Lead Opinion
MODIFIED OPINION ON REHEARING
for the Court:
¶ 1. Thе motion for rehearing is denied. The court’s original opinion is withdrawn, and this opinion is substituted in lieu thereof.
■ ¶ 2. T.C.B. Construction Company, Inc. (TCB) sued W.C. Fore Trucking, Inc. (Fore) for breach of contract. The suit was based on Fore’s non-payment for work TCB performed removing debris south of Highway 53 in Harrison County, Mississippi, after Hurricane Katrina. Fore disagreed that the subcontract between the two companies was modified to include this area. Although the jury found Fore had modified the subcontract, it awarded TCB only $3,577,583.34 in damages, which in effect compensated TCB for only half of the work it undisputably performed. On appeal, TCB argues it was entitled, as a matter of law, to $6,634,436.69, based on the undisputed amount of debris it removed. Specifically, TCB claims it was entitled to summary judgment or a directed verdict in its favor because Fore was estopped from denying the subcontract’s modification.
¶ 3. Under Mississippi’s quasi-estoppel doctrine, a party cannot claim the benefits of a transaction and at the 'samé time repudiate its obligations. Fore accepted the benefits of the modified subcontract with TCB, billing Harrison County (County) for each cubic yard of debris TCB removed south of Highway 53. And Fore admits that neither it nor any other subcontractor besides TCB performed the work for which Fore was compensated. Based on Mississippi’s quasi-estoppel doctrine, we find Fore is estopped from denying it owed TCB any portion of the approximately $8.5 million it collected from the County for TCB’s wоrk south of Highway 53. Thus, the. circuit, court erred by submitting the issues of modification and damages to the jury. We reverse the circuit court’s $3,577,583.34 judgment and render judgment in TCB’s favor in the amount of $6,634,436.69.
¶ 4. The circuit court correctly awarded TCB prejudgment interest of eight percent. But we find this interest should have been awarded from the date of breach, not the date TCB filed its complaint. Therefore, we remand to the circuit court to calculate prejudgment interest. We affirm the circuit court’s directed verdict in favor of Fore on the issues of punitive damages and attorney’s fees.
BACKGROUNDS FACTS
¶ 5. On August 29, 2005, the County began clearing debris left in the wake of Hurricane Katrina from its right of ways. It divided the county into three zones. Fore won the contract to remove debris in Zone 2. The County agreed to pay Fore $10.64 per cubic yard of debris removed from this zone.
¶ 6. On September 16, 2005, Fore entered into a subcontract with TCB to haul debris in Zone 2 north of Highway 53 for $8.90 per cubic yard. The subcontract required TCB to send Fore daily reports, referred to as “truck tickets.” The subcontract also had an express good-faith clause, which stated “the contract can and will be modified based upon facts and circumstances of all debris removal.”
¶8. An independent accounting firm, R.W. Beck & Associates (Beck), oversaw the debris removal. Each day Beck inspected the trucks removing the debris. It also calculated the cubic yardage and verified the location from which the debris had been removed. Once Beck approved the truck tickets, it sent copies to Fore. TCB also sent Fore weekly invoices. Fore utilized the figures contained in TCB’s invoices to create its own invoices, which Fore submitted to the County for payment. Beck verified the invoices and told the County these invoices should be paid; and the County, in turn, looked to the Federal Emergency Management Agency (FEMA) for funds to pay Fore’s invoices.
¶ 9. Fore claims in March 2006 it first learned TCB had been hauling debris from south of Highway 53. Although Fore stopped paying TCB’s invoices at this point, it does not dispute it billed the County for all of the debris TCB hauled south of Highway 53. And the County paid Fore in full for each invoice submitted. In total, Fore received $12,292,176.10 from the County based on debris cleared by TCB. This represents approximately 1,155,280 cubic yards, at $10.64 per cubic yards. TCB claims it is entitled to $10,273,125.77 of that money, or $8.90 for each yard it undisputably hauled. Fore’s payments to TCB totaled only $3,638,689.08, a difference of $6,634,436.69.
PROCEDURAL HISTORY
¶ 10. TCB sued Fore for breach of contract. To recover for breаch of contract, a plaintiff has the burden to prove by preponderance of the evidence: (1) the existence of a valid and binding contract, (2) the defendant’s breach of the contract, and (3) resulting monetary damages. Warwick v. Matheney,
¶ 11. Before trial, TCB moved for summary judgment. It argued there were no disputed facts concerning the modified subcontract’s existence because Fore actually utilized TCB’s invoices to bill the County for debris removed south of Highway 53, thus proving the subcontract had been modified. The circuit judge denied
¶ 12. The circuit court submitted the issues of the modified subcontract’s existence, breach, and the amount of damages to the jury. TCB questioned whether the jury should decide the amount of damages and argued that if the jury found the subcontract had been modified then it should award TCB the set amount of money represented by invoices Fore accepted from TCB and billed to the County. The circuit judge rejected TCB’s argument that the amount of damages was set, deciding “to leave the amount of the verdict up to the jury in its discretion....” In a special interrogatory verdict form, the jury found the subcontract had been modified but that TCB was only entitled to $4,098,314.33 for breach of the modified subcontract. It also awarded Fore $520,730.99 on its “overpayment” counterclaim. The result was a $3,577,583.34 net award for TCB.
¶ 13. The circuit judge awarded TCB prejudgment interest of eight percent, accruing from the date TCB filed its complaint. The circuit judge refused to submit TCB’s punitive damages claim to the jury.
ISSUES ON APPEAL
¶ 14. On appeal, TCB argues the issues of the existence of the modified subcontract and the amount of damages owed for Fore’s breach should not have been submitted to the jury. Instead, TCB claims, as a matter of law, that Fore owed it $6,634,436.69 based on Mississippi’s doctrine of quasi-estoppel, as applied in Hoerner v. First National Bank of Jackson,
¶ 15. As to prejudgment interest, TCB claims that because the amount of damages was liquidated, it is entitled to the eight-percent prejudgment interest from the date of breach, not the later date of filing the complaint. Fore cross-appeals on this issue, asserting TCB’s damages were unliquidated; thus, the award of prejudgment interest was an abuse of discretion.
¶ 16. TCB also requests that we remand the issue of punitive damages for a jury trial.
DISCUSSION
I. Modified Subcontract and Damages
¶ 17. TCB moved for a directed verdict in its favor on its breach-of-contract claim. We review the denial of a directed verdict de novo. Figueroa v. Orleans,
¶ 18. The circuit court found W.C.’s denial of the subcontract’s modification was sufficient to create jury questions on the issues of modification and damages. But our review shows there were no jury issues to be resolved. Fore admits it did not reject a single one of TCB’s daily truck tickets or weekly invoices. Likewise, prior to TCB filing suit, Fore did not protest that TCB was working in an area outside of the area covered in the subcontract. Fore also admits it billed the County — and received payment from the County — for TCB’s work represented by these invoices. Mississippi law prevents Fore from simultaneously benefitting from the modified subcontract — by receiving over $8.5 million from the County because of TCB’s work south of Highway 53 — and then in turn repudiating any obligation to pay TCB its approximately $7.15 million share. Fore’s undisputed conduct, as a matter of law, established the subcontract’s modification. And TCB’s unquestioned invoices proved Fore owed TCB a remaining balance of $6,634,436.69.
A. Mississippi’s Quasi-estoppel Doctrine
¶ 19. Quasi-estoppel is an equitable principle that applies to certain bars, such as ratification, acquiescence, or acceptance of benefits. This long-standing doctrine is applied to preclude contradictory positions by preventing a person from asserting, to another’s disadvantage, a right inconsistent with a position previously taken. Wood Naval Stores Exp. Ass’n v. Latimer,
¶ 20. In addressing the equitable concepts еmbodied in the quasi-estoppel doctrine, the Mississippi Supreme Court has explained:
Where one having the right to accept or reject a transaction takes and retains benefits thereunder, he ratifies the transaction, is bound by it, and cannot avoid its obligation or effect by taking a position inconsistent therewith. A party cannot claim benefits under a transaction or instrument and at the same time repudiate its obligations.
Wood Naval,
¶ 21. In Hoerner, the Mississippi Supreme Court applied the doctrine of quasi-estoppel to reverse a chancellor’s ruling that Fred Hoerner was not personally liable under a guaranty agreement. Hoerner,
¶ 23. The supreme court held proof of Hoerner’s actual approval was unnecessary because Hoerner’s “acceptance of the benefits flowing from [the loans] could not be other than an implied approval by operation of law.” Id. at 762 (emphasis added). The Hoerner court recognized: “Where one having the right to accept or reject a transaction takes and retains benefits thereunder, he ratifies the transaction, is bound by it, and cannot avoid its obligation or effect by taking a position inconsistent therewith.” Id. Thus, “based on equity and good conscience[,]” the supreme court reversed the judgment in favor of Hoerner and rendered judgment in the bank’s favor based on evidence of Hoerner’s conduct. Id. at 761-62.
¶ 24. Earlier, in Wood Naval, the supreme court similarly looked to the conduct of two association members. Wood Naval, 220 Miss, at 664-65,
¶ 25. More recently, in Bailey, the supreme court relied on the same estoрpel principle to uphold a contract for services provided to sell out-of-state rental properties. The Bailey court held:
This doctrine, termed “quasi-estoppel,” precludes a party from asserting, to another’s disadvantage, a right inconsistent with a position it has previously taken, and applies when it would be unconscionable to allow a person to maintain a position inconsistent with one to which he acquiesced, or from which he accepted a benefit. This is exactly the situation at hand; the Baileys cannot profit under this contract and also seek to have it declared invalid where their obligations under the contract are concerned.
Bailey,
¶ 26. As equitable principles go, our inquiry focuses solely on the application of the doctrine of quasi-estoppel, as expressed in Hoerner, Wood Naval, and Bailey, to Fore’s actions related to the subcontract. Because Judge Carlton’s separate opinion delves into equitable es-toppel, quantum meruit, and unjust enrichment, we briefly note these equitable doctrines are inapplicable to this appeal. These doctrines, which are not relied on by the appellant nor the majority, are neither synonymous with quasi-estoppel — or with each other.
¶ 27. In Hoerner, Wood Naval, and Bailey, quasi-estoppel operated to prohibit the defendants’ assertions that were inconsistent with their previous acceptances of benefits — subsequent bank loans (Hoer-ner), continued association membership benefits (Wood Naval), and real-estate investment services (Bailey) — and, therefore, prohibited the defendants from denying the existence of the contractual basis for the plaintiffs’ claims. Here, the unambiguous contractual language stated the subcontract between Fore and TCB “can and will be modified based upon facts and circumstances of all debris removal.” TCB essentially argues Fore is estopped from denying the modification of its subcontract with TCB since the “facts and circumstances of all debris removal” undis-putedly showed (1) Fore’s previous acceptance and ratification of TCB’s invoices for debris removed south of Highway 53, (2) Fore’s submissions of these invoices to the County for payment, (3) Fore’s receipt of payment from the County for debris TCB removed south of Highway 53, and (4) the fact that TCB — not Fore nor any other company — was the only contractor that had removed debris south of Highway 53. Because Fore ratified, accepted, and greatly benefitted from TCB’s debris removal south of Highway 53, TCB argues quasi-estoppel precludes Fore from later flip flopping to an entirely inconsistent position aimed solely at shirking its obligation to pay TCB.
B. Operation of Quasi-Estoppel on TCB’s Claim
¶ 28. Generally, “[q]uasi-estoppel is a factual determination and thus the province of the jury[.]” Stinnett v. Colo. Interstate Gas Co.,
¶ 29. Bearing in mind that quasi-estoppel “precludes a party from asserting, to another’s disadvantage, a right in
¶ 30. Fore argues W.C. was the only corporate agent that could bind Fore to the modified subcontract, and W.C. testified he did not know TCB was working south of Highway 53 because the “ladies” in the bookkeeping department handled these invoices without his knowledge. Therefore, Fore argues it cannot be bound to the modified subcontract through quasi-estoppel. But what Fore does not argue is that its bookkeeping employees were unauthorized to accept the invoices or submit them to the County for payment or that Fore, the corporation, was without knowledge it was accepting the benefit of TCB’s work.
¶ 31. First, only TCB, not Fore nor any other subcontractor, removed debris from that area. Second, TCB submitted invoices to Fore’s accountants depicting TCB had removed debris from this area. Fore then reviewed TCB’s invoices and utilized the figures provided by TCB to generate its own invoices, which Fore submitted to the County for payment. Third, an independent accounting firm also inspected TCB’s trucks daily before they left the area south of Highway 53. This process required that Beck calculate the cubic yardage and verify the location from which the debris was removed. After approving the truck tickets, Beck sent copies of these tickets, which included the removal location, to Fore. Fourth, by submitting invoices to the County, Fore represented to the government that the amount and location of debris being removed from Zone 2 was accurate. Amd Fore has never
¶ 82. Fore does not deny these interactions or dispute that only TCB performed debris removal south of Highway 53. Instead, Fore simply argues it gets to keep every cent of the over $8.5 million the County paid it for TCB’s debris removal south of Highway 53 because the subcontract was not modified. We find, as a matter of law, that Fore cannot keep this windfall. See Bailey,
¶ 33. Judge Carlton’s separate opinion focuses on the denial of TCB’s motion for a judgment notwithstanding the verdict and finds the evidence supports the jury’s verdict. “Our standards of review for a denial of a judgment notwithstanding the verdict and a directed verdict are ... identical.” Sperry-New Holland v. Prestage,
If the facts so considered point so overwhelmingly in favor of the appellant that reasonable men could not have arrived at a contrary verdict, [we are] required to reverse and render. On the other hand if there is substantial evidence in support of the verdict, that is, evidence of such quality and weight that reasonable and fair minded jurors in the exercise of impartial judgment might have reached different conclusions, affirmance is required.
Id. (citing Munford,
¶ 34. Just as the issue of modification was not a jury issue, neither was the issue of damages. The circuit court decided to leave the amount of damages to the jury’s discretion. We find the submission of the issue of damages to the jury to be error. Fore presented no evidence to dispute the
¶ 35. Judge Carlton’s separate opinion claims TCB failed to submit a jury instruction asking for damages in the set amount of $6,634,486.69. But TCB moved for summary judgment, arguing there were no disputed factual issues, and then moved for a directed verdict for the same reasons. We hold that the issue of damages should not have gone to the jury. Nonetheless, TCB explained to the circuit court that it had not prepared an instruction on damages because it was unsure whether the court would award it the amount of its claim or submit the issue to the jury. Though TCB continued to maintain that it should be entitled to the set amount, the circuit court decided to submit the issue of the amount of damages to the jury.
¶ 36. In A & F Properties, this court held it was error to find the defendant breached the cоntract but not award the undisputed amount plaintiff would have received but for the breach. A & F Props., LLC v. Lake Caroline, Inc.,
C. Fore’s Claim of Waiver
¶ 37. Fore argues TCB did not plead estoppel — only breach of contract — and, therefore, cannot recover under this equitable theory of quasi-estoppel. Fore further claims TCB neither asserted “estop-pel” in its motion for summary judgment nor in its ore tenus motion for a directed verdict but instead raised this equitable theory for the first time on appeal. TCB counters that quasi-estoppel was not a separate claim or an alternative ground for recovery. Instead, quasi-estoppel arose as TCB’s response to Fore’s breach-of-contract defense that the subcontract was never modified. Having considered Fore’s argument, we find TCB did not waive the application of quasi-estoppel.
¶ 38. Quasi-estoppel is not an independent claim that must be pled. E.g., Hoemer,
¶ 39. TCB correctly points out that Mississippi’s pleading rules do not require the plaintiff to file a response to the defen
¶ 40. TCB pled that the subcontract existed because Fore accepted the benefit of the modified subcontract. And in its motions for summary judgment and motion for a directed verdict, TCB argued W.C.’s inconsistent testimony that the subcontract had not been modified could not be used to dispute Fore’s previous conduct. Specifically, when moving for a directed verdict, TCB’s attorney argued:
The evidеnce is undisputed that all of this work was done that we’ve been arguing about, that the tickets were given to [W.C.]. He accepted them, turned them into the County and the County has paid it. I believe that the evidence would justify at this point a motion for entry of judgment in favor of [TCB] for the amount of [$6,634,436.69] just like I thought summary judgment should have been granted ... I don’t think [W.C.’s testimony] is evidence sufficient to overcome the completion of the contract and the acceptance of the work and the money by [W.C.].
While TCB did not use the magic word “estoppel,” it did argue W.C.’s denial of the modification was not “sufficient to overcome the completion of the contract and the acceptance of the work and the money_” Thus, we find TCB sufficiently raised and argued the application of quasi-estoppel to the circuit court.
¶ 41. Further, we note that in Hoerner, a case that directs us to apply quasi-estop-pel under these circumstances, the supreme court did not attribute its application of estoppel to the bank’s pleadings or defenses below. Hoerner,
II. Prejudgment Interest
¶ 42. Both TCB and Fore appeal the circuit court’s award of prejudgment interest. TCB argues, because its damages were liquidated, prejudgment interest should have been awarded from the date of the breach of the subcontract, not the later date when it filed its complaint for breach of contract. Fore claims, because TCB’s damages were unliquidated, no prejudgment interest should have been awarded. We affirm the award of prejudgment interest but remand this case to the circuit court to calculate the interest from the date of the breach.
A. Standard for Awarding Prejudgment Interest
¶ 43. A trial judge may “award prejudgment interest to the pre
¶ 44. When damages are liquidated or there has been a bad-faith denial of payment, “the prevailing party in a breach of contract suit is entitled to have added legal interest on the sum recovered computed from the date of the breach of the contract to the date of the decree.” Sentinel Indus. Contracting Corp. v. Kimmins Indus. Serv. Corp.,
¶ 45. In contrast, “unliquidat-ed” damages “cannot be determined by a fixed formula, so they are left to the discretion of the judge or jury.” Moeller,
¶ 46. If there is a bona fide dispute as to whether the plaintiff is entitled to recover damages and in what amount, the claim is not liquidated. Estate of Gillies v. Gillies,
¶ 47. But prejudgment “[ijnterest may be awarded when the amount of damages is certain, even if the fact of liability for those damages is disputed.” Cain,
B. TCB’s Liquidated Damages
¶ 48. Citing Gillies and Warwick, Fore argues the amount of damages was disputed; thus, the circuit court abused its discretion by awarding prejudgment interest at all. Though the contract rate of $8.90 was fixed, Fore argues the extent to the which the subcontract was modified required jury resolution. Fore supports its argument with the fact the jury returned a damages award for less than TCB’s requested amount.
¶ 49. We disagree and find TCB and Fore’s dispute is similar to that in Cain. Fore denied it owed anything for work south of Highway 53 because the subcontract had not been modified. But it did not dispute the amount of work TCB performed south of Highway 53. Indeed, it used the exact figures from TCB’s invoices to generate the bills Fore sent to the County. As we determined Fore’s undisputed conduct left no jury issue as to Fore’s contractual obligation to pay these invoices, we find there is no dispute as to how much is owed on these invoices. Thus, TCB’s damages are liquidated and were fixed at the time Fore breached the subcontract by failing to pay TCB for its work.
¶ 50. The circuit court correctly awarded TCB eight-percent prejudgment interest. But it erroneously set the date the interest began to accrue as the date TCB filed suit. This interest actually began to run at the time of breach. Mississippi Code Annotated section 75-17-1(1) (Rev.2009) provides: “The legal rate of interest on all notes, accounts and contracts shall be eight percent (8%) per an-num, calculated according to the actuarial method-” And Mississippi Code Annotated section 75-17-7 (Rev.2009) provides:
All judgments or decrees founded on any sale or contract shall bear interest at the same rate as the contract evidencing the debt on which the judgment or decree was rendered. All other judgments or decrees shall bear interest at a per annum rate set by the judge hearing the complaint from a date determined by such judge to be fair but in no event prior to the filing of the complaint.
In interpreting these two statutes, the Mississippi Supreme Court has made the distinction between judgments based on a contract and other judgments. In re Duckett v. Duckett,
III. Punitive Damages and Attorney’s Fees
¶ 51. In addition to full compensation under the modified subcontract, TCB seeks remand of the issue of punitive damages and attorney’s fees to the circuit court. We find the circuit court did not abuse its discretion in denying punitive damages.
A. Standard for Recovering Punitive Damages
¶ 52. The prevailing party in a breach-of-contract action may recover punitive damages “where such breach is attended by intentional wrong, insult, abuse, or such gross negligence as amounts to an independent tort.” Fought v. Morris,
¶53. The Mississippi Supreme Court has cautioned that punitive damages “are appropriate only in extreme cases” and “should be awarded only with caution and within narrow limits.” Fought,
¶ 54. “Punitive damages may not be awarded if the claimant does not prove by clear and convincing evidence that the defendant against whom punitive damages are sought acted with actual malice, gross negligence which evidences a willful, wanton or reckless disregard for the safety of others, or committed actual fraud.” Miss. Code Ann. § ll-l-65(l)(a) (Supp.2011). The trial court must consider the “totality of the circumstances to determine if a reasonable, hypothetical trier of fact could find either malice or gross neglect/reckless disregard.” Doe,
B. Standard of Review
¶ 55. TCB asserts the question of whether to submit the issue of punitive damages to the trier of fact is one of law, prompting our de novо review. To this end, TCB argues the line of Mississippi Supreme Court cases relying on Hurst v. Southwest Mississippi Legal Services Corp.,
¶ 56. However, “[t]here is no right to recover punitive damages. The award of such damages has always been discretionary.” Tideway Oil Programs, Inc. v. Serio,
(c) If, but only if, an award of compensatory damages has been made against a party, the court shall promptly commence an evidentiary hearing to determine whether punitive damages may be considered by the same trier of fact.
(d) The court shall determine whether the issue of punitive damages may be submitted to the trier of fact; and, if so, the trier of fact shall determine whether to award punitive damages and in what amount.
Miss.Code Ann. § 11-1-65(1) (Supp.2011) (emphasis added); see Doe,
C. The Circuit Court’s Decision
¶ 57. After the jury’s verdict, the circuit court granted Fore’s motion for a directed verdict on the issue of punitivе damages because it found no evidence of malicious conduct by Fore. TCB argues Fore’s decision not to pay TCB any part of the outstanding $6,634,436.69 in invoices is evidence of malice on Fore’s part. While we find Mississippi law estops Fore, based on its conduct, from denying the subcontract had been modified, our holding does not necessitate a rejection of the circuit judge’s finding that Fore’s denial of the modification was not malicious.
¶ 58. The punitive-damages statute establishes a high evidentiary burden — clear and convincing evidence — and.accords the trial court discretion over this issue. And the supreme court cautions punitive damages aye for the extreme cases. Fore took a hard-line business position by arguing it owed TCB nothing for the work south of Highway 53, an approach prohibited under Mississippi’s quasi-estoppel principle. But the circuit court found some validity in W.C.’s testimony that he did not know TCB was performing work for Fore south of Highway 53. Though the question is admittedly close, we do not find the trial court abused its discretion as gatekeeper by finding Fore’s actions did not necessitate submission of the punitive-damages issue.
¶ 59. Because we affirm the circuit court’s ruling on punitive damages, we likewise affirm its denial of attorney’s fees. Puckett,
¶ 60. THE JUDGMENT OF THE HARRISON COUNTY CIRCUIT COURT IS AFFIRMED IN PART, REVERSED AND RENDERED IN PART, AND REMANDED FOR FURTHER PROCEEDINGS CONSISTENT WITH THIS OPINION. ALL COSTS OF THIS APPEAL ARE ASSESSED TO THE AP-PELLEE/CROSS-APPELLANT.
Notes
. Equitable estoppel involves the enforcement of a promise that does not rise to the level of a
. We note W.C.’s personal knowledge is not the legal equivalent of the corporation’s. Rather, a corporation, like Fore, is charged with the collective knowledge of its employees and agents acting on its behalf. Gutter v. E.I. Dupont De Nemours,
. Contrary to Judge Carlton's separate opinion, the figure of $6,634,436.69 did not include any bills that Fore contested shоuld not have been submitted for compensation. Instead, the figure is based on the undisputed amount of compensation the County paid Fore.
Concurrence in Part
concurring in part and dissenting in part:
¶ 61. I respectfully dissent as I find that the trial court erred in granting W.C. Fore’s motion for a directed verdict on the issues of punitive damages and attorney’s fees. The jury should have been allowed to consider T.C.B. Construction’s (TCB) claim for punitive damages and attorney’s fees. Fore blatantly decided not to pay $6,634,436.69 in invoices submitted by TCB. Fore made excuses as to why it did not pay TCB, but the excuses were found to be without merit at trial. Fore admitted it billed Harrison County and received payment for all work done by TCB. TCB bore the expense of its work and paying its employees while Fore denied payment. Fore should be punished for its willful conduct, and under our law, the means of doing this is to award punitive damages.
¶ 62. Punitive damages are to be awarded when the claimant can “prove by clear and convincing evidence that the defendant against whom punitive damages are sought acted with actual malice.... ” Miss.Code Ann. § 11 — 1— 65(l)(a)(Supp.2011). “[T]he plaintiff is entitled to recover punitive damages ‘only if he has demonstrated a willful or malicious wrong or the gross, reckless disregard for the rights of others.’ ” McCorkle v. McCorkle,
¶ 63. This is a clear case of wanton disregard for TCB’s rights. Fore asserts that punitive damages and attorney’s fees were correctly denied because it did not act maliciously. Fore claims that it did not know TCB was performing work south of Highway 53; thus, it did not know it owed TCB the money. I find this argument disingenuous and contradictory to the defense put on at trial. At trial, Fore’s defense was that it hired TCB to perform debris removal north of Highway 53. TCB claimed that the subcontract was modified orally to include debris removal south of Highway 53. Fore denied knowledge of an oral agreement. Fore’s denial came after TCB submitted invoices to Fore, and Fore billed the County for the work south of Highway 53. The performance of TCB’s work was monitored by R.W. Beck <& Associates. Beck audited all the bills, and the County paid Fore over $12 million for TCB’s debris removal north and south of Highway 53. In addition, after TCB sent Fore a letter demanding to be paid, Fore responded on June 19, 2006, stating that TCB had not been paid because of a potential set off for interest on delayed payments from the County. Fore did not deny knowledge that TCB was performing the work.
¶ 64. I find that the foregoing facts present clear and convincing evidence of malicious conduct. Fore’s actions were willful and inflicted in the spirit of wanton disregard for TCB’s rights. Summers,
IRVING, P.J., AND RUSSELL, J„ JOIN THIS OPINION.
Concurrence in Part
concurring in part and dissenting in part:
¶ 65. I respectfully dissent in part and concur in part with the majority. I find that the record reflects that substantial evidence
When the jury has returned a verdict in a civil case, we are not at liberty to direct that judgment be entered contrary to that verdict short of a conclusion on our part that, given the evidence as a whole, taken in the light most favorable to the verdict, no reasonable, hypothetical juror could have found as the jury found. Snapp v. Harrison,699 So.2d 567 , 569 (Miss.1997); Starcher v. Byrne,687 So.2d 737 , 739 (Miss.1997); Junior Food Stores, Inc. v. Rice,671 So.2d 67 , 76 (Miss.1996); Bell v. City of Bay St. Louis,467 So.2d 657 , 660 (Miss.1985). “In reviewing a jury verdict, this Court resolves all conflicts of evidence in the appellee’s favor and determines all reasonable inferences from testimony given towards the appellee’s position. Reversal occurs only where the facts presented are so overwhelming in favor of the appellant’s position that reasonable jurors could not have found for the appellee.” Thompson Mach. Commerce Corp. v. Wallace,687 So.2d 149 , 151-52 (Miss.1997) (citations omitted).
¶ 66. Fore, in its motion for rehearing, also asserts that the majority misapprehended the law by applying an erroneous
¶ 67. In the case before us, the jury found in favor of TCB as to the existence of the disputed oral modification finding TCB orally agreed with Fore to perform as Fore’s subcontractor in the removal of debris south of Highway 53 as a modification to its existing subcontrаct with Fore for work north of Highway 53. Fore unsuccessfully claimed that TCB had removed debris south of Highway 53 in violation of its contract and billed that debris as though collected in Zone 2, an area north of Highway 53 and covered by the written subcontract between TCB and Fore. Fore denied agreeing to allow TCB to haul debris south of Highway 53, and albeit unsuccessful, Fore denied possessing any knowledge that TCB was hauling debris from south of Highway 53 in violation of the1 contract.
If 68. After finding that the oral modification occurred, the jury then awarded TCB the amount of $4,098,314.33 for performing, the oral modification of debris removal south of Highway 53.' A review of the jury instructions
¶ 69. I concur with the trial judge’s finding that disputes of material fact existed as to the oral modification as shown by the conflicting testimony and Fore’s denial. I, therefore, find no abuse of discretion in the trial court’s denial of TCB’s rеquest for a directed verdict as to the modification. Like the trial court, I find equitable estoppel fails to apply where disputes of material fact exist as to the alleged repre
¶ 70. With respect to the related doctrine of quantum meruit mentioned in TCB’s post trial filings, the record shows that during the jury-instruction conference, TCB acknowledged that it failed to put on proof of reasonable certain compensation, other than the contract terms, as is required to recover on a theory of quantum meruit. See Tupelo Redevelopment Agency v. Gray Corp., Inc.,
¶ 71. The jury found for Fore in its counterclaim against TCB, returning a verdict finding that Fore overpaid TCB for debris removal north of Highway 53. The record also shows that some of TCB’s bills should not have been submitted to Fore for compensation. Therefore, since the jury verdict as to the counterclaim was also supported by substantial evidence, I respectfully submit that our standard of review requires affirmance of the jury’s verdict as to the counterclaim as well.
¶ 72. I concur with the majority’s opinion on the issue of punitive damages. Upon review, I find no abuse of discretion in the trial court’s grant of Fore’s request for a directed verdict on the issue of punitive damages, since a question of fact existed as to whether the parties orally modified the written subcontract between them. King v. Progressive Gulf Ins. Co.,
¶ 73. I also find that the trial court properly awarded prejudgment interest from the date of the complaint, since such an award is within the trial court’s discretion. Gordon v. Gordon,
¶ 74. As stated, I would not apply es-toppel by operation of law to prohibit Fore from presenting its evidence of a denial of a material fact as to the oral modification. Instead, I would affirm the jury verdict since the record reflects substantial evidence in support of the verdict. The majority applies equitable estoppel by operаtion of law to reverse this case. Jurisprudence establishes that equitable es-toppel should only be used in exceptional circumstances. Eagle Mgmt., LLC v. Parks,
¶ 75. When disputes as to material facts exist, generally, it is the role of the trier of facts to resolve questions raised by an allegation of estoppel,
¶ 76. The majority cites to a Texas case, Allen v. Dempster Mill Manufacturing Company,
¶ 77. TCB’s post-trial filings comment upon quantum merit, and I will briefly address the applicability of this contractual remedy based upon the evidence and jury instructions in this case. The related contractual remedy of quantum meruit allows for recovery of work done outside of a contract, or not contemplated by the contract. However, TCB failed to present sufficient proof
Your Honor, if you’re not going to going to give a quantum meruit instruction for the defense I don’t need this one, and I can’t tell if they are really requesting such an instruction. I don’t think it’s a quantum meruit case because there has been no evidence of a reasonable value other than the $8.90 that we put into evidence. If they’re not going to request a quantum meruit instruction from their viewpoint then I withdraw this one. If they want one, then I want this one.
The trial court then refused the jury instruction, and TCB asserted no objection but, as stated, agreed that this case was not a quantum-meruit case. Consistent with that representation, the jury instructions show that TCB failed to request any
¶ 78. The majority applies quasi-estop-pel by operation of law to prohibit Fore from factually disрuting the oral modification. My dissent evaluates the application of quasi-estoppel and also evaluates the application of related doctrines of equitable estoppel and quantum meruit, albeit briefly, while distinguishing between the doctrines.
¶ 79. The majority cites Bailey v. Estate of Kemp,
¶ 80. The Bailey court cites to Bott v. J.F. Shea Company, Inc.,
¶ 81. In Bott, the Fifth Circuit recognized that quasi-estoppel “precludes a party from asserting, to another’s disadvantage, a right inconsistent with a position [it has] previously taken. The doctrine applies when it would be unconscionable to allow a person to maintain a position inconsistent with one to which he acquiesced, or from which he accepted a benefit.” Id. at 512. The Bott court found, however, that despite the general contractor’s receipt of the insurance certificates with the improper name and despite the fact that general contractor allowed the subcontractоr to commence work and be paid for its completion, the general contractor was not precluded from later enforcing the contract provisions against the subcontractor. Id. at 512-13. The court found that the general contractor’s failure to enforce the contract provisions against the subcontractor was not a waiver of the subcontractor’s obligations under the contract, even though the general contractor had acted inconsistently by accepting the insurance certificates with the incorrect name and allowing the subcontractor to work without proper insurance. Id; see also Wood Naval,
¶ 82. In conclusion, with respect to equitable estoppel, I concur with the trial judge’s determination that a dispute of material fact as to the issue of modification existed and also as to damages; therefore, such disputes bar an application of equitable estoppel by operation of law. Based on our limited scope of review, we cannot retry the case for the parties on appeal nor can the parties retry their case on appeal. Gale v. Thomas,
. In denying the appellant’s post-trial motion for a JNOV, the trial court again found sufficient evidence supporting the jury verdict.
. In Wal-Mart Stores, Inc. v. Johnson,
When this Court reviews the action of the jury after the trial court has refused to grant a new trial on the question of damages, the question then becomes whether the verdict was either so excessive or made-quate as to shock the conscience and to indicate bias, passion and prejudice on the part of the jury, or, whether the jury failed to respond to reason.
Dorris v. Carr,
. The transcript of the jury-instruction conference reflects that the parties and the judge discussed at length the applicability of quantum meruit. TCB agreed that this case failed to constitute a quantum meruit case, and TCB had not pled quantum meruit. TCB's case constituted a contract case to determine whether there was a meeting of the minds as to the formation of an oral modification to the subcontract, and if so, then the price set forth in the contract would be awarded, less payments made by Fore. The only evidence of reasonable value was the cost set forth as a term of the contract. See record transcript pages 791-92. The transcript of the juiy-instruction conference shows that TCB withdrew the instruction that seemed to raise the issue of quantum meruit.
. See generally Greater Canton Ford Mercury, Inc. v. Lane,
. Warwick v. Matheney,
. See record transcript page 795.
. See generally Barnes, Broom, Dallas & McLeod, PLLC v. Estate of Cappaert,
.See also Byblos Corp. v. Salem Farm Realty Trust,
. See AmFed. Co., LLC v. Jordan,
. See also Miss. Dep’t of Public Safety v. Stringer,
. See generally In re Estate of Fitzner,
. The trial judge herein provided no instructions to the jury to consider a certain sum, stating: "I’m going to leave the amount of the verdict up to the jury in its discretion.” TCB raised no objection to this ruling.
. This key dispute as to the representation, or oral modification, was addressed by the trial court in the record, and the court recognized that the key dispute of material fact concerned whether the or not the removal of debris south of Highway 53 was authorized by Fore.
. C.E Frazier Constr. Co. v. Campbell Roofing and Metal Works,
. Citizens Nat’l Bank of Meridian v. L.L. Glascock, Inc.,
. Such recovery requires proof of reasonable measure of compensation.
. I find that quantum meruit applies as a contractual remedy in cases involving written or oral contracts where additional work is performed, in anticipation of payment, where the work is not contemplated by the oral or written contract and sufficient proof of reasonably certain compensation due is shown.
. Tupelo Redevelopment Agency,
. Proof of a reasonable amount of compensation is a prerequisite to establishing grounds for recovery under a quantum meruit theory. Langham v. Behnen,
. See record transcript page 792.
. The special interrogatories only request that the jury provide whether they find that the proof showed by a preponderance of evidence that the oral modification occurred, and if so, what amount of money TCB was entitled to receive for hauling debris south of Highway 53. However, the special interrogatories, like the other jury instructions, failed to provide any language regarding equitable estoppel, quantum meruit, or other equitable basis for relief.
. The Mississippi Supreme Court held association members to their prior association articles of agreement. The court also held that the members were estopped from denying their membership, or to claim they were no longer bound by the articles of agreement, due to conduct inconsistent with a denial of membership. The court did not apply estoppel to establish the underlying articles of agreement of the association membership; rather, the members' subsequent conduct relating to the articles of agreement and subsequent change in their partnership status, applied to estop them from denying their membership in that pri- or agreement.
