pursue in this court his claims for false arrest, abuse of process and malicious prosecution ....” Defs.’ Reply at 7. TAD-CO responds by arguing that TADCO itself has third party standing to assert claims of false arrest, malicious prosecution and abuse of process on DeMartino’s
Nevertheless, defendants are incorrect that inaction on DeMartino’s part so readily disposes of his claims. There has been no indication by DeMartino that by not filing opposition papers, he intends to withdraw his claims. Absent some affirmative indication to this effect, DeMartino’s complaint should only be dismissed if the pleadings are insufficient to withstand a 12(b)(6) motion.
See McCall v. Pataki,
As it happens, the analysis of DeMartino’s claims surrounding his November 9, 2006 arrest differs considerably from the analysis of his January 2007 arrest. For this reason, these claims are considered separately. Moreover, as the analysis differs among the named defendants, they are also considered separately.
a. Claims Arising from the November 9, 2007 Arrest
i. False Arrest against Middleton
DeMartino first brings a § 1983 false arrest claim against Middleton, DAS-NY’s field representative, with respect to his arrest on November 9, 2006. “Federal claims for false arrest and imprisonment brought via § 1983 rest on an individual’s Fourth Amendment right to be ‘free from unreasonable seizures, including arrest without probable cause,’ and are ‘substantially the same as a claim for false arrest under New York law.’ ”
Rateau,
This case presents the atypical situation of a civilian, as opposed to an arresting officer, being sued for false arrest. Defendants’ primary argument in their motion to dismiss is that civilians are not liable merely for furnishing information to the police. They are correct that “a defendant who furnishes information to police will not generally be held liable for false arrest when the police exercise independent judgment to arrest a plaintiff.”
Rateau,
The complaint relates the following events with respect to DeMartino’s November 9, 2006 arrest. On November 9, DeMartino and Middleton entered a dispute under the contract regarding whether or not DASNY could require TADCO to cover open trenches with wood planks. Compl. ¶¶ 76-79. That same day, Middleton lodged a criminal complaint against DeMartino for trespassing and “demand[ed] that he be arrested” to the state police officers in charge of the facility, who proceeded to arrest DeMartino and charge him with trespassing. Id. at ¶ 80.
At least at the pleading stage, these allegations put forth a plausible claim of false arrest against- Middleton for DeMartino’s November 9 arrest. According to the events as laid out by the complaint, rather than going through the appropriate channels to settle their contractual dispute or remove DeMartino from the job site, Middleton instead called the police and “demanded]” De-Martino’s arrest.
Defendants attempt to legitimize Middleton’s actions by explaining that certain contract provisions gave DASNY authority to order DeMartino removed from the site, thereby making him a trespasser. In general, defendants appear correct that they had the authority under certain contract provisions to have TADCO supervisory staff terminated, and employees removed from the project, at DASNY’s request.
See
Graber Deck, Ex. B § 5.01(B)-(C).
6
However, this does not answer the question of whether or not such authority was properly exercised prior to DeMartino’s November 9 arrest. It may well be that before calling state officers to demand that they arrest DeMartino, Middleton made it clear to DeMartino and TADCO that DAS-NY was exercising its contractual authority to have DeMartino removed and would consider him trespassing if he remained on the property. But it could also be that Middleton actively encouraged DeMartino’s arrest by falsely reporting him to be a trespasser before having him properly removed from the project, in which case he could be liable for the arrest.
7
Cf. Wein
ii. Malicious Prosecution against Middleton
DeMartino also asserts a claim of malicious prosecution against Middleton stemming from his November 9, 2006 arrest. “Though related, the torts of false arrest or imprisonment and malicious prosecution protect individuals from different harms. Whereas the tort of false imprisonment protects the personal interest of freedom from restraint of movement, the tort of malicious prosecution protects the personal interest of freedom from unjustifiable litigation.”
Weintraub,
As with false arrest, although malicious prosecution claims are usually made against arresting or prosecuting officials, they can also be brought against individuals other than the arresting officer when such a person actively engaged in a plaintiffs prosecution.
See Shattuck,
DeMartino has adequately pled each element of malicious prosecution. He has alleged that on November 9, Middleton falsely told police that he was trespassing, when in fact he was authorized to be at the job site, Compl. ¶¶ 80-82, thereby adequately alleging the commencement of a criminal proceeding
8
and a lack of proba
DeMartino has also alleged actual malice. Actual malice requires pleading facts that show the defendant “commenced the prior criminal proceeding due to a wrong or improper motive, something other than a desire to see the ends of justice served.”
Du Chateau v. Metro-North Commuter RR Co.,
Finally, DeMartino has properly alleged a favorable termination by stating that the case against him “was subsequently dismissed in its entirety,” Compl. ¶¶ 82-83, and “in a manner that indicated his innocence,”
id.
at ¶ 128. Athough the complaint does not indicate the actual disposition of the case, and DeMartino later will have to present facts to support his claim that the termination was favorable to him, bare allegations to this effect are sufficient at this stage.
See Rivers,
Accordingly, DeMartino’s § 1983 malicious prosecution claim against Middleton is also sufficiently pled with respect to the proceeding stemming from his November 9, 2006 arrest and will not be dismissed.
iii. Abuse of Criminal Process against Mdddleton
DeMartino’s final § 1983 claim against Middleton with respect to his November 9 arrest is for abuse of criminal process. As with false arrest and malicious prosecution, a federal § 1983 abuse of process claim tracks New York’s cause of action and has three essential elements: (1) regularly issued process; (2) the person activating the process must be moved by a purpose to do harm without that which has been traditionally described as economic or social excuse or justification; and (3) defendant must be seeking some collateral advantage or corresponding detriment to the plaintiff which is outside the legitimate ends of the process.
Bd. of Educ. Of Farmingdale Union Free Sch. Dist. v. Farmingdale Classroom Teachers Ass’n,
Here again, DeMartino has sufficiently pled each of these elements. Defendants argue that plaintiffs have not adequately pled that DASNY sought to do harm without justification or that defendants were seeking an advantage outside the legitimate ends of the process. This position, however, ignores plaintiffs’ allegations that DASNY had DeMartino arrested and charged with trespassing “in order to intimidate and frustrate Mr. DeMartino and TADCO and thereby obtain an advantage over them in the ongoing contractual and construction disputes.” Compl. ¶ 136. At this early stage, this statement sufficiently alleges the second two elements of an abuse of process claim. If DeMartino can ultimately prove that DASNY employees falsely furnished information that De-Martino was trespassing, and did so in order to achieve the collateral objective of an advantage over TADCO in their contract disputes, these actions would constitute both an improper motive and an improper purpose for DASNY’s participation in the November 9, 2006 arrest.
Cf. Rivers,
More complicated is the question of whether plaintiff has pled the first element, the existence of regularly issued process. DeMartino has alleged that defendants improperly contributed to his arrest, but not that they took any further actions in his prosecution. It remains unclear whether New York law permits abuse of process claims “based on the issuance of the process itself,” as opposed to some abuse of the process after it is issued.
Compare Webster,
iv. State law Claims
DeMartino alleges identical causes of action under New York law, for false arrest, malicious prosecution and abuse of process stemming from his November 9, 2006 arrest. Defendants argue that these state law claims are time-barred by New York’s
New York’s one-year statute of limitations does indeed govern claims for false arrest, malicious prosecution and abuse of process.
See
N.Y. CPLR § 215(3) (malicious prosecution and false imprisonment actions must be commenced within one year);
Benyo v. Sikorjak,
For false arrest, the one year statute of limitations runs from the date when the party suing for false imprisonment is released from custody or confinement.
See Roche v. Village of Tarrytown,
In contrast to false arrest claims, claims for malicious prosecution and abuse of process do not accrue until the underlying action which is the basis for the claim is terminated in the plaintiffs favor by dismissal.
See Nunez v. City of New York,
However, DeMartino’s state law claims of malicious prosecution and abuse of process suffer from a further defect. Although not required for § 1983 claims,
11
under New York law, a plaintiff proeeed
In this case, DeMartino has generally pled damages in an amount of “not less than $1,000,000.00” for his November 9 abuse of process and malicious prosecution claims, Compl. ¶¶ 405, 411, but has not pled any special damages. Accordingly, these state law malicious prosecution and abuse of process claims will be dismissed.
Cf. Morea,
In sum, DeMartino’s claims of false arrest, malicious prosecution and abuse of process under § 1983 against Middleton for his November 9, 2006 arrest are sufficient to withstand a motion to dismiss. DeMartino’s state law claim of false arrest for the November 9 arrest is dismissed as time-barred, and his state law claims of malicious prosecution and abuse of process for this arrest are dismissed for failure to plead special damages. The issue remains, however, of whether the surviving federal claims should be permitted to stand against the remaining named defendants.
v. Liability of Additional Named Defendants
As noted earlier, DeMartino’s § 1983 false arrest, malicious prosecution and abuse of process claims for his November 9, 2006 arrest name not only Middleton as a defendant, but also DASNY and Middleton’s supervisors, Cinelli and Kemp. The complaint alleges that Cinelli and Kemp “approved of and authorized” the actions of Middleton with respect to DeMartino’s November 9, 2006 arrest. Compl. ¶¶ 158, 166.
At this stage, this allegation is sufficient to state a § 1983 claim for supervisory liability. “The liability of a supervisor under § 1983 can be shown in one or more of the following ways: (1) actual direct participation in the constitutional violation, (2) failure to remedy a wrong after being informed through a report or appeal, (3) creation of a policy or custom that sanctioned conduct amounting to a constitutional violation, or allowing such a policy or custom to continue, (4) grossly negligent supervision of subordinates who committed a violation, or (5) failure to act on information indicating that unconstitutional acts were occurring.”
Hernandez v. Keane,
However, as against DASNY as a named defendant, DeMartino’s § 1983 allegations cannot stand. Although DASNY, consistent with case law, does not assert sovereign immunity or an inability to be sued as a person under § 1983 as defenses,
see supra
note 2, as a State Authority, it appears entitled to the same protections that municipalities receive when being sued under § 1983.
See Raysor v. Port Auth. of New York and New Jersey,
There are no such allegations present here. DeMartino has nowhere claimed that it is DASNY’s official custom or policy to have the employees of contractors with whom it is displeased arrested rather than removed from projects through lawful channels. As a result, the § 1983 claims for false arrest, malicious prosecution and abuse of process against DASNY fail.
b. Claims Arising from DeMartino’s January 2007 Arrest
Unlike DeMartino’s claims for his November 9, 2006 arrest, his false arrest, malicious prosecution and abuse of process claims regarding his January 2007 arrest fail in their entirety. With respect to this later arrest, defendants are correct that plaintiff has not sufficiently alleged a lack of probable cause.
The existence of probable cause defeats claims of both false arrest and malicious prosecution, although not claims of abuse of process.
See Covington v. City of New York,
DeMartino’s abuse of process claim for this arrest also fails. Although probable cause is not a specific element of an abuse of process claim under § 1983, the facts that give rise to probable cause for the January arrest also make it impossible for DeMartino to adequately plead that the person activating regularly issued process was moved by an improper purpose, as required for an abuse of process claim.
See Webster,
For the reasons explained above, all of DeMartino’s claims with respect to his January 2007 arrest are dismissed.
(4)
Leave to Amend
TADCO has requested leave to amend the complaint to cure any deficiencies. If DeMartino wishes to amend his state law malicious prosecution and abuse of process claims for his November 9, 2006 arrest to allege special damages, he may do so. As for TADCO’s request that it be permitted to amend its claim of a due process violation under § 1983, leave is denied. TAD-CO has generally claimed that it believes that any deficiency in its pleadings can be cured with an amended pleading,
see
PL’s Mem. at 25, but has not identified any way in which it could amplify its allegations of defamation except by pointing to the contents of the letter from James Gray to TADCO dated January 10, 2007.
12
See
Conclusion
Defendants’ motion to dismiss is granted with respect to TADCO’s due process claim under the Fifth and Fourteenth Amendments and 42 U.S.C. § 1983 (1st Cause of Action); DeMartino’s claims of false arrest, malicious prosecution and abuse of process under 42 U.S.C. § 1983 with respect to his November 9, 2006 arrest, as against DASNY only (2nd-4th Causes of Action); DeMartino’s claims of false arrest, malicious prosecution and abuse of process under 42 U.S.C. § 1983 with respect to his January 2007 arrest as against all defendants (5th-7th Causes of Action); and DeMartino’s state law claims of false arrest, malicious prosecution and abuse of process with respect to both his arrests as against all defendants (34th-39th Causes of Action). Defendants’ motion to dismiss is denied with respect to DeMartino’s § 1983 claims of false arrest, malicious prosecution and abuse of process arising from his November 9, 2006 arrest against Middleton, Cinelli and Kemp (2nd-4th Causes of Action).
At this time, defendants have not challenged the adequacy of plaintiffs’ claims of wrongful termination (8th Cause of Action), breach of contract (9th-30th Causes of Action), quantum meruit (31st-32nd Causes of Action) or unjust enrichment (33rd Cause of Action). Accordingly, as several federal claims remain in this case, these state law claims also remain under supplemental jurisdiction.
SO ORDERED.
Notes
. Defendants argue that their additional exhibits — including several letters exchanged between DASNY and TADCO — should be considered in ruling on this motion as part of the public record.
See
Graber Decl. ¶ 3. However, Second Circuit precedent does not clearly extend this far. It has previously been held that district courts may take judicial notice of "public disclosure documents required by law to be filed, and actually filed, with the SEC,” and public records such as case law and statutes, but it is not clear that this rule extends to the contents of a publicly filed letter from a state agency to its contractor.
See Kramer v. Time Warner Inc.,
. DASNY and the individual defendants as named in their official capacities have not asserted the defenses of sovereign immunity or an inability to be sued as a ‘person’ under § 1983, likely because the one federal case on point, and the New York Court of Appeals, have held that DASNY is not an arm of the state.
See TM Park Ave. Assocs. v. Pataki,
. Although the standards quoted here refer specifically to statements made about a government employee in the course of his or her termination, courts have analogized the termination of a government contractor to the termination of a government employee and thus have borrowed these standards in analyzing stigmatizing comments made in both situations.
See, e.g., S & D Maint.,
. Defendants argue that plaintiffs' stigma-plus claim should be dismissed for failure to adequately plead the allegedly defamatory statements made by DASNY. This contention need not be addressed, because even assuming that plaintiff has adequately pled the offending statements, the statements identified do not create the stigma necessary to state a constitutional claim.
. Because it is determined that TADCO has not adequately pled the existence of a constitutionally protected liberty or property interest of which it was deprived, defendants' argument that an adequate post-deprivation remedy existed, such that due process was not violated, need not be reached.
. These contractual provisions provide in full:
B. If at any time the supervisory staff is not satisfactory to the Owner, the Contractor shall, if directed by the Owner, immediately replace such supervisory staff with other staff satisfactory to the Owner.
C. The Contractor shall remove from the Work any employee of the Contractor or of any Subcontractor when so directed by the Owner.
Graber Deck, Ex. B, § 5.01(B)-(C).
. Defendants proffer a letter written from DASNY's Project Manager to Frank DeMartino, TADCO’s Project Manager, on November 9, 2006 as evidence that DASNY had already exercised its contractual right to have Thomas DeMartino removed from the project at the
. It is not clear from the complaint whether DeMartino made any appearance in court following the issuance of a summons against him. However, case law seems to favor the contention that the issuance of a summons following a warrantless arrest, even without a further appearance, constitutes initiation of a "proceeding.”
See Casale v. Kelly,
. Defendants again argue that Middleton had probable cause because DASNY had exercised its contractual right to have DeMartino barred from the job site, and therefore De-Martino’s continued presence made him a trespasser. This argument is rejected here for the reason explained above with respect to DeMartino’s false arrest claim: from the complaint alone, it is not clear that DeMartino had been properly terminated from the project and had been apprised of this fact at the time he was arrested.
. In contrast, plaintiffs’ federal claims because claims brought pursuant to § 1983 forum state’s general or residual statute actions — in New York, three years — even more specific statutes of limitations for personal injury actions.
Owens v. Okure,
.
See, e.g., Day v. Morgenthau,
. At one point TADCO also suggests that "similar false allegations” contained in a sec
