¶ 1. In this case we decide whether a small business whose profits allegedly suffered due to decreased road accessibility during sewer construction may maintain a suit against the contractor for breach of contract and negligence. First, we conclude that the business does not have standing as a third-party beneficiary of the construction contract. The construction contract, like all municipal public works contracts, was made for the benefit of the public as a whole. Therefore, absent contractual language indicating otherwise, an individual member of the public is not entitled to damages for breach. Second, we decide that public policy bars the business's negligence claim. To allow area businesses to recover lost profits from the contractor would open a field of liability with no just or sensible stopping point. We affirm.
¶ 2. The facts are as follows. The Village of Lan-non hired Mainline Sewer and Water, Inc. (Mainline) to install a sewer and water system. Under the terms of the contract, Mainline promised to: "provide vehicular access at all times to the properties affected by this project"; maintain one-way access during working hours and two-way access at all other times except as noted in specific permits; and "supply all necessary signs, flagmen and lights required according to the 'MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES.'" Sussex Tool & Supply, Inc. (Sussex) claims that Mainline failed to maintain access as promised and because of this it lost profits during the construction project.
¶ 3. Seeking to recover its lost profits, Sussex brought this action against Mainline and the Village. As to the Village, Sussex alleged negligence and statu
*408
tory liability for failure to keep the road in repair. As to Mainline, Sussex alleged negligence and breach of contract. The Village cross-claimed against Mainline and its insurer, Transcontinental Insurance Company, for indemnification. All three defendants moved for summary judgment. Transcontinental claimed Sussex's business losses were not covered under its policy with Mainline. The Village denied any liability toward Sussex, reasoning that its acts were discretionary in nature. If Sussex's claim against it survived, the Village argued, the construction contract required indemnification from Mainline and Transcontinental. Mainline contended that Sussex's consequential damages were not of the sort recoverable and, even if they were, Mainline was shielded from liability by the Village's governmental immunity. The trial court granted the Village's motion against Sussex in its entirety, thus mooting the Village's cross-claims against Mainline and Transcontinental. Citing
Sheeley v. Chippewa
County,
*409
¶ 4. We first address Sussex's standing to maintain its breach of contract claim.
2
The general rule is that only a party to a contract may enforce it.
See Schilling v. Employers Mut. Cas. Co.,
¶ 5. In
Schilling,
the court ruled that a student injured in shop class was not a third-party beneficiary under the employment contract between the shop teacher and the school district.
See id.
at 881,
¶ 6. In contrast, the court held that the plaintiff in
State ex rel. Journal / Sentinel, Inc. v.
Pleva,
¶ 7. Sussex could argue that this is a
Pleva
case, likening the road access clause in the sewer contract to the open meetings requirement in the
Pleva
lease. Both arguably evidence "a primary purpose of protecting the
*411
public interests."
Id.
at 616,
¶ 8. What makes Sussex's claim that it is a third-party beneficiary of the construction contract problematic is that the primary purpose of any public works contract is the benefit of the public. This characteristic has led courts and codifiers to fashion a more restrictive test to determine third-party rights in public contracts. See Robert S. Adelson, Third Party Beneficiary and Implied Right of Action Analysis: The Fiction of One Governmental Intent, 94 Yale L.J. 875, 878-79 (1985). The RESTATEMENT recognizes this by specifically addressing third-party beneficiary status under government contracts. See RESTATEMENT (SECOND) OF Contracts § 313 (1981) [hereinafter Restatement], The Restatement provides that:
*412 (2) [A] promisor who contracts with a government or governmental agency to do an act for or render a service to the public is not subject to contractual liability to a member of the public for consequential damages resulting from performance or failure to perform unless
(a) the terms of the promise provide for such liability; or
(b) the promisee is subject to liability to the member of the public for the damages and a direct action against the promisor is consistent with the terms of the contract ....
Id. Comment a explains the rationale behind the rule:
Government contracts often benefit the public, but individual members of the public are treated as incidental beneficiaries unless a different intention is manifested. In case of doubt, a promise to do an act for or render a service to the public does not have the effect of a promise to pay consequential damages to individual members of the public unless the conditions of Subsection (2)(b) are met.
Thus, unless the municipality would be liable to the individual member of the public for nonperformance, the contractor will not be liable. The RESTATEMENT provides an illustration of this principle.
A, a municipality, owes a duty to the public to keep its streets in repair. B, a street railway company, contracts to keep a portion of these streets in repair but fails to do so. C, a member of the public, is injured thereby. He may bring actions against A and B and can recover judgment against each of them.
Id. illus. 5.
*413 ¶ 9. At first blush, this illustration seems to be on all fours with the present case. But a second glance at the illustration, coupled with a review of cases discussing the Restatement rule, reveals three distinguishing factors. First, the construction company in the case sub judice did not contract to undertake an ongoing municipal duty. Second, in cases where the contractor has been held liable, the contract contained language by which the contractor expressly assumed liability. Third, in those cases, the contract language confined third-party beneficiary status to a well-defined and limited group of third parties. A few examples suffice to demonstrate the difference between those cases and the present case.
¶ 10. The reporter's note in the Restatement states that illustration five "was accepted but distinguished" in
Oman Construction Co. v. Tennessee Central Railway,
¶ 11. Where the contractor has expressly promised to repair damage, the court will allow individuals to enforce the promise. For example, in
Plantation Pipe Line Co. v. 3-D Excavators, Inc.,
¶ 12. Contractual language was held to specify a well-defined class of third-party beneficiaries entitled to lost profits in
Just's, Inc. v. Arrington Construction Co.,
*416
¶ 13. The class of intended beneficiaries to which Sussex claims to belong in our case is not so well defined. The Village/Mainline contract states that: Contractor shall provide vehicular access at all times to the properties affected by this project unless otherwise authorized in writing by the Engineer." While this does circumscribe the number of possible third-party beneficiaries, albeit somewhat vaguely, it does not have the specificity required for the court to infer an intent to assume liability for damages.
Cf. Lundt v. Parsons Constr. Co.,
¶ 14. We now address Sussex's tort claim. Sussex alleged that Mainline was negligent, claiming that Mainline "failed to provide sufficient detours, flagmen and signs to direct traffic" while the project was in progress and that this failure resulted in damages to Sussex. 4
*417
¶ 15. To constitute a cause of action for negligence there must exist: (1) a duty on the part of the defendant, (2) the breach of which, (3) causes, (4) damages.
See Coffey v. City of Milwaukee,
*418 (1) The injury is too remote from the negligence; or (2) the injury is too wholly out of proportion to the culpability of the negligent tort-feasor; or (3) in retrospect it appears too highly extraordinary that the negligence should have brought about the harm; or (4) because allowance of recovery would place too unreasonable a burden on the negligent tort-feasor; or (5) because allowance of recovery would be too likely to open the way for fraudulent claims; or (6) allowance of recovery would enter a field that has no sensible or just stopping point.
Coffey,
¶ 16. Even assuming arguendo that Sussex has shown all the elements of a negligence claim, we conclude that public policy considerations bar liability in this case. First, even if Mainline did negligently fail to place detour signs, the potential liability for all area businesses' dips in profit is way out of proportion to the significance of the negligent act. Second, an allowance of recovery would saddle Mainline, and ultimately all municipalities since contractors would pass on the risk of liability to them, with unreasonable economic exposure. Third, such liability "has no sensible or just stopping point."
Coffey,
¶ 17. We agree with the rationale set forth by the
Just's
court when addressing the negligence claim in that case.
See Just's,
This plaintiff is surely not the only person who may have suffered some pecuniary losses as a result of the downtown renovation project. For example, others who may have suffered pecuniary losses could conceivably include not only all the other businesses in the area, but also their suppliers, creditors, and so forth, Ad infinitum. In contrast to the recognized liability for personal injuries and property damage, with its inherent limitations of size, parties and time, liability for all the economic repercussions of a negligent act would be virtually open-ended. If the defendant's liability were extended to all those who suffered any pecuniary loss, its liability could become grossly disproportionate to its fault. Such potential liability would unduly burden any construction in a business area.
Id. (citation omitted). We agree. The sphere of liability in this case is not well defined. The imposition of liability for such nebulous consequences as Sussex's alleged decline in sales is not favored by public policy.
By the Court. — Judgments affirmed.
Notes
Mainline argues on cross-appeal that it is entitled to governmental immunity or, alternatively, that it was acting as a governmental agent but did not receive the notice required by §§ 893.80 and 893.82, Stats. Additionally, Mainline appeals from the trial court's decision that there is no coverage for Sussex's claims under Mainline's policy with Transcontinental. Our decision regarding Sussex's claims against Mainline renders these arguments moot.
See Diamond v. Ruszkiewicz,
Sussex argues in its reply brief that Mainline waived the third-party beneficiary standing issue by failing to raise it before the trial court. However, both standing — which is the basis of our holding on the contract claim — and waiver are rules of judicial policy rather than jurisdictional prerequisites.
See Wisconsin Bankers Ass'n v. Mutual Sav. & Loan Ass'n,
The liability assumption portion of the contract read:
*414 He [the contractor] shall be responsible for all damage or injury to property of any character resulting from any act, omission, neglect or misconduct in the manner or method of executing the work or due to his non-execution of the work or at any time due to defective work or materials .... When and where any direct-or indirect damages or injury is done to public or private property on account of any act, omission, neglect or misconduct in the execution of the work ... he shall restore, at his expense, such property to a condition similar or equal to that existing before such damage or injury was done....
Oman Constr. Co. v. Tennessee Cent. Ry.,
In its response brief, Mainline argues that Sussex's tort claim should be barred by the economic loss doctrine.
See Daanen & Janssen, Inc. v. Cedarapids, Inc.,
