Symms-Powers Co. v. Kennedy

146 N.W. 570 | S.D. | 1914

WHITING, J.

The Symms-Powers Company, as party of the first part, and one Kennedy, as party of the second part, entered into a written contract wherein the company contracted to install a heating and plumbing system in an opera house then in course of erection by Kennedy; the contract price for installing both systems being one lump sum. The only provisions of this contract necessary to be noted are: (1) that the consideration for the installation of said plants was to be paid “provided that the party of the first part shall have furnished to' tire party of the second part a good and sufficient surety bond in the 5tt*n. of one thousand dollars guaranteeing to the party of -the second part that said heating plant is installed in accordance with this contract and the specifications thereto attached and will heat the buildings as therein provided, -or, in default thereof in any respect, the party of the first paid will, upon notice thereof and with all reasonable expedition, repair aity defects in the *361installment thereof as shall he necessary to make it comply fully with this contract and specifications.” (2) That, “if, upon full completion o-f the contract, any difference shall arise between the parties hereto as to the installation of the isaid plant complying with the plan's and specifications, such difference shall be referred to a board of arbitrators” — such arbitrators to be chosen in the manner specified in said contract, and their decision upon the matter in dispute to be final upon the said parties.

Under this contract the Symme-B'owers Company installed a heating and plumbing plant. The Plumbing Supply Company ■furnished all or a large part of the material used by the contracting company. The plants having been installed and the contract price remaining unpaid, each of said companies filed a mechanic’s lien against the building and the lot whereon it was situate; the contracting company filing its lien in the full amount of the balance claimed to be due under the contract, the other company filing a lien in the amount claimed to be due it from the contracting company. Kennedy having notified each of said companies to bring an action to enforce its lien or else to satisfy the same of record, each company brought an action to foreclose its lien, in which action Kennedy and the other company were made defendants. It appearing that it was a proper case therefor, the trial court ordered the two actions to be consolidated and the issues tried in J:he action wherein the contracting company was the plaintiff. By a supplemental and amended complaint, the “Supply” company pleaded an error in the amount of its lien as filed and prayed that it be given a lien considerably in excess of the amount of the filed lien. Bindings, conclusions, and judgment were entered in favor of the two companies; by such judgment the contracting company was given a lien for the full amount claimed less $120 deducted for failure to fully comply with its contract, but from the amount of such judgment the supply company was to be paid the full amount claimed by it. Kennedy appealed from such judgment and an order denying him a new trial. We shall first discuss this appeal as though the supply company had not been and were not a party to the action.

Plaintiff, in its complaint, alleged the entering- into a written contract for the installation of the two 'systems and that it had per*362formed the same in full; it pleaded no waiver of any condition thereof. Defendant, answering, after interposing a general denial, admitted entering into the contract, but alleged that the plaintiff did not perform' the contract according to the terms thereof, and he set forth in considerable detail wherein the heating plant failed to. comply with such contract. - Defendant also alleged that plaintiff had failed, prior to bringing the action, to submit matters in difference to arbitrators. Defendant did not specifically plead the failure of plaintiff to furnish the bond hereinbefore mentioned.

Plaintiff introduced in evidence the written contract and proof of the installation of the two plants. It offered no proof that it had furnished the bond, or that it had offered to submit any difference to arbitration. There was no evidence to show that plaintiff was ever advised that defendant refused payment on the ground htat the plants had not - been properly installed. Wien plaintiff rested, defendant moved for a dismissal of plaintiff’s complaint basing such motion upon plaintiff’s- failure to prove the giving of such bond, and: upon its failure to submit matters in dispute to arbitration. The count overruled this motion. Defendant, at the opening of his defense, offered evidence to show that the bond had not been furnished. This was objected to upon the grounds, among others that it was “in no •way referred to in the pleadings,” and that “it appears undisputed in the evidence, up to this stage, that the defendant waived any claim, and accepted the performance of the contract with the knowledge that the bond had not been furnished and that the parties waived any such provision.” The objections were sustained. Defendant immediately asked leave to 'amend his answer so as to correspond with the proof offered. This was refused. Evidence was received that a demand was made for. the bond, and it stands conceded and the court found that no bond was given. At the close of all the evidence, defendant again, asked' leave .to amend his answer to conform to the evidence that had been received, and in connection with such motion presented his proposed amended answer, in which answer he alleged the 'failure of plaintiff to furnish the bond. The court refused the amendment. Defendant then renewed ‘his motion for a dismissal of plaintiff’s complaint for failure to prove compliance' with -the provisions for bond and for *363arbitration. • This motion was denied. While there are numerous errors assigned, the only ones we find it necessary or useful to discuss are those based upon the rulings above referred to.

[i] There being no evidence showing that respondent’s attention had ever been called to the fact that appellant claimed either the heating or plumbing plant to be deficient, the trial court did not err in refusing to dismiss the complaint because of respondent’s failure to submit differences to arbitration. The mere fact that appellant had neglected to pay the contract price for installing these plants gave respondent no notice that any difference had arisen between the parties requiring a submission to arbitration.

[2-6] While the respondent was not, under the statute (section 139, C. C. P.), required to set forth the facts showing performance of the conditions precedent contained in the contract but was authorized to state generally the performance thereof, yet, under the provisions of the same statute, if such allegations were controverted, in became incumbent on, it “to establish, on the trial, the facts .showing such performance.” Appellant’s general denial raised the issue; the mere fact that he saw fit to set up the particulars wherein he claimed the heating plant did not comply with the contract, and to plead specifically the alleged failure of respondent to submit differences to arbitration, did not in any manner admit the performance of the other parts of the contraot or waive proof of same. Respondent urges that appellant is claiming a forfeiture of the contract owing to respondent’s failure to furnish bond, and that such claim of forfeiture is inconsistent with certain counterclaims for damages which formed part of appellant’s answer and which were based upon alleged failures in performance of the contract. There is nothing in respondent’s contention-; appellant does- not, and could not, contend that a failure to give the bond forfeited the contract or respondent’s rights thereunder; respondent has lost none of its rights under the contract, but its right to recover thereunder is, by the terms of the contract itself, postponed until such time as it should give the bond, -or appellant should waive the giving thereof. Neither can respondent, rightfully urge, as it does in its brief, that the- evidence shows a waiver of the giving of the bond. Under its complaint it could not prove nor rely upon a waiver. Anders v. In*364surance Co., 62 Neb. 585, 87 N. W. 331. Furthermore there were no facts proven which would constitute a waiver; that appellant urged respondent to install the plants when he knew the bond had not been furnished, that he used the building' after the plants had been installed, did not amount to an acceptance of such plants and a waiver of defects therein. In fact, appellant’s right to -the bond in no manner depended upon there being defects in either of these plants; if the proof had shown that the contract had been in every respect complied with iso far as the installation of perfect plumbing and heating systems, it would in no’ manner have relieved respondent from its obligation to furnish the bond, or permit of his recovering the contract price untill such bond was furnished. Respondent was bound to prove the performance of the condition precedent, and, having failed so to do, appellant’s motion to dismiss should have been granted1.

[7] But, even if it were not error for the trial court to deny appellant’s motion to dismiss the complaint, and even if it were incumbent upon him to specifically plead respondent’s failure to furnish bond, it was an abuse of the discretion vested in the trial court for it to refuse to permit appellant to amend his answer so as to allege the failure to give the bond.

[8] Inasmuch as our conclusion herein requires a reversal and new trial as between Kennedy and the Symms-Powers Company, we feel justified in referring to another matter that may be presented to the court upon a new trial. The court found that there had been a substantial performance of the contract, and yet found that, it would require an addition of 300 feet of radiation to make the heating plant comply therewith. To us, these two findings appear inconsistent. With the heating plant so1 deficient, we can hardly see wherein the trial court was justified in finding that there had been a substantial compliance with the terms of such contract.

[9] Long after the trial, but before the entering- of findings and conclusions, the respondent offered to furnish the' bond. No bond was executed and presented; but even if there had been, it could not have given respondent a right to recover when it had no such right at the time it instituted the suit.

[to] The supply company urges that, even though the judgment be reversed as to the contracting- company, yet it should be *365sustained as to it; in other words, it contends that its right to enforce its lien in no -manner depends upon whether or rot the contractor had fulfilled its contract. There can be no- question hut that its -right .to recover any sum in excess of the amount claimed in its lien as filed, depended- upon the recovery by the contractor un-.er its lien; therefore, -to the extent that the judgment of the trial court allowed a recovery by the supply company in excess of the amount of its lien -as filed, such judgment must be modified.

3i. Can. a subcontractor recover for material or labor furnished where, under the terms of the contract between the contractor and the property -owner, there is nothing yet due the contractor, but the amount .of the contract price between the property owner and the contractor exceeds the -amount claimed by the material man? That a subcontractor or materialman is entitled to a lien under such circumstances is the established law of this st.de. (Albright v. Smith, 2 S. D. 577, 51 N. W. 590; Id. 3 S. D. 631, 54 N. W. 816), and is in harmony with the great weight of authority. The reasons for such holding are fully set f-o-rth in the two opinions in the above case. The authorities, both federal and state, supporting this holding are collected in Hightower v. Bailey & Kochner, 108, Ky. 198, 56 S. W. 147, 49 L. R. A. 254, 94 Am. St. Rep. 350, wherein special mention is made of the reasoning of this court in its first opinion in Albright v. Smith.

The judgment in so far as it is in favor of Symms-Powers 'Company is reversed, with costs for appellant. The judgment in favor of the Plumbing Supply Company should he modified so that it be limited, to the amount claimed in the lien filed and interest thereon; as so modified, it is affirmed, without costs to either party.

midpage