12 Abb. Pr. 100 | N.Y. Sup. Ct. | 1872
The bridge in question is being constructed by the city of Troy, for public purposes, and within the limits of said city, upon one of the streets thereof) designated upon the map of said city, and no portion of the plaintiff’s land is touched or taken. I am unable to distinguish this case in principle, from Ely v. City of Rochester (26 Barb., 134). There is a striking similarity between the facts of the two cases, and the reasoning of the court in that case applies with force upon the case under consideration.
A distinction is sought to be drawn by the counsel of the plaintiffs upon the ground, that in the case referred to, the bridge had been used as a public highway or thoroughfare for many years. Whereas in frhip case the bridge had been used, previous to its destruction, for railroad purposes only. If the latter fact should be deemed established, although the affidavits upon that question are very conflicting, I do not think the plaintiffs have succeeded in so far distinguishing their case, as to avoid the force and effect of the decision in Ely v. City of Rochester. In the last mentioned case the bridge was erected in 1824, with two abutments, and two stone piers located within the channel of the river, and was so used for a period of about thirty years. The new structure was built of stone with five arches supported by four stone piers in the channel of the river, with a stone abutment at each end of the bridge. The bridge which was destroyed by fire, and which the city of Troy is attempting to replace, was built about twenty years since, pursuant to an act of the legislature, passed June 20, 1851 (Laws of 1851,
In the last case, Gilbert, J., remarks: “The cases establish the principle that the legislature may rightfully authorize the construction of railroads or other works of a public nature, without requiring compensation to be made to persons yrhose property has not actually been tafeen or appropriated for the use thereof, but who may nevertheless suffer indirect or consequential damages by the construction of such works. The case is clearly within the principle stated. What property of the plaintiffs has been taken or appropriated? None whatever. They may suffer an injury by having the easement or servitude with which the estate of their grantor, and the roadway of the defendants are burdened, impaired. But this is an injury which the property of the plaintiffs suffers in consequence
It has been before remarked that no portion of the plaintiffs’ land has been taken or touched by the defendants. And the injury which the plaintiffs appre hend is indirect and consequential. There is no rule by which it can be ascertained or estimated, before the effect of the proposed structure upon the stream is observed, after its completion. Until then all conclusions in this respect must, at best, be only conjectural and uncertain.
We have been referred to a series of decisions bearing upon the rights of riparian owners and defining the nature of such rights. But the rule which obtains in such cases is hot necessarily applicable, where, as in this case, the apprehended injury must be occasioned by an interference with a stream by the construction of a public work by public authority, and where the land of the party complaining is not actually taken. I am satisfied that within the principle settled by adjudged cases that the plaintiffs have failed to establish such an
Reference has been made to the case of George W. Swett against the Mayor, &c., of Troy, in which an injunction was granted and sustained. But in that case there was a direct physical injury to the plaintiffs’ land, as the city undertook to fill up the plaintiffs’ mill pond, and in part upon the land of the plaintiffs, which last mentioned fact creates the distinction in this respect between that case and this. It does not seem to be contended by the plaintiffs that the bridge is not being constructed with skill and in a proper manner to answer the purposes intended, and in this respect it is not objectionable.
The affidavits read upon this motion are numerous and very conflicting in regard to the probable effect which the structure will have, when completed, upon the flow of water from the plaintiffs’ works, and also, in regard to the effect of ice in its passage from the plaintiffs’ dam. Each party has advanced a theory in respect to the probable effect of the work in question, and endeavored to support it by facts and scientific investigations and speculations. In order to authorize the continuance of this injunction the plaintiffs are bound to establish a clear legal right to such injunction, and that they have no other adequate remedy. In Sixth-avenue R. R. Co. v. Kerr (28 How. Pr., 283 ; affg. 45 Barb., 138), Sutherland, J., remarks: “The threatened injury or grievance must be irreparable, or such as cannot be compensated in damages at law, to authorize a court of equity to interfere.” In the same case another member of the court says : “The injunction should be refused till the final hearing, when the subject of compensation can be considered, and if necessary, can then be enjoined, unless payment shall be made” (Thomp
I conclude that the case does not authorize the continuance of the injunction, and the same must therefore be dissolved, with costs of this motion.