Sweeney v. Jackson CountySweeney v. Jackson County
Lead Opinion
The first question presented for consideration is in regard to the motion to quash, for the reason the suit was commenced in the wrong county. It is evident that the suit is embraced within that portion of Section 396, subdivision 3, L. O. L., which enacts that:
“In all other cases, the suit shall be commenced and tried in the county in which the defendants, or either of them, reside, or may be found at the commencement of the suit.”
The defendant bank is an institution of Multnomah County. This question therefore depends upon whether or not the bank, was a necessary or proper party defendant. If it is, then the suit was properly commenced in Multnomah County. Section 393, L. O. L., which prescribes who may be plaintiffs and defendants, provides in part that:
“Any person may be made a defendant who has or claims an interest in the controversy adverse to the plaintiff, or who is a necessary party to a complete*108 determination or settlement of the questions involved therein. ’ ’
The record discloses that both the county and the bank claimed that the estimate of the amount due plaintiff was in fact final and was in the nature of an adjudication fixing the amount due the plaintiff from the county. The bank was the assignee of all of the interest of the plaintiff by virtue of the estimate. The bank insisted that the estimate could not be set aside to its prejudice; and the complaint prayed that notwithstanding the claim of the bank that a decree be entered fixing a new and correct estimate which should be paramount to any rights or claims of the bank under its assignment and that the bank be enjoined from asserting that the estimate was final and binding on the plaintiff. According to the claim made by the bank, it was the owner by virtue of the assignment as collateral security of the whole amount due Sweeney from plaintiff. Therefore, if this is correct, the bank would have had the right to have instituted an independent action upon the claim, and would not have been compelled to wait from April, 1915, until the present litigation is concluded. This interest of the bank in having the $35,573.56 paid to it instead of having the claim assigned to it, declared to be an equitable assignment of only a’ portion of plaintiff’s demand from the county, was wholly adverse to plaintiff’s interest. In order that the bank should not commence such an independent action, and that all questions involved between the plaintiff and the county might be completely settled, it was necessary to make the bank a party to the suit. If the plaintiff had proceeded against the county alone, he would probably have been met at the inception of the litigation by an objection
This court said:
“The orders in favor of the Commercial National Bank, The North Pacific Lumber Co., Kelly, Dunne & Co. and Jacobson operated as an equitable assignment of a part of the fund, and gave to these order claimants a prior right to be paid out of such fund before the general creditors.”
As to an interest acquired by an equitable assignment: See McDaniel v. Maxwell,
“When it appears in a proceeding in equity that the subject matter, or an interest therein, has been assigned, the assignee is a necessary party to the proceeding brought by the assignor, or against him.”
The county bases its claim that the bank was not a necessary party upon decisions involving facts which are dissimilar to those in the present case. In Allen v. Miller,
, “The employment of Houts and Suddath, although for a contingent fee, was wholly independent of each other. H. neither has nor claims to have any rights against S., and vice versa.”
Questions of public policy, which would prevent the county being sued in any other forum than its own, are urged. That by bringing the suit in Multnomah County, the expense of the trial was excessive and burdensome. Section 45, Subd. 4, L. O. L., provides for a change of the place of a trial on motion of either party to the action when it appears:
“That the convenience of witnesses and the parties would be promoted by such change.”
There was no application for a change of the place of the trial of which we are advised, in so far as it appears at this stage of our investigation Multnomah County was a convenient forum for the witnesses and it does not appear that it increased the expenses of the parties.
“He ought to do one thing or the other — either fight it out on the line of his special appearance; or, if he appear and go to trial, accept its incidents and consequences”: Belknap v. Charlton,25 Or. 41 (34 Pac. 758 ); Winter v. Union Packing Co.,51 Or. 97 (93 Pac. 930 ); Jones v. Jones,59 Or. 308 (117 Pac. 414 ).
The county’s demurrer to the complaint, on the ground that the matters alleged are not cognizable in equity, raises the next question. It is the position of counsel for the county that equity has no jurisdiction for the impeaching of an award, unless the contract, by the most explicit terms, makes the engineer selected by the parties the arbiter whose judgment is final, binding and conclusive upon both parties; nor unless fraud in making the award, which was participated in by the county, is alleged and proved; nor unless the error or mistake plainly appears upon the face of the award. That the plaintiff is precluded from obtaining relief by making an assignment to the bank, and thereby accepting benefits of the award.
The provisions of this contract relating to the finality of the award of the state engineer are as follows:
*114 _ “All of said work is to be done under the supervision and direction of the engineer selected by the State Highway Engineer. To be approved by him and accepted by said State Highway Engineer. Said State Highway Engineer shall have the right to fully decide on all questions arising as to the proper performance of said work, and in case of improper construction, or noncompliance with the contract in any manner, to suspend said work at any time, and to order the partial or entire reconstruction of said work, or declare the contract forfeited; and in case of forfeiture, to re-let said contract and to adjust any difference of price, or the damage, if any there be, which said party of the second part shall pay to Jackson County, Oregon, on account thereof, and in all such matters the decision of said State Highway Engineer shall be final. * *
“The State Highway Engineer shall, as soon as practicable after the completion of this contract, make a final estimate of the amount of work done thereunder, and the value of such work, and Jackson County shall, at the expiration of thirty-five (35) days from and after such final estimate is to be made, and is approved by the County Court of Jackson County, pay the entire sum so found to be due hereunder, after deducting therefrom all previous payments and all amounts to retained under the provisions of this contract.”
Upon the trial counsel for the county moved for a decree under Section 411, L. O. L., for the reason that the plaintiff is not entitled to the relief claimed. All of these questions thus raised are so closely allied to the determination on the merits that we pause here to read the record.
“The authorities leave no doubt that construction contracts, in which the contractor stipulates that the engineer or architect of the owner shall finally and conclusively decide, as between him and the owner, what amount of work has been done, and its character, and the amount to be paid therefor under the contract, are legal and should be enforced. In such cases, after the work has been done, the contractor can recover nothing in excess of the amount found due by the engineer, unless he can make it appear that the engineer’s decision was fraudulently made, or was founded on palpable mistake.”
In Lewis v. Chicago, S. F. & C. Ry. Co. (C. C.),
“The estimate may be impeached for fraud; that is to say, it may be shown that the engineers in charge intentionally underestimated or .overestimated the work. It may also be impeached by proof of gross errors in the measurements and calculations. If the evidence shows such errors, it either creates the presumption of fraud, or warrants the conclusion that the engineers did not exercise that degree of care, skill and good faith in the discharge of their duty which the law exacts; and in either event the court will disregard the estimate so far as is necessary to do substantia] justice.”
See, also, Elliott v. Missouri, K. & T. Ry. Co.,
In the case at bar, it is not claimed by plaintiff that there was any intentional fraud on the part of the
Having made this explanation, a general description of the method of procedure must suffice. Plaintiff Sweeney, after executing the contract, proceeded to the scene of the works with a crew of men and his construction outfit. In about three weeks, an engineer appeared. In the meantime the contractor was compelled to use all of his force in clearing the right of way without commencing actual construction. Engineering work for the construction of the road and the profiles for the work were far behind what they should have been at the time of the commencing of
The total yardage not including the work designated as the
Steinman crossing being.......274,173.90 cubic yards
The total number of cubic yards of the excavation as shown by the county engineers was......................257,469.89
The amount of estimate of Kyle and Houston being........ 16,704.01
—in excess of the total yardage allowed by the county engineers.
The trial court set' aside the award made by the highway engineer and adopted the amount of excavation as fixed by the engineers for the county, and adopted the classification of the material excavated as estimated by the plaintiff’s engineers. Taking the Kyle and Houston estimate of the total without disturbing the figures of the other classifications and computing the same as common excavation at the price thereof, 29 cents per cubic yard, makes $4,844.16, which should be allowed plaintiff in addition to the amount allowed by the trial court.
The county employed á skilled engineer to examine the highway and in company with the resident highway engineer devoted two days in checking the classification that had been made by the resident highway engineer. This was about two years after the completion of the work, and at a time when several sec
Labor.........................$5,139.10
Teams ....................... 2,478.38 $ 7,617.48
Ten per cent................... 761.75
Material ...................... 7,074.88
Total ......................... $15,454.11
Allowed on estimate (K. and H.). 9,282.61
Leaving a balance $ 6,171.50
“The contract nnder which they were obligated required that all of the work which they had contracted to perform should be completed by August 15, 1903. Certainly, when appellant company obligated these parties to do and finish the work within a fixed period, if was its duty to afford them a fair and reasonable opportunity to begin and complete the work; or, in other words, under the mutual contract entered into between it and them, it became its duty to furnish the required material, secure the right of way, and have the road grade in readiness, as required by the contract, so that appellees, in the exercise of reasonable diligence, might begin and finish the work within the prescribed period without being subjected to unreasonable cost or expenses on account of the default, delays, and hindrance of appellant. Its default or failure in these respects would subject it to liability for whatever damages appellees might reasonably sustain on that account. * * ” Citing “French v. Cunningham,149 Ind. 632 , 637 (49 N. E. 797 ), and authorities there cited; Louisville etc. R. Co. v. Donnegan,111 Ind. 179 (12 N. E. 153 ); Lewis v. Atlas etc. Co.,61 Mo. 534 ; Minneapolis Mill Co. v. Goodnow,40 Minn. 497 (42 N. W. 356 , 4 L. R. A. 202); Mississippi River Logging Co. v. Robson,69 Fed. 773 (16 C. C. A. 400 ).”
See, also, Salt Lake City v. Smith,
The contract in question in the present case stipulates in regard to extra work as follows:
“The contractor shall do such extra work and furnish such materials as may be required by the State Highway Engineer for the proper completion or construction of the whole work herein contemplated; # * The contractor shall receive for such extra work the actual cost of all materials furnished bylhim as shown*129 by bis paid vouchers. For such labor and teams as are necessary he shall receive the current prices in the locality, which shall have been agreed to in writing by the engineer and by the contractor, plus ten (10) per cent.”
By this stipulation the parties fixed a certain rate of payment for extra work of this character, thus avoiding the question as to “reasonable value.” This construction of the contract by the parties is borne out in making and receiving payment at force account prices for similar extra work as that performed between Stations 563 and 594. The proof sustains the claim made by plaintiff both as to material and labor. The bridge as constructed and the work done between these stations was entirely different from that contemplated by the contract in the first instance. The stipulation made a part of the contract that the state highway engineer during the progress of the work might by giving written notice to the contractor, alter any of the details of the construction in any manner that might be found expedient or suitable without invalidating the contract, relates as the language suggests to details, or proportionally small changes as when necessary to the construction of the contemplated bridge, and not to an entire change of the plan or time for the construction thereof. The stipulation in the contract that:
“The contractor shall receive for such extra work the actual cost of all materials furnished by him as shown by his paid vouchers. For such labor and teams as are necessary he shall receive the current-prices in the locality, which shall have been previously agreed to in writing by the Engineer and by the contractor, plus ten (10) per cent”
—makes applicable the agreement made by the parties
The contractor furnished to the agents of the county statements-, of the force account work claimed by him, substantially as provided for in the contract. Some of these claims were allowed by the county engineers. The plaintiff was not at all times informed as to what items were allowed and what were disallowed, so that when the defendant county demanded of plaintiff a statement of the various items claimed by him, its agents were in possession of the same detailed information or more than plaintiff. Therefore, it was not erroneous for- the trial court to deny an order requiring a further presentation of such items under the circumstances of this case. As the. trial of the case progressed, counsel for the defendant county were furnished with the various lists of estimates and information as to the surveys and engineering work of the plaintiff’s engineers, and were permitted access to the books of account and other records of plaintiff so as to facilitate a fair trial of the cause.
In the construction of the highway, the plaintiff encountered material known as “adobe,” “gumbo,” or “sticky,” which it is claimed on his behalf was not covered by the contract and should be paid for on a basis of a reasonable value, under the rule in Indianapolis Northern Traction Co. v. Brennan,
“The term ‘plowed’ was certainly used in its usual meaning, and must have been so imderstood by the parties. They did not mean or intend thereby the mere £rooting-up’ of the material or cutting a very shallow furrow, or such plowing as would require men to ride upon the whiffletree and upon the plow beam in order to keep the nose of the plow in the material which was attempted to be plowed.”
This language is particularly applicable to the material in question as described by the witnesses. The
As to the correctness of the final estimate as the determination of the quantities and hinds of material to which the unit prices fixed by the contract were applicable, it seems plain that unless Mr. Bowlby, the highway engineer, and Mr. Kittredge, his assistant, had reliable data to determine quantity and classification, the estimate must of course lose the benefit of any presumption in its favor. The contract provides that “all grading shall be done and estimated by the cubic yard.” The obvious purpose of this provision was to insure payment to the contractor for the actual quantities and not for any theoretical quantities excavated by him. The measurements of the county engineers were largely the theoretical contents of the road prism as it was expected the excavation would take place. The lateral lines of the excavation were assumed by the county engineers on the hypothesis that material of a certain character allowing a certain slope line would be encountered when the excavation was made. Of course whenever a different kind of material was encountered, the actual slope line was necessarily either flatter or steeper, and the theoretical contents of the road prism did not represent the actual excavation. The practice of employing offsets in case of line changes adopted by the county engineers resulted as follows: Whenever an offset was employed on a curve, the theoretical contents of the excavation did not correspond with the actual excavation, the line being lengthened or shortened, and the distance between cross-sections thereby affected.
We have carefully read the evidence and examined the case from many angles, which time and space for
With the change in the figures above mentioned, the decree of the lower court is affirmed.
Affirmed. Rehearing Denied,
Rehearing
Denied July 15, 1919.
PETITION FOR REHEARING.
(
Acknowledging our appreciation of the assistance rendered by the briefs of able counsel upon both sides of this suit, we note that it is earnestly urged upon a petition for rehearing that the court erred in affirming the decree of t'he trial court for the \same amount as there decreed by reason of the fact that this court arrived at its conclusion by a different process from that followed by the trial court.
“Much of appellant’s brief is devoted to a discussion of the question whether the findings of fact of the trial court are supported by the evidence. Under our statute, on an appeal from a decree in a suit in equity, the cause is tried de novo upon the transcript and evidence accompanying it, and a final decree rendered here, without reference to the findings or conclusions of the trial court. ’ ’
In Gentry v. Pacific Livestock Co.,
“Under our statute, on an appeal from a decree in a suit in equity, the case is tried de novo, and a final decree entered by the appellate court, without reference to the findings of fact or conclusions of law of the trial court. ’ ’
Whatever our view may be in regard to the evidence in the case as to the amount, we confine the same to the
In the short time of thirteen years that the writer has been engaged on this end of the line of work, a more solid record of material testimony, either of such .volume or of any length, has never been examined. We were pleased to give it our best thought and most careful attention, employing all the time necessary. This we are aware is not indicated by the memorandum opinion. ,
“That if the court shall set aside the award of the highway department, and make a new award, the burden of proving the items upon which'such award must be based, rested upon the plaintiff. * * That no evidence whatever of a substantive nature was ever introduced to substantiate a single item of such account,” referring to “force account.”
This important question was called to the attention of the court at the oral argument of the case, and commented upon by the respective counsel. The length of the record practically precludes a discussion of every point in the case. If we take this one which is so ably and strenuously contended for on behalf of the county, it will illustrate the others to a certain extent.
Referring, first, to some of the issues made in the pleadings relative to the force account work which are illustrative of the remainder, we find in paragraph XVII of the complaint the following:
“That at a certain other point on the line of said highway between Stations 392 and 398, heretofore known and referred to between the parties as the*137 ‘Siskiyou Curve,’ the said State Highway Engineer made certain substantial changes in the location of said highway and certain substantial alterations in the plans thereof, and in making such changes and alterations failed to furnish to the plaintiff proper stakes or elevations or directions for constructing that portion of said highway, and plaintiff was compelled by direction of said State Highway Engineer to keep a large force of men on the ground at great expense waiting for directions as to the manner of doing such work, and by reason of such changes, alterations and delays, plaintiff suffered damages in the sum of $804.
“That at Stations 674+90, 526+90, and 615+20 of said highway, the plaintiff put in place, under the grade of said highway, strictly in accordance with the plans and specifications and und'er the direction of said State Highway Engineer certain unprotected concrete culvert pipe. That the plans providing for the use of such pipe at said three points were defective for the reason that the pipe specified by the said State Highway Engineer for such use was not of sufficient strength to support the grade of the highway constructed thereover, and said pipe at each of said three points was crushed by the weight of the fill placed thereon. That thereupon, and after the said fill was so completed, the said State Highway Engineer directed and required the plaintiff to tunnel through the said highway fill at said three points and construct therein and thereunder at each of said three points a protected concrete culvert. That the work of constructing said three protected concrete culverts was exceedingly expensive on account of the fact that the fill at said points had been completed. That plaintiff was entitled to compensation for constructing said culverts at the prices for force account work so agreed upon between the parties, and at said prices, together with the cost of the material used in such construction, plaintiff is entitled to compensation in the sum of $3,280.”
“That at various other places along the location of said highway, not hereinbefore described, the said State Highway Engineer made numerous substantial changes in the location of said highway and numerous substantial changes in the plans thereof, and in making such changes and alterations failed to furnish to the plaintiff proper stakes or elevations or directions for. constructing said highway at such points, and plaintiff was compelled by directions of said State Highway Engineer to keep a large force of men on the ground at great expense, waiting for directions as to the manner of doing such work. That at all points along the line of said highway the said State Highway Engineer ..caused stakes to be set indicating the elevations of the completed road bed of said highway and said elevations were computed by said Engineer with reference to a large number of bench marks which the said Engineer had caused to be established along the line of said highway, and which bench marks the said Engineer represented to the plaintiff were in agreement one with another. That the said bench marks were in a large number of cases erroneous and not in agreement one with another, and as a result the grade stakes so set for the finished road bed were erroneous and the plaintiff was therefore required and directed by the said Engineer to change the grade of large portions of said highway after they had been completed in accordance with said stakes.
“That the plaintiff was entitled to compensation for performing the work described in this paragraph at the prices so agreed upon between the parties for force account work and at said prices, plaintiff is entitled to compensation in the sum of $15,344.25.”
In paragraph XXI, it is alleged as follows:
l “ * # That in accordance with the terms of said contract plaintiff delivered to the defendant County of Jackson on or before the 15th day of each calendar month bills for all the force account work above de*139 scribed performed during the preceding calendar month.”
Paragraph XVII is answered in paragraph XIII of the answer as follows:
“That as to the allegations of paragraph XVTI of the complaint, this defendant denies that at a certain, or any, point on the line of said highway between Stations 392 and 398, designated in the complaint as Siskiyou Curve, or elsewhere, the State Highway Engineer made certain substantial, or any, changes in the location of said highway, or certain, or any, alterations in the plans thereof or that in the making of such, or any changes or alterations, failed to furnish the plaintiff with proper stakes or elevations or directions for constructing that or any portion of said highway, or that the plaintiff was compelled by direction of said State Highway Engineer to keep a large, or any, force of men on the ground at great, or any, expense, waiting for directions as to the manner of doing the work, or for any reason, or by reason of any such changes, alterations or delays the plaintiff suffered damage in the sum of $804, or any other sum, or otherwise, than as hereinafter alleged.”
With a further answer which reads:
“Further answering the allegations of Paragraph XVTI of the complaint, relating to work at the Siskiyou Curve this defendant alleges that the plaintiff did suffer some loss at said point due to changes in location and which were unavoidable, but within the terms of the contract, and for all extra work performed by him he was allowed force account therefor amounting to $154.38, and in the final estimate hereinafter referred to he was allowed under the head of ‘Extra Work Siskiyou Station’ the further sum of $950, which was allowed to, and did, include all of the claims and demands of plaintiff in said Paragraph XVII and all damages sustained by him by reason of any changes, alterations or delays at said Station- and was intended to and did cover every demand on account of any of*140 the matters alleged in said Paragraph XYII of the complaint.”
Paragraph XIX is answered as follows by Paragraph XY:
“As to the allegations of paragraph XIX of the complaint, the defendant denies that at various other places along the location of said highway, not specifically described in the complaint, or elsewhere, the said State Highway Engineer made various substantial, or auy, changes in the location of said highway or numerous substantial, or any, changes in the plans thereof, except as hereinafter alleged, or that in the making of any changes or alterations, failed to furnish the plaintiff with proper stakes or elevations or directions for constructing said highway at such points, or that plaintiff was compelled by direction of State Highway Engineer to keep a large, or any, force of men on the ground at great, or any, expense waiting for directions ' as to the manner of doing such work or for any other reason; denies that the bench marks mentioned in said paragraph XIX of the complaint were in a large, or any, number of cases erroneous or not in agreement with one another, or that as a result the grade stakes so set for the finished road bed were erroneous, or that they were at all erroneous, and denies that the plaintiff was, therefore, or at all directed by said Engineer to change a large portion of said highway after the same had been completed ifi accordance with said stakes, or otherwise, except' as hereinafter alleged; denies that the plaintiff was or is entitled to compensation for performing the work described in said paragraph at force account prices or at any other prices than those specified in the contract, or that at said prices, or at all, the plaintiff is entitled to compensation in the sum of $15,344.25, or any other suip, or at all, except as hereinafter alleged.”
The allegation as to delivering to the county on or before the fifteenth day of each calendar month, bills
Of course, no one contends but that the burden of proof is upon the plaintiff. The important question is: Has he borne the burden ?
Our notes made when reading the testimony obviate the necessity of again perusing over two thousand pages of typewritten testimony. Referring to them, thence the record, we find at page 148 et seq. of the transcript of testimony that Mr. Sweeney, the plaintiff, when a witness in his own behalf, was interrogated upon cross-examination in regard to having all his books of account at the beginning of the trial. He answered as follows:
“I expect from our records it could be worked up but it would take a long time to do it. You must remember too that I am a little short of money, I don’t want to go out and hire a lot of auditors and so on to do this.”
To the question:
“But when you filed the complaint and made your demand under a certain paragraph of your complaint for fifteen thousand three hundred and forty-four dollars, under paragraph 19 of your complaint, — before you could swear to this complaint, swear to your complaint making up those items you had to know it was correct?”
—he answered:
“The bills had all been furnished; we have a duplicate of those bills.” 1
—meaning, as we understand the record, that the bills for the force account work under the contract stipulating the prices had been furnished to the county.
At page 648 et seq., of the testimony, referring to an item of force account, to the question:
“What was the amount of the work performed at force account in your opinion, or according to your best recollection?”
—he answered: “It was $52.50.”
Whereupon counsel for the county propounded the following:
“Let me ask you, Mr. Sweeney, a question right there. Mr. Sweeney, you wouldn’t be able to testify to that except by looking at this tabulated statement (Plaintiff’s Exhibit 90) that you have in your hand would you, — you don’t know that from your independent recollection?”
To which the witness answered:
“I know about the work being done. I know where the work is, and I know about the work being done, but as to the amount, I wouldn’t know, but I know there was work done there. * *
“ Q. In other words, this testimony that you are giving here is just what you take off of that tabulated statement there that counsel handed you?
“A. A lot of it, — I could tell the circumstances connected with the work, and a lot of it I couldn’t remember the details of it because it is quite a little while ago and there were a lot of changes being made and I couldn’t possibly keep track of all of them over fourteen miles of work. But, in a general way I knew about them and I have specifically talked over those things with the time keeper and the foreman and given them my idea of what their force account work was and that sort of thing.
“Mr. Reames: But as to the amount of the labor on these different jobs, you don’t know that, and you wouldn’t know that unless you read it off of this exhibit that you have there, would you?
*143 “The witness: No, sir.
“ (Further questions by Mr. Kerr.)'
“Q. Have you examined in the last few days, Mr. Sweeney, the copies of the force bills rendered under your direction which are on file in your office covering these items in this Plaintiff’s Exhibit ‘90’?
“A. Yes, sir.
“Q. Do these force hills and this recapitulation of the force hills recall to your mind any recollection of any work having been done on this highway with respect to excavating below water?
“A. "Well, of course, it was called to my attention and I knew it was done at the time it was done, and where it was done about, — well it was at a box culvert down on Dollarhide, — Mr. Dexter was in charge of that work, — it was the first box culvert on the line.
“Q. Well, why did you think it was force account instead of work under the contract?
“A. Well, it was under water and we always figure that work under water is something that is usually paid force account for, — as a matter of fact because it wasn’t in the contract as far as I could see, and it is something special, — and the cost is a little more money than ordinary excavation.”
The testimony proceeds:
“Q. What is the next item on this Plaintiff’s Exhibit ‘90’?
“A. Well, retaining walls in under culverts, that was fixing up around the walls.
“Q. And what culverts?
“A. At this same culvert.
“Q. And why do .you think that was properly chargeable to force account?
“A. Well, from the fact that they had to get some material you know, rock and stuff like that to fix up under the wall.
“Q. You remember that work being done?
“A. Yes, sir.
“Q. What was the next item on this Exhibit ‘90’ in ‘ this segregation?
*144 “A. Well, that is the moving cement at station 507, that is np at the Dollarhide Bridge, — that was something in the nature of a tent and cement being in the roadway and having to be moved.
“Q. Do you remember it being moved?
“A. Yes, sir.
“Q. And what is the next item?
“A. The next item is for retrimming slopes and borrow from slopes.
“Q. What do you remember about that?
“A. Well, I remember we done a lot of retrimming, quite a lot of retrimming of those places, and we borrowed from slopes. I presume that was up there on the Dollarhide Work, there was a borrow from some slopes there.
“Q. Under whose orders was that work done?
“A. Well, under the engineer’s orders.
“Q. And why did you cause it to he billed as force account?
“A. Because that certainly was extra work, it was extra work for us.
“Q. Why was it extra work?
“A. Because you trim a slope down and then after you have gone, you have to come back and retrim it again, — trimming a slope is a little more expensive because it has to be trimmed to make a kind of a nice appearance, and it costs a little money to do that if you have to go and retrim it ag’ain, why you just have to spend that much more extra money.
“Q. Why did you charge borrow from slopes as force account?
“A. Well, I suppose we had to go and borrow to get material, I suppose to make the road bed.
“Q. And if you borrowed would it be necessary to retrim that slope?
“A. Well, that particular slope I don’t believe it was retrimmed up very much to the best of my recollection, it may, they may have ruffed it up a little bit where they made a borrow there, but in most of the places why the slopes was retrimmed.
*145 “Q. Supposing this had been borrowed from a place other than a slope, would it have been force account?
“A. Sir?
“Q. Suppose it had been borrowed from a place other than a slope, would it have been force account?
“A. No, sir.
“Q. Why would it be force account because it was borrowed from a slope?
“A. Well, we had already finished the work there one time and trimmed the slope and then went away and we were ordered to dig into it again.”
Mr. Sweeney testified in a similar manner in relation to the different items of force account work. He certainly claimed to have a good deal of knowledge in regard to the matter. He stated that he was on the work practically all of the time, and was absent on trips to Portland to borrow money for short periods of time. His testimony in regard to the work being done is not contradicted in any way. Indeed as we understand the theory of the defendant during the trial of the cause, it was not that the force account work was not performed by plaintiff, but that he was not entitled to payment therefor at force account prices; that the liquidation should be at the regular contract or unit prices.
Mr. M. 0. Bennett, one of the engineers for the county, in his testimony when a witness in behalf of that defendant, on cross-examination, explained the matter fully as follows:
“Q. Well, these plaintiff’s exhibits that have been put in in connection with your testimony, covering disallowed force bills, some of them contain notations by you, and some of them do not, is that correct?
“A. Yes, sir.
“Q. And those force bills which carry notations by you were force bills which you investigated either per*146 sonally or through reports made to you by your assistants ?
“A. Yes, sir.
“Q. And those force bills concerning which you have testified would bear no notations but were disallowed, — what investigation of those did you make if any?
“A. Well, I would say none, I guess.
“Q. Well, why didn’t you make investigation of those?
“A. In my opinion they were obviously not force account.
“Q. Because of the character of the work?
“A. Yes, sir.
“Q. You were back and forth on the ground often enough to determine that question?
“A. I think so.
“Q. Now, in these force bills which you have disallowed and upon which you have put notations, there was no. question in your mind that the work was done, but the question was, that it was work which fell under the contract, that is the work covered by the disallowed part?
“A. Yes, sir.
“Q. The work was done all right, but it was work that was done under the contract’?
“A. Yes, sir.
“Q. And is that true to the other disallowed bills upon which you made no notation?
“A. Yes, sir.
“Q. That is true as to all of the force bills which the plaintiff introduced as well as those particular ones to which you have testified?
“A. Yes, sir.”
We find there was substantive evidence showing that the force account work was done. We cannot accede to the point so strenuously urged by counsel.
It is alleged that certain claims against the plaintiff for materials and supplies furnished in the fur
With this provision added, we adhere to our former opinion. Affirmed. Rehearing Denied.