Syro Steel Co. v. Hubbell Highway Signs, Inc.Syro Steel Co. v. Hubbell Highway Signs, Inc.
Defendants bring forward primarily two assignments of error for this Court to consider on appeal. They argue: (1) Syro is barred from recovering against Propst’s payment bond on the grounds of equitable estoppel, since Syro authorized Propst to pay Hubbell; and (2) the trial court erred in determining that Syro is entitled to recover the full amount of its claim against Propst’s payment bond when a genuine issue of material fact exists as to whether all of the materials for which payment is sought were actually delivered to the project.
Defendants contend that Syro should be barred from recovering against Propst’s payment bond on the grounds of equitable estoppel, since Propst sought and acquired authorization from Syro to pay Hubbell after becoming aware of Syro’s claim against Hubbell. Defendants contend that they relied on the statement of Syro’s credit manager, Mr. E.W. Cantor, that it was “o.k.” for Propst *532 to pay Hubbell, and that if Syro had not given such an authorization, Propst would have retained the funds owed to Hubbell in order to honor Syro’s claims against its payment bond. In this regard, Mr. Cantor’s statement misled and prejudiced Propst by inducing Propst to release funds that it would have used to protect itself from Syro’s claim against the payment bond. Furthermore, defendants argue that by allowing Syro to seek payment under the payment bond, they are in effect required to pay for the same materials twice.
The doctrine of equitable estoppel requires that the party sought to be estopped: “(1) misrepresented or concealed material facts; (2) intended that such misrepresentation or concealment be acted upon by the other party; and (3) had knowledge, actual or constructive, of the true facts.”
Neal v. Craig Brown, Inc.,
The statement by Syro’s credit manager that it was “o.k.” for Propst to pay Hubbell cannot be construed as a misrepresentation. There is no evidence that, in making this statement, Syro intended to relinquish its rights under Propst’s payment bond if Hubbell failed to pay, or that this statement raised an inference of any such intention.
See J.W. Cross Industries, Inc. v. Warner Hardware Company, Inc.,
In addition, the party asserting estoppel must lack knowledge and the means to acquire knowledge as to the real facts in question. This Court has stated that estoppel is not available to protect
*533
a party from the consequences of its own negligence.
Five Oaks Homeowners Association, Inc., v. Efirds Pest Control Co.,
By their second argument, defendants contend that the trial court erred in granting summary judgment and in determining that Syro was entitled to recover the full amount of its claim against Propst’s payment bond when a genuine issue of material fact existed as to whether all of the materials for which payment was sought were actually delivered to the project. The purchase order submitted by Hubbell to Syro called for 500 pieces of guardrail material (at 25 feet per piece) for a total of 12,500 linear feet of guardrail material. It is undisputed by Syro that 6,250 feet of steel beam guardrails were delivered to Hubbell’s Charlottesville warehouse and that an additional 6,250 feet of steel beam guardrails were delivered to the project site. The question, then, is whether Syro is entitled to recover under the payment bond for materials which were neither delivered to the project site nor utilized under the prime contract.
Defendants analogize this case to those involving mechanics’ liens pursuant to Article 2, Chapter 44A of the North Carolina General Statutes, which requires that material be delivered to the project site in order to enforce a lien on a private project.
See Queensboro Steel Corp. v. East Coast Machine & Iron Works, Inc.,
North Carolina law prohibits the attaching of liens, such as mechanics’ liens, on public projects.
American Bridge Division United States Steel Corp. v. Brinkley,
Like its North Carolina counterpart, the Miller Act requires government contractors to furnish a payment bond for the protection of subcontractors and other persons supplying labor and materials for the project.
United States ex rel. Sherman v. Carter,
In light of the similarities between and parallel purposes of the Miller Act and N.C.G.S. § 44A-25 et seq., and the recognition of such by this Court, we find these federal cases to be instructive as to our analysis of N.C.G.S. § 44A-25 et seq. For this reason, we find that neither actual delivery of material to the prime contract job site nor incorporation of the material into the work affects a materialman’s right to recover under the contractor’s payment bond. In order for a materialman who furnishes a subcontractor with materials for use on a public project to recover against a prime contractor’s payment bond pursuant to N.C.G.S. § 44A-25 et seq. it is only necessary that the materialman sold and delivered the materials to the subcontractor in good faith and under the reasonable belief that these materials were for ultimate use under the prime contract.
In the instant case, there is evidence from which the court could find that Syro delivered the material to Hubbell in good faith and under the reasonable belief that the material was intended for use on the project. The purchase order submitted by Hubbell to Syro states:
Note: This material is for use on North Carolina Dept, of Transportation project #.-8.1223348/49; our Job #: VN-808 in Duplin County and must conform to all standards and specifications thereof. Certifications must accompany material shipment.
Delivery address will follow at a later date.
The address for Hubbell is listed as Charlottesville, Virginia. Syro’s invoice to Hubbell for material shipped to Charlottesville recites Duplin County project 8.1223348/49 within its description. Defendants have failed to present any evidence which indicates that Syro should have had reasonable grounds to believe that materials shipped to the Charlottesville warehouse were not intended for the Duplin County project site. Neither the purchase order nor the invoices would put Syro on notice that the materials were intended for use other than on the project such that Syro could not have *536 acted in good faith. We therefore conclude that the trial court did not err in granting summary judgment in favor of Syro for the sum of $37,231.25, which includes materials shipped to Duplin County and to Charlottesville. Additionally, the trial court did not err in denying defendants’ motion for summary judgment. We note, however, that the cross-claim alleged by defendant Propst against Hubbell remains viable.
AFFIRMED.
Judges GREENE and WYNN concur.