38 Mass. App. Ct. 764 | Mass. App. Ct. | 1995
Sutton Corporation (Sutton), a construction
and excavation contractor, brought an action in the Superior Court against the Metropolitan District Commission (MDC)
1. The subsidiary findings of the master are binding upon us unless they are “clearly erroneous, mutually inconsistent, unwarranted by the evidence before the master as a matter of law or are otherwise tainted by error of law.” Mass.R.Civ.P. 53(h)(1), as amended, 386 Mass. 1242 (1982). Here, the MDC contests basic facts on appeal without first having filed below specific objections to any findings. Mass.R.Civ.P. 53(h)(2), as amended, 386 Mass. 1242 (1982). When a party makes objections to the findings, as allowed by Mass.R.Civ.P. 53(h)(2), the party must “clearly stat[e] the grounds for each objection and the relief sought.”
The rule further provides that judicial review of a question of law that depends upon the evidence presented to the master requires the filing of “a transcript of so much of the proceedings before the master as is necessary to dispose of the objections adequately.” Mass.R.Civ.P. 53(h)(3), as amended, 386 Mass. 1242 (1982). The filing of the transcript does not, however, eliminate the need to make the original objections clear and specific. As we said in Libman v. Tuckerman, 33 Mass. App. Ct. 341, 343 (1992), “The filing of the transcript permits an appellant to direct a reviewing
The MDC’s general objections were not sufficient, under the rule, to raise a challenge to the master’s subsidiary findings of fact. See Meehan v. North Adams Sav. Bank, 302 Mass. 357, 363 (1939)(decided under earlier rule). Likewise, Sutton’s objections, although containing specific references and requests for relief, only contest the master’s ultimate conclusions regarding the damage award. Since there is no cognizable challenge to the master’s subsidiary findings, we adopt the facts as set forth in his report. “[Ojur function on appeal ... is to determine what disposition of the case is legally required by the master’s findings.” D. Federico Co. v. Commonwealth, 11 Mass. App. Ct. 248, 249 (1981). Glynn v. Gloucester, 21 Mass. App. Ct. 390, 392 (1986). See also Melrose Hous. Authy. v. New Hampshire Ins. Co., 402 Mass. 27, 31 n.4 (1988).
2. We briefly summarize the master’s pertinent factual findings. After commencing the site preparation, Sutton experienced unanticipated soil conditions in connection with the sand drain installation which made completion of the contract according to the preliminary bid virtually impossible. Sutton notified the MDC that it had encountered a changed condition under G. L. c. 30, § 39N, and requested the MDC to approve the use of a substitute construction method not contained in the original contract in order to complete the project. The MDC denied the existence of a changed soil condition and did not respond to Sutton’s request for formal approval of a substitute method. Sutton sought, and the master awarded, added expenses of completing the project according to original contract specifications in the unanticipated soil conditions, including costs for added manpower and materials. The master denied Sutton’s claim for additional damages relating to the removal and replacement of certain materials created by the continued use of the work method specified in the contract.
The master concluded that Sutton experienced a changed condition under G. L. c. 30, § 39N, based on the unantici-
The master concluded that “Sutton’s letter to the MDC . . . that it would be seeking damages . . . combined with the knowledge of the MDC through the personal observation of its representatives on the project of the problems that Sutton encountered during the installation of the sand drains, and the Complaint filed on April 20, 1982, constitute sufficient notice to the MDC of Sutton’s claim.” However, knowledge on the part of the public agency alone is not sufficient to support a finding that the agency waived strict compliance with the damage provisions of a public works contract or that compliance was excused. See Glynn v. Gloucester, 9 Mass. App. Ct. at 462 n.10. The master’s finding that the MDC was aware Sutton was incurring additional expenses from extra work and intended to bring a claim for reimbursement
The master also excused Sutton’s failure to follow the claim procedures by concluding that it would have been futile for Sutton to have provided a detailed statement of costs and expenses because the MDC had already denied that a changed condition existed, citing as authority D. Federico Co. v. New Bedford Redev. Authy., 9 Mass. App. Ct. 141. This conclusion cannot stand. D. Federico Co. v. New Bedford Redev. Authy., supra, is distinguishable because the claim provision of the contract in that case only required the contractor to notify the public agency of the facts surrounding the alleged breach, but specifically provided that the contractor “need not detail the amount of the claim.” Id. at 143 n.l. Additionally, the disputed claim in that case pertained to a line-item amount for protection and maintenance of traffic that the agency refused to pay; there was nothing more that the contractor could do once the agency rejected the request for payment for traffic maintenance. The case further recites that “[a]s requisitions proceeded, that category of work [for maintenance and protection of traffic] stayed in the breakdown of amounts to be paid, an implicit acknowledgement ... of the plaintiffs reservation of right to draw down construction payments on account of it.” Id. at 143 (emphasis added). In contrast, Article XVIII required that Sutton both notify the MDC of its claim and file an itemized statement of damages in order to fulfill its obligations under the contract. There certainly was no similar “implicit acknowledgement” of any reservation of a right to increased payment here.
Sutton was required document its damages even if it would have been “an exercise in futility.” The situation here is analogous to that where a public agency commits what we
Judgment reversed.
Sutton initially brought claims against Vibroflotation Foundation Company, the company that manufactured the sand drains, as well as Geotechnical Engineers, Inc., and Somerville Engineers, Inc., two engineering firms hired by the MDC to consult on subsurface conditions at the work site. United States Fidelity and Guaranty was also a party. All of these parties were dismissed prior to the determination of the case on the merits.
The master’s conclusion that Sutton experienced a changed condition when the system called for by the contract failed to accomplish the project as expected misinterprets G. L. c. 30, § 39N, and is incorrect as matter of law. The statute does not contemplate an equitable adjustment where machinery or a construction method does not measure up to past performance. Rather, its intent is to provide extra compensation where a contractor suffers damages on account of unexpected actual subsurface or latent physical conditions. We do conclude, however, that Sutton experienced a changed condition under § 39N, since the subsidiary findings support the conclusion that the actual soil conditions differed radically from those described in the contract plans. See Glynn v. Gloucester, 9 Mass. App. Ct. 454, 460 (1980).
“If the contractor claims compensation for extra work not ordered as aforesaid, or for any damage sustained, he shall, within one week after the beginning of any such work or of the sustaining of any such damage, make a written statement of the nature of the work performed or damage sustained to the Engineer, and shall on or before the fifteenth day of the month succeeding that in which any such work shall have been done, or any such damage shall have been sustained, file with the engineer an itemized statement of the details and amount of such work or damage. . .
“There is ... a distinction between claims under a contract [equitable adjustments] and damages for a wrongful breach of that contract.” Thomas O’Connor & Co. v. Medford, 16 Mass. App. Ct. 10, 13 (1983).
“Every such act shall provide that an item equal to that named or described in the said specifications may be furnished; and an item shall be considered equal to the item so named or described if (1) it is at least equal in quality, durability, appearance, strength and design, (2) it will perform at least equally the function imposed by the general design for the public work being contracted for or the material being purchased, and (3) it conforms substantially, even with deviations, to the detailed requirements for the item in the said specifications.”