Pursuant to the Wetlands Protection Act, G. L. c. 131, § 40, and the town’s wetland protection bylaw, chapter 178, the plaintiff filed a notice of intent with the conservation commission of North Andover for the filling of 250 square feet of bordering vegetative wetlands and the performance of work in the buffer zone adjacent to the wetlands in order to construct a roadway in its subdivision. The commission approved the work subject to forty-six conditions.
On appeal from the ensuing judgment entered in the Superior Court in favor of the plaintiff, the commission challenges only the judge’s determination that the town’s by-law is less stringent than the Wetlands Protection Act and the judge’s denial as to three of the conditions imposed by the commission on the project, namely: (1) condition 15, a twenty-five foot no-cut and a fifty foot no-construction zone from the edge of the adjacent wetland resource areas, except for the approved wetland crossing and drainage discharge at the entrance of the subdivision; (2) condition 29, the placement of a filter fabric fence backed by a single row of staked hay bales between all construction areas and wetland areas; and (3) condition 37, the maintenance during the construction period of dumpsters outside the wetlands resource area for the storage and removal of waste generated by the construction. We discuss each of these claims.
1.
The by-law.
The Wetlands Protection Act, G. L. c. 131, § 40, “establishes minimum Statewide standards leaving lo
The commission rests its argument on the ground that its by-law regulates all activity within the buffer zone, see c. 178-3A, while the State regulations provide for regulation of activity in a buffer zone only if the activity will “alter” a wetland resource area, see 310 Code Mass. Regs. § 10.02(2)(b) (1989). This is a significant difference. Under the State regulations, a party is required to file a notice of intent for work in the buffer zone only when it has been shown that the work will alter a protected area. 310 Code Mass. Regs. § 10.02(2)(b) (1989). While the word “alter”
The commission also argues that its by-law is more stringent than the act because it adds erosion control, sedimentation control, and recreation, c. 178-1, 3 to the eight interests protected by the act, G. L. c. 138, § 40, and 310 Code Mass. Regs. § 10.01(2) (1989). By expanding the interests to be protected under the by-law, the commission may impose conditions which might not be permissible under the act. See Kreiger, Local Wetlands By-Laws and Hearings, in Wetlands, A Guide to Understanding a Complex Federal, State and Local Regulatory Scheme 39, 43 (Mass. Continuing Legal Educ. 1991).
Insofar as the by-law regulates all activity performed in the buffer zone and provides for the protection of additional
2. The challenged conditions. The judge determined that the imposition of the no-cut and no-construction limitation in the buffer zone and the requirement of a double siltation barrier were invalid conditions because they were “arbitrary, unreasonable or capricious, not grounded in evidence and therefore not supportable.” He determined that the requirement of placement of dumpsters outside the wetland resource areas for the storage and removal of waste material was reasonable.
In reviewing his decision, the first issue to be addressed is the standard of review applicable to the plaintiff’s complaint for relief in the nature of certiorari under G. L. c. 249, § 4. The standard of review varies according to the nature of the action for which review is sought.
McSweeney
v.
Town Manager of Lexington,
Although the judge appears to have applied the appropriate standard of review, we do not think the record supports a conclusion that the commission acted arbitrarily or capriciously. A decision is not arbitrary and capricious unless there is no ground which “reasonable men might deem proper” to support it.
Cotter
v.
Chelsea,
Under the by-law, the commission may impose “such conditions ... as it deems reasonable, necessary or desirable to carry out the purposes of [the] chapter. . . .” North Andover wetlands protection by-law c. 178-4(C). Among the interests protected by the by-law and the act are the public and private water supply, groundwater supply, and wildlife habitat c. 178-1 (note 3, supra), G. L. c. 131, § 40, and 310 Code Mass. Regs. § 10.01(2) (1989). In imposing the no-cut and no-construction limitation, the commission asserted that the proposed construction work would have impact upon the adjacent wetland resource areas. In reaching that conclusion, the commission relied on research suggesting the need for buffer strips to protect water quality and wildlife habitat. Imposition of that condition was within the reasonable range of the commission’s authority to regulate activity in the buffer zone.
Similarly, the commission’s imposition of a double siltation barrier was imposed to prevent erosion, a protected interest under the by-law. While there was no evidence that the fabric fence was needed in addition to the single row of hay bales, it is plausible that a double layer of protection would be more effective than a single barrier. We think the judge was in error in ruling that this condition was arbitrary and capricious.
Finally, we agree with the judge that the requirement of a dumpster for the storage of waste material away from the wetland resource area was a reasonable condition. This condition is reasonably related to the protection of the wetland resource areas insofar as it may prevent the seepage of contaminated liquids into the soil and the blowing of contami
The judgment of the Superior Court is reversed. Upon remand to the Superior Court, judgment should enter declaring the commission’s authority to impose conditions 15; 29, and 37 under c. 178 of the town’s by-law.
So ordered.
Notes
Section 3A of the by-law in effect at the time provided:
“A. No person shall remove, fill, dredge or alter any bank, freshwater wetland, beach, marsh, wet meadow, bog, swamp or lands bordering any creek, river, stream, pond or lake or any land under said waters or any subject to storm flowage or flooding or inundation by groundwater or surface water or the buffer zone, without filing written notice of the intention to do so with the Conservation Commission in accordance with the provisions set forth in this chapter and without receiving and complying with the order of conditions, and provided that all appeal periods have elapsed, unless the Commission shall have determined that this chapter does not apply to the activity proposed.” (Emphasis added.)
As in effect at the time, this section provided:
“The purpose of this chapter is to preserve and protect the floodplains and wetlands of the Town of North Andover, as specified in [c.] 178-3A, by regulating and controlling activities deemed to have significant or cumulative effect upon the functions and characteristics of such floodplains and wetlands, including but not limited to the following: public or private water supply, groundwater, flood control, erosion control, sedimentation control, storm damage prevention, prevention of pollution, protection of fisheries, wildlife habitat and recreation.”
