MEMORANDUM OPINION AND ORDER REGARDING SUMMARY JUDGMENT MOTIONS
FACTUAL BACKGROUND
A. The Nuclear Waste Policy Of 1982 Act Required The Federal Government To Provide For The Permanent Disposal Of High Level Radioactive Fuel.
In 1982, Congress enacted the Nuclear Waste Policy Act, 42 U.S.C. § 10101 et seq. (“NWPA”), pursuant to which the federal government assumed the legal duty to “provide for the permanent disposal” of spent nuclear fuel
By June 30,1983, the Department of Energy (“DOE”) was required to enter into contracts with the generators and owners of SNF and HLW that required DOE to accept, transport, and dispose of such SNF and HLW. See 42 U.S.C. § 10222(b)(2) (“No [SNF or HLW] may be disposed of by the Secretary ... unless the generator or owner of such [SNF or HLW] has entered into a contract with the Secretary under this section by not later than — June 30, 1983[.]”). Accordingly, DOE established a Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste and set the fee amounts to be paid by utilities into the Nuclear Waste Fund to fund acceptance and disposal of SNF (hereinafter the “Standard Contract”). See 42 U.S.C. § 10222(a)(1) (“[T]he Secretary is authorized to enter into contracts with any person
The Standard Contract provided, in return for the payment of fees from a utility,
The priority of SNF and/or HLW acceptance was to be determined by the material’s age, calculated as of the date of discharge from a nuclear power reactor. See 10 C.F.R. § 961.11 at Art. VI(B)(l)(a) (“[A]cceptance priority shall be based upon the age of the SNF and/or HLW as calculated from the date of discharge of such material from the civilian nuclear power reactor.”); see also Gov’t Resp. at 8. DOE’s acceptance of SNF and/or HLW would be prioritized, pursuant to Delivery Commitment Schedules (“DCSs”) submitted by each utility and approved by DOE. See 10 C.F.R. § 961.11 at Art. V(B)(1) (“After DOE has issued its proposed acceptance priority ranking ... the Purchaser shall submit to DOE the delivery commitment schedule(s) which shall identify all SNF and/or HLW the Purchaser wishes to deliver to DOE beginning sixty-three (63) months thereafter.”); see also Gov’t Resp. at 8-9. The Standard Contract further provided that DOE first would accept the oldest SNF and/or HLW. See 10 C.F.R. § 961.11 at Art. VI(B)(1)(A) (“DOE will first accept from Purchaser the oldest SNF and/or HLW for disposal in the DOE facility, except as otherwise provided for in paragraphs B and D of Article V.”). A utility, however, had the right to
On May 25, 1994, however, DOE announced that it would not be able to start accepting SNF from any nuclear utilities until 2010, at the earliest. See Office of Civilian Radioactive Waste Management: Waste Acceptance Issues, 60 Fed. Reg. 21,793, 21,794 (May 3, 1995) (“The DOE currently projects that the earliest possible date for acceptance of waste for disposal at a repository is 2010.”); Report to the Congress by the Secretary of Energy on Reassessment of the Civilian Radioactive Waste Management Program (Nov. 29, 1989), at vii (“This schedule shows a significant slip for the expected start of repository operations — from the year 2003 to approximately 2010.”).
B. On June 30, 1983, System Fuels Inc. Entered Into A Department Of Energy Standard Contract For Disposal Of Spent Nuclear Fuel And/Or High-Level Radioactive Waste.
In 1983, the Nuclear Regulatory Commission (“NRC”) issued a license to System Fuels, Inc. (“SFI”) and the South Mississippi Power Association (“SMEPA”) to operate Unit 1 of Grand Gulf Nuclear Station (“Grand Gulf’). See Compl. II2. On June 30, 1983, SFI entered into a Standard Contract with DOE on behalf of SFI, System Energy Resources (“SERI”), and SMEPA. Id. HU 2, 9. SERI and SMEPA own Grand Gulf, but SFI performs the duties of the Purchaser under the Standard Contract. Id. at n. 1; see also Franklin Aff. U 5. As of November 5, 2003, System Energy and SMEPA paid approximately $148 million into the Nuclear Waste Fund for the removal of SNF by the DOE, pursuant to the terms of the Standard Contract. See Compl. UU1, 9, 23.
The operation of Grand Gulf Unit 1 generated and continues to generate SNF that is stored on site in a “wet pool”.
PROCEDURAL HISTORY
On November 5, 2003, SFI, SERI, and SMEPA (hereinafter “SFI”) filed a Complaint in the United States Court of Federal Claims alleging: a partial breach of the June 30, 1983 Standard Contract (Count I); and breach of the implied covenant of good faith and fair dealing (Count II). On that date, the case was assigned to the undersigned
On January 5, 2004, the Government filed an unopposed Motion to Stay, arguing that the Standard Contract did not set a mandatory minimum SNF acceptance rate, a prerequisite for any damage claim. The Government also argued there were outstanding summary judgment motions in similar SNF cases that were likely to impact this case. On March 4, 2004, the Government’s Motion to Stay was denied. On March 15, 2004, the Government filed an Answer.
As of April 14, 2004, forty-five SNF cases were pending in the United States Court of Federal Claims. The Government filed a “Motion to Stay all Proceedings or, in the Alternative, for Coordinated Discovery Regarding the Rate and Schedule Issues” in almost half of the pending SNF cases. On that date, however, the court issued an Order requiring SFI to submit a report specifying discovery plans and objectives, including, but not limited to: the nature and scope of discovery anticipated to respond to the Government’s standard dispositive motion on the rate of acceptance; any circumstance that may affect the timing of discovery or trial; if known, whether discovery, including depositions, previously provided in the old cases on the same issues, would suffice in this case (if the Government consented to full use of the depositions in the new case); and additional responses to the issues raised in the Government’s motion to stay or coordinate discovery. The court also required that the Government issue a report presenting views on the same matters, including, but not limited to, information regarding: how the Government proposes, either with or without a “coordination order,” to provide access to and use of the material produced in the old SNF cases to the new SNF eases; any conditions that it would impose on the use of such materials in the new SNF eases; the nature, extent, and schedule of any discovery the Government anticipates requesting from any SNF plaintiff, old or new, before the trials are concluded in the lead cases; and comments on SFI’s responses to its Motion for a Stay or Coordination.
On April 23, 2004, SFI filed a Response opposing a stay of this case. In addition, the court was advised that SFI would file a Motion for Summary Judgment on the issue of liability, pursuant to Northern States Power Co. v. United States,
On October 29, 2004, SFI filed a Motion for Summary Judgment on Liability and Proposed Findings of Uncontroverted Facts in support thereof. On December 6, 2004, the Government filed a Response and Cross-Motion for Summary Judgment. On January 5, 2005, SFI filed a Reply in Support of the Motion for Summary Judgment on Liability and Response to Defendant’s Cross-Motion for Summary Judgment. On February 10, 2005, the Government filed a Reply.
On February, 25, 2005, the court held an argument on the pending summary judgment motions, during which SFI agreed to provide evidence of damages incurred arising directly from the DOE’s partial breach of the Standard Contract. On March 4, 2005, SFI filed an affidavit of Charles B. Franklin to verify that approximately $4.75 million had been incurred as of that date, as a result of the breach caused by DOE’s failure to accept
DISCUSSION
A. Jurisdiction.
The United States Court of Federal Claims has “jurisdiction to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1). The Tucker Act, however, is only a “jurisdictional statute; it does not create any substantive right enforceable against the United States for money damages.” United States v. Testan,
In this case, SFI properly plead a contractual relationship with the Government. See Trauma Service Group v. United States,
B. Standing.
The lower federal courts have been advised to “decide standing questions at the outset of a case. That order of decision (first jurisdiction then the merits) helps better to restrict the use of the federal courts to those adversarial disputes that Article III defines as the federal judiciary’s business.” Steel Co. v. Citizens for a Better Env’t,
Since standing is a component of jurisdiction that the court has the authority to raise sua sponte, the issue will be addressed. See Folden v. United States,
C. Standard For Decision On Summary Judgment.
On a motion for summary judgment, if there is no genuine issue as to any material fact, the moving party is entitled to judgment as a matter of law. See American Pelagic Fishing Co. v. United States,
The burden of demonstrating the absence of any genuine issue of material fact is on the party moving for summary judgment. See Celotex Corp. v. Catrett,
A trial court is required to resolve all doubt over factual issues in favor of the non-moving party. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,
When evaluating cross-motions for summary judgment, as are presented in this case, “the court must evaluate each party’s motion on its own merits, taking care in each instance to draw all reasonable inferences against the party whose motion is under consideration.” Mingus Constructors, Inc. v. United States,
D. Resolution Of Plaintiff’s October 29, 2004 Motion For Summary Judgment Establishing Liability.
1. The United States Court Of Appeals For The Federal Circuit Has Settled The Issue Of Whether The Government Breached The Standard Con-
The United States Court of Appeals for the Federal Circuit has settled the legal issue of whether the Government’s failure to begin accepting nuclear waste by January 31, 1998, constituted a breach of contract. See Maine Yankee Atomic Co.,
SFI’s June 30, 1983 Standard Contract also required that the Government begin accepting nuclear waste from utilities by January 31, 1998. See Compl. 115. This requirement was not conditioned on the occurrence
The Government does not dispute that SFI has paid approximately $148 million to date, pursuant to the applicable fee schedule. See Answer H 9; Gov’t Prop. Find. Fact HIT 5, 28. Nor does the Government dispute that DOE has not begun to accept, transport, and dispose of any SNF, including that of SFI. See Office of Civilian Radioactive Waste Management: Waste Acceptance Issues, 59 Fed. Reg. 27,007, 27,008 (May 25, 1994) (“The Department currently projects that the earliest possible date for acceptance of waste for disposal at a repository is 2010.”); see also Maine Yankee Atomic Power Co.,
Therefore, the Government admitted on February 10, 2005 that “DOE’s delay in beginning acceptance of SNF from the commercial nuclear industry ... constitutes a partial breach of the Standard Contract!.]” See Govt. Reply at 1; see also TR at 29-30. Accordingly, the court has determined that the Government breached the June 30, 1983 Standard Contract with SFI on January 31, 1998.
2. As A Matter Of Law, The Date Of The Government’s Breach Is Not Determined By The Annual Capacity Report Or Delivery Commitment Schedules.
The Standard Contract also required DOE to issue an Annual Capacity Report (“ACR”) “for planning purposes” to set forth the projected annual receiving capacity for the DOE facility(ies) and the annual acceptance ranking for the disposal of SNF and/or HLW. See 10 C.F.R. § 961.11 at Art. IV(B)(5)(b) (“Beginning not later than July 1, 1987, DOE shall issue an annual capacity report for planning purposes. The report shall set forth the projected annual receiving capacity for the DOE facility(ies) and the annual acceptance ranking relating to DOE contracts for the disposal of SNF and/or HLW including, to the extent available, capacity information for ten (10) years following the projected commencement of operation of the initial DOE facility.”). In addition, the Standard Contract required DOE to issue an annual acceptance priority ranking, based on the age of the SNF and/or HLW, with the oldest fuel having the highest priority. See 10 C.F.R. § 961.11 at Art. IV(B)(5)(a) (“Beginning on April 1, 1991, DOE shall issue an annual acceptance priority ranking for receipt of SNF and/or HLW at the DOE repository____The oldest fuel will have the highest priority for acceptance, except as provided in paragraphs B and D of Article V and paragraph B.3 of Article VI hereof.”).
After the ACR was issued, the utilities were to submit DCSs that identified “all SNF and/or HLW the Purchaser wishes to deliver to DOE beginning sixty-three (63) months thereafter.” See 10 C.F.R. § 961.11 at Art. V(B)(1) (“After the DOE has issued its proposed acceptance priority ranking ... the Purchaser shall submit to DOE the [DCSs] which shall identify all SNF and/or HLW the Purchaser wishes to deliver to DOE beginning sixty-three (63) months thereafter.”). The DCSs required approval by DOE. Id. (“DOE shall approve or disapprove such schedules within three (3) months after receipt.”). In the event of disapproval of a DCS, the parties could seek to negotiate a mutually acceptable schedule. Id. at Art. V(B)(2) (stating that if revised schedule(s) are not approved by DOE, DOE “shall submit its proposed schedule____ If these are not acceptable to the Purchaser, the parties shall promptly seek to negotiate mutually
The submission, review, and approval of DCSs also included an additional step that involved final delivery schedules. Id. (“Final delivery schedule(s) ... for delivery of SNF and/or HLW covered by an approved delivery commitment schedule shall be furnished to DOE by Purchaser.”). There also is no evidence that the process set out in Article V of the Standard Contract was ever completed, since final delivery schedules were not issued. See Maine Yankee Atomic Power Co.,
In fact, DOE unilaterally refused in 1996 to approve or disapprove any new DCSs and voided the DCSs from utilities that previously had been approved. See PI. Motion for S.J. at 15. Thus, according to DOE’s current Contracting Officer, it would have been impossible for a nuclear utility to obtain approval for their DCSs during that time period. Id. at 4. Although DOE resumed the DCS process in July of 2004, those activities were suspended again in December 2004, when DOE informed the industry that “resumption of the DCS process was premature” and that DOE would not resume the DCS process until after the Yucca Mountain repository began operating. See Pl. Reply Ex. A; see also Entergy Nuclear Indian Point 2, LLC v. United States,
Since SFI never submitted a DCS to DOE for approval, the Government argued that DOE had no commitment to accept any SNF from SFI. See Gov’t Resp. at 7. In the alternative, the Government argued that since DOE was not scheduled to accept SFI’s SNF and/or HLW prior to 2008 and SFI did not ask DOE to accept the fuel outside of the “oldest fuel first” acceptance queue, DOE could not have breached SFI’s Standard Contract before 2008. See Gov’t Resp. at 2-3.
As a matter of law, however, the Government cannot amend the terms of the Standard Contract sua sponte and without separate consideration evidencing acceptance of new terms. See Cal. Fed. Bank v. United States,
There is absolutely no evidence in the record that the ACR and DCSs were binding on either party nor were they intended to create a separate contract between the parties. In fact, the Standard Contract provided that the ACRs were only created “for planning purposes.” See 10 C.F.R. § 961.11 at Art. IV(B)(5)(b); see also Commonwealth Edison Co. v. United States,
Therefore, the court has determined that, as a matter of law, the ACR and DCSs did not amend the Standard Contract and SFI’s failure to submit a DCS is irrelevant and does not alter the Government’s obligation under the Standard Contract to accept and store SNF.
3. As A Matter Of Law, SFI Has Proffered Sufficient Evidence Of Damages To Establish Liability For A Breach Of Contract.
A long lead time is required to plan and construct SNF dry storage facilities due to the extremely hazardous nature of SNF, the logistical problems associated with storing it safely, and the significant public interest in safely storing such materials. See 42 U.S.C. § 10131. Therefore, SFI began planning and developing an ISFS in 2003 to prepare for the time when the wet pool at Grand Gulf will reach capacity in 2007. See Franklin Aff. 111Í 6, 7. As of March 4, 2005, SFI alleges to have spent approximately $4.75 million in order to build an ISFS for SNF storage as a result of the Government’s breach. Id. 11119-10.
The United States Court of Appeals for the Federal Circuit requires evidence of a breach and at least a non-cfe minimus amount of damages to establish liability for a breach of contract. See Entergy Nuclear Indian Point 2,
Therefore, under the precedent binding the court, SFI has proffered sufficient evi
4. As A Matter Of Law, SFI’s Election To Continue Performance Under The Standard Contract Does Not Bar The Recovery Of Damages Caused By A Partial Breach.
SFI has elected not to treat DOE’s failure to comply with the January 31, 1998 date to commence collection of SNF as a total breach of the June 30, 1983 Standard Contract.
It has been settled by the United States Court of Appeals for the Federal Circuit that:
A material breach does not automatically and ipso facto end a contract. It merely gives the injured party the right to end the agreement; the injured party can choose between canceling the contract and continuing it. If he decides to close the contract and so conducts himself, both parties are relieved of their further obligations and the injured party is entitled to damages at the end of the contract term (to put him in the position he would have occupied if the contract had been completed). If he elects instead to continue the contract, the obligations of both parties remain in force and the injured party may retain only a claim for damages for partial breach.
Cities Service Helex, Inc. v. United States,
Therefore, as a matter of law, SFI’s election to continue performance under the Standard Contact does not bar SFI from the recovery of damages caused by DOE’s partial breach.
E. Resolution Of The Government’s December 6, 2004 Cross-Motion For Summary Judgment.
1. On Count I-Genuine Issues Of Material Fact Are At Issue As To Whether The Government Has Repudiated The Standard Contract.
The Government seeks summary judgment on Count I (Partial Breach of Contract) arguing that SFI may recover damages only if the Government repudiated the Standard Contract, rendering it void. See Gov’t. Resp. and Cross-Motion for S.J. at 17-19. SFI denies that the Government repudiated the Standard Contract and instead asserts that the Government only delayed performance. See PL Motion S.J. at 18-19. Repudiation is a “statement by the obligor to the obligee indicating that the obligor will commit a breach that of itself would give the obligee a claim for damages for total breach.” Mobil Oil Exploration & Produc. Southeast, Inc. v. United States,
Despite the Government’s assertions to the contrary, as a matter of law, a “[t]he injured party does not change the effect of a repudiation by urging the repudiator to perform in spite of his repudiation.” Restatement § 257; see also 9 Corbin § 981 at 830 (“[The] doctrine that an anticipatory repudiation is not a breach until accepted as such by the injured party has been repudiated.”). The rationale behind this doctrine is that “the repudiator has a power of retraction as long as there has been no substantial change of position by the injured party; and the latter’s continuing to urge performance may be properly held to keep this power of retraction alive.” Corbin § 981 at 831. Thus, “[a]ny possibility that the injured party might unfairly mislead the repudiator is avoided by the duty of good faith and fair dealing.” Restatement § 257 cmt. a (internal citations omitted).
In this case, the Government does not admit to repudiation, although the public record raises serious questions as to whether the Standard Contract is void in fact. See Sacramento Municipal Utility Dist.,
One additional comment is in order. SFI’s strategy not to claim that DOE repudiated the Standard Contract is not without risk, because the party that has not repudiated a contract can take “reasonable efforts in the form of affirmative steps ... to mitigate damages.” Robinson v. United States,
2. On Count II-Breach Of The Implied Covenant Of Good Faith And Fair Dealing.
The Complaint also alleged that the Government breached the implied duty of good faith and fair dealing under the Standard Contract by: DOE’s implementation and cancellation of the DCS process; DOE’s failure to publish annual APR/ACRs; DOE’s use of the ACR process to unilaterally limit the amount of SNF/HLW it would accept from each utility; and the arguments made in the various spent nuclear fuel lawsuits since the 1990’s. See Compl. HH 26-30; see also PI. Reply 8-13. SFI, however, has failed to proffer sufficient evidence to overcome the presumption that the relevant government officials have acted in good faith. See Am-Pro Protective Agency v. United States,
SFI relies exclusively on the testimony of David Zabransky, the DOE Contracting Officer, that DOE did not change the ACR rates from year to year because it was attempting to minimize the commitments under the Standard Contract. See PI. Reply at 10 n. 4. This testimony, however, is not clear and convincing evidence of any intent by DOE specifically to harm SFI. At best, it indicates only an employee’s opinion that DOE was attempting to limit its contractual responsibilities and any potential liability. See Am-Pro Protective Agency,
Therefore, the Government’s Cross-Motion for Summary Judgment on Count II-Breaeh of the Implied Covenant of Good Faith and Fair Dealing, set forth in Paragraphs 26-30 of the Complaint, is granted.
CONCLUSION
For the reasons discussed herein, SFI’s October 29, 2004 Motion for Entry of an Order that the Government is liable for a partial breach of SFI’s June 30, 1983 Standard Contract is granted. Whether any specific damages were caused by the Government’s partial breach and the final determination of damages due, if any, has not been adjudicated and can only be determined after an evidentiary hearing. Therefore, the Government’s December 6, 2004 Cross-Motion for Summary Judgment on Count I and Request for Rule 56(f) Discovery on the Issue of Liability are denied.
The Government’s December 6, 2004 Cross-Motion for Summary Judgment on Count II-breach of implied covenant of good faith and fair dealing, however, is granted.
The Clerk of the Court is hereby ordered to enter partial summary judgment in accordance with this Memorandum Opinion and Order.
IT IS SO ORDERED.
Notes
. The facts discussed herein are derived from: the November 5, 2003 Complaint ("Compl.”); the Government’s March 15, 2004 Answer ("Answer”); Plaintiff's October 29, 2004 Motion and Memorandum for Summary Judgment on Liability ("PI. Motion for S.J.”); the Government’s December 6, 2004 Response thereto and Cross-Motion for Summary Judgment on Counts I and II (“Gov’t Resp. and Cross-Motion for S.J.”); the Government’s December 6, 2004 Proposed Findings of Uncontroverted Fact ("Gov’t Prop. Find. Fact”); Plaintiff's January 5, 2005 Reply ("Pl.Reply”); the Government’s February 10, 2005 Reply in Support of Cross-Motion for Summary Judgment ("Gov’t Reply”); February 15, 2005 Oral Argument ("TR”); and a March 3, 2005 Affidavit of Charles B. Franklin (Manager, Project Management, Fleet Dry Fuel Storage for Entergy Services, the parent company for System Energy Resources) ("Franklin Aff.”).
. Spent Nuclear Fuel ("SNF") is defined as fuel that “has been withdrawn from a nuclear reactor following irradiation, the constituent elements of which have not been separated by reprocessing.” 42 U.S.C. § 10101(23). SNF contains toxic uranium and toxic byproducts, such as plutonium. "Moreover, SNF 'remains radioactive after it is removed from a nuclear reactor and must be isolated in safe disposal facilities for thousands of years.’" Sacramento Municipal Utility District v. United States,
. High-level radioactive waste ("HLW”) was defined by Congress as "highly radioactive material resulting from the reprocessing of spent nuclear fuel, including liquid waste produced directly in reprocessing ... and other highly radioactive material that the [Nuclear Regulatory] Commission, consistent with existing law, determines by rule requires permanent isolation.” 42 U.S.C. § 10101(12).
. The "person [or entity] who generates or holds title to high-level radioactive waste, or spent nuclear fuel, of domestic origin” is referred to in the Standard Contract as the "Purchaser.” 10 C.F.R. § 961.11.
. "Utility” or "utilities” refers to an entity or entities that generate or hold title to high-level radioactive waste, or spent nuclear fuel, of domestic origin, and have entered into a DOE Standard Contract.
. Nuclear plants replace the nuclear fuel assemblies used to generate electricity approximately every 18 months and store those assemblies on site in pools of treated water referred to as "wet pools." See Indiana Michigan Power Co. v. United States,
. Prior to that time, a considerable amount of procedural maneuvering took place in other SNF cases. In January 2001, in Yankee Atomic Electric Co. v. United States, No. 98-126C (Fed.Cl. July 30, 2003), the Government had filed a Motion to Consolidate all of the SNF cases before the United States Court of Federal Claims. The Honorable Diane G. Sypolt assumed the responsibilities of overseeing a consolidated discovery. After the conclusion of discovery in Yankee Atomic, the Government renewed the Motion to Consolidate, which Chief Judge Edward J. Damich stayed pending the issuance of decisions in six SNF cases, designated as “lead" or "accelerated” cases for resolution of certain issues. On July 30, 2003, the Government had filed a Renewed Motion to Consolidate in Yankee Atomic. On January 4, 2004, Chief Judge Damich denied that motion.
. The United States Court of Federal Claims has issued a number of opinions and orders in SNF cases regarding the Government’s liability based on this precedent. See, e.g., Sacramento Municipal Utility Dist. v. United States,
. The United States Court of Appeals for the D.C. Circuit also has discussed the requirements of the Standard Contract in Indiana Michigan Power Co. v. Dept. of Energy,
The NWPA provided that "contracts entered into under this section shall provide that — ... in return for payment of fees established by this section, the Secretary, beginning not later than January 31, 1998, will dispose of the HLW or SNF[.]” 42 U.S.C. § 10222(a)(5)(B). Therefore, after the utility paid the requisite fees, DOE had both a statutory and contractual duty to begin accepting SNF by January 31, 1998. See Indiana Michigan Power Co.,
. Some plaintiffs in Maine Yankee and Northern States filed DCSs after the January 31, 1998 deadline for DOE to begin collecting nuclear waste from the utilities. See Sacramento Municipal Utility Dist.,
. In addition, DCS approval was contingent upon the setting of an ACR. See 10 C.F.R. § 961.11 at Art. V(B)(1). Several decisions of the court have held that DOE's obligation to accept SNF under Article II of the Standard Contract is not dependent upon the existence of an ACR or upon a commitment for the DOE to accept SNF from a particular party before or after the January 31, 1998 breach. See e.g., Sacramento Municipal Utility Dist.,
. Although DOE was scheduled to begin acceptance in 1998, DOE does not anticipate accepting any SNF from Grand Gulf prior to 2010. See
. The Government’s alternative legal bases for seeking summary judgment were rejected by the court, as discussed herein.
