787 F. Supp. 542 | D.S.C. | 1992
MEMORANDUM OPINION AND ORDER
This matter is before the Court on Motion Of Plaintiff Sverdrup Corporation For Entry Of Arbitration Award As A Final Judgment And Rule 54(b) Certification Of Judgment As Final Judgment. Defendant WHC Constructors, Inc. (“WHC”), opposes plaintiff's motion arguing that the motion is untimely because it was filed more than one year after entry of the arbitration award.
I
The relevant facts are not in dispute. Plaintiff and WHC are parties to a subcontract agreement (“the Subcontract”) entered into on or about November 4, 1987. The Subcontract provided for WHC to do certain PVC System work on a project for which plaintiff contracted with Sonoco Products Company (“Sonoco”) in Harts-ville, South Carolina. The Subcontract contains the following arbitration clause:
1. All claims that cannot be resolved between the parties shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
The Subcontract also contains a procedure for implementing the arbitration process and other Provisions relating to arbitration which are not relevant to the disposition of this case.
Following WHC’s work on the Sonoco project, leaks developed in the PVC System. Plaintiff contacted WHC, which had already left the job site, about the leaks. WHC agreed with plaintiff that Century III, another contractor on site, could perform the repair work. After Century III had made the repairs, part of the PVC System exploded, causing a failure of the system. Plaintiff called upon WHC and Century III to replace the PVC System; WHC and Century III refused. Pursuant to its contract with Sonoco, plaintiff then replaced the PVC System.
On December 14, 1988, plaintiff instituted this diversity action alleging eight causes of action against defendants: breach of contract, breach of express warranty, breach of implied warranty, indemnity, common law indemnity, negligence, breach of oral contract (against Century III only), and indemnity (against WHC only).
[T]he award rendered by the arbitrators will be final and judgment may be entered upon it in any court having jurisdiction thereof and will not be made subject to modification or appeal except to the extent permitted by Sections 10 and 11 of the Federal Arbitration Act....
On October 4, 1989, the Court, through former Magistrate Judge (now District Judge) Henry M. Herlong, Jr., to whom the case had been assigned, entered a Consent
WHC does not seek to vacate, modify, or otherwise challenge the validity of the Award. Instead, WHC argues that the Award is not enforceable as a final judgment because it is not self-executing as a judgment and plaintiff is now precluded from obtaining judgment on the Award due to its failure to have the Award confirmed within the applicable limitations period. In making this argument, WHC maintains that the appropriate limitations period is set forth in either Section 9 of the FAA, 9 U.S.C. § 9 (one year),
II
An arbitration award is not self executing as a judgment but, instead, must be enforced by a court. Sentry Life Ins. Co. v. Borad, 759 F.2d 695, 698 (9th Cir.1985); Tamari v. Conrad, 552 F.2d 778, 781 (7th Cir.1977). Congress has created a mechanism for enforcement of arbitration awards in Section 9 of the FAA, which provides:
If the parties in their agreement have agreed that a judgment of the court shall be entered upon the award made pursuant to the arbitration, and shall specify the court, then at any time within one year after the award is made, any party to the arbitration may apply to the court so specified for an order confirming the award, and thereupon the court must grant such an award unless the award is vacated, modified, or corrected as prescribed in sections 10 and 11 of this title. If no court is specified in the agreement of the parties, then such application may be made to the United States District Court in and for the district within such award was made.
9 U.S.C. § 9. A confirmation proceeding under Section 9 of the FAA is intended to be summary: generally, confirmation can only be denied if an award has been corrected, vacated, or modified in accordance with the FAA. Taylor v. Nelson, 788 F.2d 220, 225 (4th Cir.1986). The main issue before the Court is whether confirmation under Section 9 may be denied based on a party’s failure to seek confirmation within one year from the date the arbitration award is made. The resolution of this issue depends upon whether the one-year provision of Section 9 is a statute of limitations. For the reasons stated below, the Court finds that the one-year period set
A.
Initially, the Court notes that the case law on this point is scant. The parties have not cited, and the Court has not uncovered, any cases in which the Supreme Court or the Fourth Circuit have held that the one-year provision in Section 9 is or is not a limitations period. Likewise, the Court is not aware of any decisions from either of those two courts in which they have refused to confirm an arbitration award under Section 9 based on a statute of limitations. Plaintiff has cited three cases from other jurisdictions in which courts have recognized that the one-year period in Section 9 is not a limitations period. See Kentucky River Mills v. Jackson, 206 F.2d 111, 120 (6th Cir.), cert. denied, 346 U.S. 887, 74 S.Ct. 144, 98 L.Ed. 392 (1953) (“The language of [Section 9] . is not mandatory, but permissive ... Enforcement of the award in this case is not barred by the one-year limitation contained in Section 9 of the Act, which provides for the summary remedy of confirmation of the award by the court”): Brown v. Bridgeport Rolling Mills Co., 245 F.Supp. 41, 45 n. 7 (D.Conn.1965) (citing Kentucky River Mills, the court stated in dictum “the summary remedy of confirmation of an award provided by Section 9 has been held not barred by the one-year limitation contained therein which is not mandatory, but permissive”); Paul Allison, Inc. v. Minikin Storage of Omaha, Inc., 452 F.Supp. 573, 575 (D.Neb.1978) (citing Kentucky River Mills and Brown, the court stated that “the case law indicates that the ‘one year’ provision of § 9 of the Arbitration Act is not tantamount to a statute of limitations”).
The Court is convinced that the decisions in Kentucky River Mills, Brown, and Paul Allison, Inc. are based on an incorrect interpretation of Section 9. Therefore, the Court declines to follow those cases. The plain language of Section 9 reads “at any time within one year after the award is made, any party to the arbitration may apply to the court so specified for an order confirming the award:...” (emphasis added).
B.
Plaintiff argues, however, that even if the one-year provision is a statute of limitations, the Court should nevertheless enter judgment on the Award because plaintiff may avail itself of enforcement remedies other than the FAA if confirmation is denied. Plaintiff principally relies upon Paul Allison, Inc., in which the court, in finding that the one-year provision is not a limitations period, stated:
Nothing before the Court indicates that the
plaintiff would be precluded from filing a petition to affirm the award in this district tomorrow if the motion to dismiss would be granted today. Since the matter is before the Court on the merits at the present time, it would be impractical and inefficient to require the parties to engage in an additional circuitous procedure to satisfy a jurisdictional technicality-
452 F.Supp. at 575. Plaintiff also relies upon language in the Kentucky River Mills case, in which the court stated that a party may apply for an order confirming an arbitration award, but “is not limited to such remedy.” 206 F.2d at 120.
Ill
As noted, in October 1989, the Court ordered that this litigation be stayed pending entry of an arbitration award or further order of this court. While the parties have completed arbitration on issues relating to Counts I — VII, they have not, as noted, pursued arbitration with respect to Count VIII during the two and one-half year period since the Court stayed this case. Having determined that plaintiff’s motion for entry of the Award as a judgment (i.e., confirmation) should be denied, the Court must now decide what to do with this litigation, which is well over three years old. The Court has carefully considered this matter and finds the following action to be appropriate. First, the Court will lift the stay entered in October 1989. Second, the Court will dismiss with prejudice Counts I-VII since they have been fully arbitrated.
Count VIII, however, presents a different situation. On the one hand, the Court recognizes that there has been no adjudication, either judicial or arbitral, of the merits on that claim. On the other hand, the parties have had more than ample opportunity to institute arbitration procedures pursuant to the Court’s Order staying this litigation. Because the stay is now dissolved, the Court must either call this case to trial for resolution of Count VIII, which would deprive defendant of its right to have this claim arbitrated; issue a further stay so that the parties can again have the opportunity to arbitrate this claim, which would only prolong this litigation; or dismiss Count VIII for failure to prosecute.
The Court has inherent authority to control its own docket and to dismiss a case for failure to prosecute. Link v. Wabash R. Co., 370 U.S. 626, 630, 82 S.Ct. 1386, 1388-89, 8 L.Ed.2d 734 (1962). Before a district court can dismiss a case for failure to prosecute, it must consider the following factors: the plaintiff’s degree of personal responsibility, the amount of prejudice caused the defendant, the presence of a drawn out history of deliberately proceeding in a dilatory fashion, and the effectiveness of sanctions less drastic than dismissal. Doyle v. Murray, 938 F.2d 33, 34 (4th Cir.1991). While it is appropriate for a district court to dismiss an action for the parties’ failure to pursue arbitration, see Morris v. Morgan Stanley & Co., 942 F.2d 648 (9th Cir.1991); Ames v. Standard Oil Co., 108 F.R.D. 299 (D.D.C.1985); the Court is not now prepared to do so because there is insufficient information before the Court to apply the four factors used in this circuit for involuntary dismissals. The Court is also not prepared to institute another stay of these proceedings in order to allow the parties to once again have the opportunity to arbitrate Count VIII. Therefore, the Court intends to set this
IV
IT IS THEREFORE ORDERED that plaintiffs Motion For Entry Of Arbitration Award As A Final Judgment And Rule 54(b) Certification As Final Judgment be DENIED; that the stay entered by the Court on October 4, 1989, be LIFTED; and that Counts I-VII of the complaint be DISMISSED WITH PREJUDICE due to the resolution of arbitration. IT IS FURTHER ORDERED that this case shall be called to trial during the Court’s term of court beginning May 4, 1992, for the resolution of Count VIII only.
AND IT IS SO ORDERED.
. Defendant Century III, Inc. ("Century III”), does not contest plaintiffs motion.
. Counts I-VII involve a dispute over a cooling water system. Count VIII involves a dispute over a temperature control system.
. Although plaintiff designated its motion as one for entry and certification of judgment under Rule 54, the Court shall treat the motion as one for confirmation of the Award under Section 9 of the FAA. See Maidman v. O’Brien, 473 F.Supp. 25, 27 (S.D.N.Y.1979) (treating motion to dismiss as motion to confirm).
. In its brief, WHC actually concedes that the one-year period in Section 9 is not itself a limitations period. WHC argues, however, that because there is no appropriate state limitations period which could be applied, the Court should apply the one-year period established in Section 9. At oral argument, WHC argued that the one-year provision is in fact a limitations period which may be applied without first resorting to state law.
. In Paul Allison, Inc., the district court also held that a party who failed to object to an arbitration award within three months of the award, as set forth in Section 12 of the FAA, was not barred from thereafter objecting when a motion to confirm the award was made. 452 F.Supp. at 575. The Court notes that the Fourth Circuit has held to the contrary on that precise point. See Taylor, 788 F.2d at 225 ("once the three-month period has expired, an attempt to vacate an arbitration award could not be made even in opposition to a later motion to confirm” absent a tolling or due diligence exception).
. The parties did not specify that application for confirmation would be made to this Court. However, the Court reads the one-year provision to be applicable to the present situation where the parties'are making application "to the United States District Court in and for the district within [the Award] was made.” 9 U.S.C. § 9.
.Although not directly on point, the Court is aware of those cases in which courts have confronted the issue of whether the venue provision in Section 9, which uses the term "may” in referring to the court to which application for confirmation can be made, is permissive or mandatory. Compare Island Creek Coal Sales Co. v. City of Gainesville, 729 F.2d 1046, 1050 (6th Cir.1984) (Section 9 venue provision is mandatory): Arthur Imerman Undergarment Corp. v. Local 162, 145 F.Supp. 14, 17 (D.N.J.1956) (same); with Amalgamated Clothing & Textile Workers Union v. Federation of Union Representatives, 664 F.Supp. 995, 996 (S.D.W.Va.1987) (Section 9 venue is permissive); Paul Allison, Inc., 452 F.Supp. at 574) (same).
. The FAA is patterned after the New York Arbitration Act (“NYAA”). Enserch Inti Exploration, Inc. v. Attock Oil Co., 656 F.Supp. 1162, 1165 (N.D.Tex.1987). Under the comparable, but not identical section of the NYAA (N.Y.Civ. Prac.Law 7510), a petition for confirmation which is filed more than one year following the award is subject to dismissal. See, e.g., Teachers Ass’n of the Tarrytowns v. Tarrytown Bd. of Educ., 59 A.D.2d 890, 399 N.Y.S.2d 45 (2d Dept.1977).
. While the plain language of Section 9 is dis-positive, the Court also notes that the general purpose of the FAA is to afford a party the opportunity to secure a speedy resolution of a controversy through the arbitration procedure, In re Mercury Constr. Co., 656 F.2d 933, 938 (4th Cir.1981), aff’d sub nom. Moses H. Cone Memorial Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983); unless that party is guilty of dilatoriness or delay. Radiator Specialty Co. v. Cannon Mills, Inc., 97 F.2d 318, 319 (4th Cir.1938). In this case, plaintiff is clearly guilty of delay in seeking confirmation of the Award.
. The parties recognized this fact in drafting the Agreement, which specifically states that any award made will not be subject to modification or appeal "except to the extent permitted by Sections 10 and 11 of the Federal Arbitration Act_’’
. Although the Order staying this action did not compel arbitration, it is implicit in that Order that the parties were to avail themselves of arbitration on all claims. The failure to arbitrate could also be deemed failure to comply with an order of the Court.
. The Court notes that the parties, in consenting to the stay of these proceedings for arbitration, specifically reserved their right to conduct discovery during the pendency of the stay. The parties have, therefore, had ample opportunity to conduct discovery and this case should be ready for trial.