Lead Opinion
Opinion for the court filed by Chief Judge RADER. Opinion coneurring-inpart, dissenting-in-part filed by Circuit Judge NEWMAN.
On summary judgment, the United States Court of Federal Claims determined that the United States breached its contract with Plaintiffs-Appellants System Fuels, Inc., System Energy Resources, and South Mississippi Electric Power Association (collectively “Plaintiffs”) for the removal of spent nuclear fuel. Sys. Fuels, Inc. v. United States,
I.
In 1983, Congress enacted the Nuclear Waste Policy Act of 1982 (“NWPA”), Pub.L. No. 97-425, 96 Stat. 2201 (codified at 42 U.S.C. §§ 10101-10270 (2006)), to provide for the Government’s collection and disposal of spent nuclear fuel (“SNF”) and high-level radioactive waste (“HLW”). The NWPA authorized the Department of Energy (“DOE”) to contract with the owners of SNF and HLW for disposal. 42 U.S.C. § 10222(a)(1). In return for the payment of fees into the Nuclear Waste Fund, the Standard Contract provided that the DOE would begin to dispose of the SNF and HLW “not later than January 31, 1998.” 42 U.S.C. § 10222(a)(5)(B); 10 C.F.R. § 961.11 (2011). The Standard Contract provides that “[t]he Purchaser shall arrange for, and provide, all preparation, packaging, required inspections, and loading activities necessary for the transportation of SNF and/or HLW to the DOE facility.” 10 C.F.R. § 961.11 (Article IV. A.2). Because collection and disposal of SNF and HLW did not begin on January 31, 1998, this court held in Northern States Power Co. v. United States,
On June 30, 1983, System Fuels, Inc. entered into the DOE’s Standard Contract on behalf of itself, System Energy Resources, and South Mississippi Power Association. SFI I,
Every 18 months, the reactor at Grand Gulf shuts down to facilitate removal of fuel assemblies, which are then placed in two onsite storage facilities for 20 to 25 days during routine maintenance. Id. at 779. In an effort to explore their options for dry fuel storage, Plaintiffs sought guidance from an engineering services firm in the commercial nuclear industry. This firm recommended the “best short-term option for increasing spent fuel storage capacity at Grand Gulf was to recover cells currently inaccessible in the existing [on-site storage facilities].” Id. at 780. Plaintiffs also contracted with a dry cask storage system company and explored long-term options. Plaintiffs undertook construction of dry fuel storage because the core of the Grand Gulf reactor would reach capacity in 2007, and, by their estimates, the Government would not remove waste until 2022. Id. at 781. As a business practice, Plaintiffs maintain a full core reserve — a practice beyond current federal requirements. Id. at 782. Plaintiffs determined that they could maintain this business practice through 2005 and, with cell recovery efforts, accommodate the SNF and HLW discharges through 2007. Id. at 782-83.
In constructing the ISFSI, Plaintiffs created six categories of capital work operations: spent fuel studies, ISFSI design and construction, cask fabrication facility, dry fuel equipment storage building, ISFSI electrical and security systems, and auxiliary building door modification. Plaintiffs recorded and tracked costs associated with the dry fuel storage facility. Id. at 783. Plaintiffs sought damages for the capital work operations, totaling $10,591,000, and cost of capital to finance these operations, totaling $1,587,000. Id. at 783, 785.
The trial court revisited its causation analysis after this court rendered the following decisions: Yankee Atomic Electric Co. v. United States,
Plaintiffs appeal the trial court’s refusal to award the cost of borrowed funds and overhead costs as mitigation damages. The Government appeals on the ground that the trial court’s causation analysis did not include a comparison of breach and non-breach worlds under the Standard Contract. This court has jurisdiction under 28 U.S.C. § 1295(a)(3).
II.
This court reviews the factual findings of the United States Court of Federal Claims for clear error, Ind. Mich.,
III.
Plaintiffs sought $1,587,000 as damages for the cost of borrowed funds to construct their dry fuel storage facility. SFI II,
As this court stated in England, “[t]he no-interest rule is an aspect of the basic rule of sovereign immunity.”
Although expressing concerns about the policy and uniform application of England, the trial court ultimately applied the rule of that case and denied interest. In Energy Northwest v. United States, issued after the trial court’s judgment in the present case, this court addressed those concerns and reaffirmed England, distinguishing it from cases where the Government has been held liable for interest.
IV.
Plaintiffs incurred additional overhead costs when managing the six capital work operations. Plaintiffs maintained a separate accounting for overhead costs, consistent with the Generally Accepted Accounting Principles and Federal Energy Regulatory Commission (“FERC”) regulations. The separate accounting, referred to as the “capital suspense loader,” includes the cost of administrative and engineering personnel supporting capital construction projects. J.A. 348-49, 351. These overhead costs consist of two pools: (1) administrative and general costs for personnel at corporate headquarters and (2) nuclear-specific costs for personnel at the Nuclear South headquarters and Grand Gulf site. J.A. 349. The trial court acknowledged that “DOE was aware that Plaintiffs were required to account to FERC for all costs incurred.” SFI II,
As explained in Indiana Michigan, “[djamages for a breach of contract are recoverable where: (1) the damages were reasonably foreseeable by the breaching party at the time of contracting; (2) the breach is a substantial causal factor in the damages; and (3) the damages are shown with reasonable certainty.”
Thus, Plaintiffs may recover overhead costs incurred for mitigation-related work. The record shows that Plaintiffs used an internal accounting system with particular codes for the “capital suspense loader.” Further, the record shows that the internal accounting system allocates on a monthly basis the overhead associated with the pool and charges accounts for the appropriate project. J.A. 348-50. Thus, Plaintiffs used accounting procedures “as mandated by FERC,” J.A. 349, and “consistent with Generally Accepted Accounting Principles,” J.A. 351. The trial court clearly erred in finding that these accounting records did not “demonstrate the effect of the mitigation project on the capital pools entitlement with ‘reasonable particularity.’ ”
Therefore, because the record fully supports Plaintiffs’ proof of overhead costs, this court reverses the trial court’s grant of offset of damages for the “capital suspense loader” overhead costs.
V.
In Yankee Atomic, this court determined that a SNF utility company “had the burden to provide the contractual acceptance rate and apply that rate before suggesting that the Government’s breach was a substantial factor in causing the [Plaintiffs’] claimed expenses.”
In SFI II, the trial court determined that Plaintiffs’ mitigation was foreseeable:
[T]he record contains clear and convincing evidence that on June 30, 1983, it was “foreseeable” to DOE that, if performance could not be commenced by January 31, 1998, Plaintiffs would have to make interim arrangements to store SNF and HLW and DOE could have foreseen that such interim arrangements could entail the need to plan, design, and construct dry fuel storage and the [sic] incur costs to borrow funds to finance those mitigation efforts.
In SFI III, the trial court weighed evidence concerning causation of the contested damages and application of the 1987 Annual Capacity Report Rate.
The trial court also weighed evidence regarding the “cell recovery effort.” After comparing the breach and non-breach worlds, the trial court determined that Plaintiffs were “not entitled to include[] $184,208 for the cell recovery effort as damages.” Id. at 105-06. The trial court then applied this court’s holding in Yankee Atomic,
Review of the record shows that the trial court’s damages analysis in SFI II included comparison between breach and non-breach worlds, and offsets were awarded where appropriate. In SFI III, the record confirms the trial court’s application of the 1987 Annual Capacity Report Rate and also applicable additional adjustments. The record evidence further supports the trial court’s comparison between the breach and non-breach worlds for the assessment of damages. This court discerns no error in these determinations. Thus, the trial court accurately addressed causation as set forth by Yankee Atomic and applied offsets as necessary. This court affirms the trial court’s causation analysis and its revised nominal damages award.
YI.
Because the trial court properly adhered to the decision of England, this court af
AFFIRMED-IN-PART AND REVERSED-IN-PART.
Costs
Each party shall bear its own costs.
Concurrence Opinion
concurring in part, dissenting in part.
In this arena of varied Federal Circuit pronouncements on diverse facts, the court now carves an exception into the rule that damages due to breach of contract shall render the injured party monetarily whole. The rule, applicable to the government as to all contracting entities, is that when the non-breaching party is required to incur expenditures in order to mitigate the consequences of breach, the cost of those expenditures is compensable as damages. That cost of mitigation is not “interest on a claim,” but a component of damages. Thus the “no-interest rule” is inapplicable. I respectfully dissent from the portion of the court’s decision that denies recovery of such damages.
Discussion
Analytical care is required to avoid blurring the distinction between the cost of money expended to mitigate a breach and interest awarded on a judgment for damages. The “non-interest” statute is directed to interest on an adjudicated claim:
28 U.S.C. § 2516. Interest on claims and judgments
(a) Interest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a contract or Act of Congress expressly providing for payment thereof.
This statute does not apply to the System Fuels situation. System Fuels incurred capital costs to construct an Independent Spent Fuel Storage Installation, a facility that was required to be constructed in view of the government’s partial breach of the Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste. “All capital raised by a corporation has a cost....” LaSalle Talman Bank, F.S.B. v. United States,
This distinction has long been recognized. In Library of Congress v. Shaw,
Recognition that damages include the cost of the money expended in mitigation is exemplified in the FIRREA cases, e.g., Bluebonnet Sav. Bank, F.S.B. v. United States,
“Government liability in contract is viewed as perhaps ‘the widest and most unequivocal waiver of federal immunity from suit.’ ” United States v. Mitchell,
Law and precedent establish government liability for the cost of mitigation, where government breach requires expenditures in mitigation. In Mobil Oil Exploration & Producing Se., Inc. v. United States,
The government’s argument that recovery of mitigation costs is precluded by its reinterpreted “no-interest rule” is as inappropriate as it is incorrect, and should be rejected by the court, not adopted and enlarged. As stated in Indian Towing Co. v. United States,
Notes
. System Fuels, Inc. v. United States,
