SUNSWICK CORPORATION OF DELAWARE v. UNITED STATES
No. 46696
Court of Claims
Jan. 5, 1948
75 F.Supp. 221
All other demands for inspection having been disposed of on the argument, the motion for the production of “libellant‘s” signed statement by the “respondent” is denied without prejudice to a renewal thereof on the showing of the facts constituting good cause therefor. See Corbett v. Columbia Transp. Co., D. C., 5 F.R.D. 217, 219; Leach v. Greif Bros. Cooperage Corporation, D. C., 2 F.R.D. 444, 445; Thomas French & Sons v. Carleton Venetian Blind Co., D. C., 30 F.Supp. 903, 905; 2 Moore‘s Federal Practice, 1946 Supp. p. 241. Compare Price v. Levitt, D. C., 29 F.Supp. 164 and Bough v. Lee, D. C., 28 F.Supp. 673, both of which involved
The attention of counsel is called to the fact that although his pleading states that the libellant elects to maintain the action under the Jones Act,
Richard H. Tunstead, of New York City (Spencer & Iserman, of New York City, on the brief), for plaintiff.
S. R. Gamer and John F. Sonnett Asst. Atty. Gen., for defendant.
Before JONES, Chief Justice, and LITTLETON, HOWELL, MADDEN and WHITAKER, Judges.
LITTLETON, Judge.
Plaintiff sues to recover $11,492.93, plus overhead and profit, for increased labor costs incurred in the performance of a lump sum construction contract entered into with defendant September 21, 1944, cover
The contract specifications, prepared by defendant and upon which plaintiff relied in the preparation of its bid, fixed the minimum wage to be paid journeymen carpenters on this project at $1.25 per hour, and provided that the wage specified “shall be the maximum wages to be paid, subject, however, to
Article 17 of the contract entered into by plaintiff and defendant, following the acceptance of plaintiff‘s bid, directed the contractor to pay all labor employed directly upon the site of the work at wage rates “not less or more than those stated in the specifications (subject to
Plaintiff commenced the contract work immediately upon the execution of the contract and during the first two weeks experienced no difficulty in obtaining a sufficient number of carpenters through the local union at $1.25 per hour. However,
Plaintiff disagreed with the union‘s contention, in view of the fact that its carpenters were not working under conditions similar to those pertaining where certain other contractors on earlier occasions had agreed to the higher rate for so-called waterfront construction work, and refused throughout to agree to or to adopt a rate of pay at variance with the wage rate provisions of the specifications. The U. S. Conciliation Service of the Department of Labor having failed to negotiate a settlement of the controversy, the dispute was referred by the Secretary of Labor to the National War Labor Board under the written stipulation of plaintiff and the union agreeing thereto, and the dispute was referred by said Board in turn to the Wage Adjustment Board in the Department of Labor to which it had delegated authority for determining such disputes. After a hearing attended by representatives of plaintiff and the local union, and by the defendant‘s project manager representing the contracting officer, before a Hearing Officer, and a report by the latter to the Wage Adjustment Board, favorable to the union‘s contention, the Wage Adjustment Board adopted the Hearing Officer‘s recommendations over plaintiff‘s objections thereto and on January 10, 1945, issued a directive order to plaintiff (finding 13) directing it to pay all carpenters employed on the project on waterfront work, as defined in said order, a wage rate of $1.42 1/2 per hour, retroactive to the beginning of the project.
Plaintiff rightly regarded the order to be obligatory upon it, notwithstanding it had consistently opposed the union‘s demand from beginning to end and had submitted to the Board in writing its objections to the Hearing Officer‘s recommendations. Nevertheless plaintiff, on January 22, 1945, sought the contracting officer‘s formal advice on this point (finding 14), and requested confirmation from the contracting officer that plaintiff would be compensated for the extra payments ordered to be made to carpenters on the project. The contracting officer‘s reply of February 27, 1945, was entirely noncommittal as regards the question of whether plaintiff was obligated to comply with the order of the Wage Adjustment Board. There was no suggestion that the order to pay the increased wages was not obligatory upon plaintiff. The contracting officer rejected any adjustment in the contract price to cover such increased costs, but the letter of rejection was not responsive to the issues raised by plaintiff‘s letter and in our view did not amount to a decision on those issues by the contracting officer adverse to plaintiff‘s claim. Coming from the representative of the defendant to whom the contract granted power to make equitable adjustments in the amount payable to the contractor in the event changes should be made by the Government in the specifications, it evidenced little more than indifference to the problem confronting the contractor. The contracting officer said:
Your inquiry was referred by this office to the Office, Chief of Engineers, and that office has advised that the action of the Wage Adjustment Board is no basis for an adjustment in the price of subject contract.
This office regrets that it, therefore, has no choice but to advise you that no adjustment can be made to compensate you for the increased wage rates of carpenters on the job.
The increased wage rate which plaintiff proceeded to pay its carpenters in com
The question, whether the contract entered into by plaintiff with defendant acting through the War Department could properly be interpreted as obligating defendant to reimburse plaintiff for the increased labor costs which the Board of Contract Appeals concluded the Wage Adjustment Board of the Department of Labor had caused plaintiff to pay, was left unanswered.
We are not certain that the War Department Board had clearly in mind the true issue in the case. We do not doubt, however, the soundness of the Board‘s conclusion that the determination of plaintiff‘s claim was essentially a matter for judicial determination.
The issue to be decided is whether or not the Government, in its capacity as a contracting party, has imposed upon the plaintiff a burden of performance which it was not intended by the contract should be borne by plaintiff without an adjustment of the contract price.
In a number of instances we have discussed the principle that it is an implied condition of every contract that neither party will hinder the other in his discharge of the obligations imposed upon him, nor increase his cost of performance. LeVeque et al. v. United States, 96 Ct.Cl. 250; Beuttas v. United States, 101 Ct.Cl. 748, rev‘d 324 U.S. 768, 65 S.Ct. 1000, 89 L.Ed. 566; York Engineering Co. v. United States, 62 F.Supp. 546, 103 Ct.Cl. 613, certiorari denied, 327 U.S. 784, 66 S.Ct. 700, 90 L.Ed. 1011; Clemmer Construction Co. v. United States, 71 F.Supp. 917, 108 Ct.Cl. 718; Paretta Contracting Co. v. United States, No. 46395, 109 Ct.Cl. 324, decided October 6, 1947.
Applicability of this principle in a given case depends upon not only the nature of the act which is alleged to have increased the burden of performance but as well upon the intention of the parties, with respect to such act, either expressed or implied in the contract. If the Government, having let a contract which fixed the minimum wages to be paid by the contractor on a certain project, thereafter sets a higher minimum wage level on a separate project at the same site, the court may conclude that in view of the respective undertakings of the parties, as disclosed in their contract, the Government by such conduct cannot be said to have “knowingly hindered” the contractor in his performance, or “culpably increased” his costs, notwithstanding there ultimately results from the Government‘s conduct a condition wherein the contractor finds it necessary to increase wages in order to insure the timely completion of his work. This conclusion was reached in United States v. Beuttas, 324 U.S. 768, 65 S.Ct. 1000, 89 L.Ed. 566, and by this court in LeVeque et al. v. United States, supra, where, in each instance, the contractor by the express terms of his contract undertook to pay not less than the wage rate prescribed in the specifications, and where the Government, having specifically provided for an adjustment of the contract price in the event the minimum wage rate prescribed should be changed by a certain designated Government official, expressly stipulated that “the Government will not consider any claims for additional compensation made by the contractor because of payment by the contractor of any wage rate in excess of the applicable rate” contained in the specifications, and that “all disputes in regard to the payment of wages in excess of those specified herein shall be adjusted by the contractor.” In such cases it is obvious that the Government‘s act does not directly compel the
In York Engineering Co. v. United States, supra, it appeared that no direct action by the Government compelled the contractor to pay increased wages, the court, nevertheless, concluded on the facts that the contractor was entitled to recover its increased labor costs which resulted from the Government‘s action in raising WPA wages for common labor from 35 cents to 50 cents, a figure in excess of the minimum rate provided for such labor in the plaintiff‘s contract. The contractor was required by the contract to look to the United States Employment Service for the bulk of its workmen, with a preference in employment given to persons from the public relief rolls. It was found that the WPA wage increase from a rate 10 cents lower than the 45-cent rate the contractor had been paying to a rate 5 cents higher than such rate made it difficult or impossible for the latter to secure labor at its old rate. Notwithstanding the contractor‘s undertaking was merely to pay not less than the minimum rate the court concluded that the increased cost of performance should be borne by the Government in view of the fact that the contract itself provided that the minimum rate established in the contract should be subject to change by the contracting officer, and that the contract price should be adjusted to compensate for any change he made. These provisions evidenced an intention in the contract to limit the risk which a contractor who agreed to pay “not less than” the specified minimum would otherwise be deemed to have undertaken with respect to increased wages. Though not within the exact letter of the provision excluding from the contractor‘s undertaking the burden of increased rates ordered by the contracting officer the WPA wage increase fell within its intended scope, since it added a burden of performance of a type the contractor was not intended to have to bear without an adjustment of the contract price. The fact that the increase was effected by action of the WPA rather than by the contracting officer was considered to be of minor importance.
In Paretta Contracting Co., Inc., v. United States, supra, we held that the plaintiff was entitled to recover its increased labor costs where defendant‘s representative in charge of the work wrongfully induced the contractor to increase the wages of its laborers from the 65 cents per hour rate, fixed by the contract as the minimum wage, to the 80 cents per hour rate contained in a Wage Adjustment Board ruling issued during the performance of said contract purporting to cover all Federal Public Housing Authority projects in the area where the contractor‘s work was proceeding. In that case defendant‘s representative advised the contractor that failure to pay the adjusted wage rate was a noncompliance with the terms of the plaintiff‘s contract, and that unless supplemental pay roll records should be submitted showing payment of the increased rate the noncompliance would be reported as such to the United States Department of Labor. We expressed the opinion that the project engineer‘s statement to the contractor, that its failure to pay the 80 cents was a noncompliance with its contract, was erroneous; that the contract there considered required no more than that plaintiff pay a minimum of 65 cents an hour (there was no provision that the wages be computed at rates not less or more than those stated in the specifications subject to
Defendant‘s position is (1) that the action of the Wage Adjustment Board furnishes no basis for recovery against defendant because the directive order of said Board did not in fact cause plaintiff to pay the increased wages, and even if such order should be deemed to have been the compelling cause of the increase in plaintiff‘s cost of performance, the effect of the wage order cannot be attributed to the Government in its capacity as a contracting party, since the order issued as an act of the sovereign; (2) that no undertaking by defendant either express or implied is to be found in the contract for reimbursement of increased costs which plaintiff may incur as a result of giving full effect to the wage provisions of the contract, including the provision with reference to
When, shortly after the work began, the carpenters’ union at the site of plaintiff‘s project demanded a higher wage rate than that set forth in the specifications, and plaintiff refused to pay it, work on the project was not suspended but recourse was had by the parties to the dispute to the machinery provided by Federal law for the peaceful settlement of such disputes involving Government contracts. Throughout the proceedings which followed plaintiff continued to oppose the union‘s demand for a higher rate, and at no time suggested that authority to pay a higher rate was necessary in order for it to retain the services of its carpenters on the job. Instead of seeking authority to pay a rate higher than that fixed in the contract, it consistently maintained the position that no change in rate was warranted. Mention is made in the Government‘s brief that plaintiff did not at any time invoke the procedure specified in paragraph 1-21(b) of the specifications (finding 4), looking toward a reclassification or an additional classification by the Secretary of Labor for the carpenters who were claiming to be doing “waterfront work.” It would have been strange had plaintiff submitted such a request, since it contended from the beginning that no “waterfront work” was involved in the job and that the contract had fixed the wage rate for all carpenters.
Defendant contends that the Wage Adjustment Board‘s order, adverse to plaintiff‘s position, came about simply because the parties agreed between themselves to allow the Board to serve as an arbitrator of the dispute and voluntarily enlisted its services. This position ignores the fact previously noted, that both the positive direction in Article 17 of the contract, that the contractor should pay his workmen at wage rates “not less or more than those stated in the specifications,” and the declaration in section 1-21(b) of the specifications, that “The wages specified in the schedule shall be the maximum wages to be paid,” were “subject, however, to
It is apparent, therefore, that when the dispute arose over the carpenter union‘s demand for $1.42 1/2 per hour, and plaintiff joined in the submission of the dispute with the knowledge and consent of defendant, to the Conciliation Commission and later to the Wage Adjustment Board, plaintiff did no more than adhere to the letter and spirit of the contract to which it and defendant were parties. It was only after the Wage Adjustment Board issued its directive order of January 10, 1945, defining substantially all of the carpentry work on plaintiff‘s project as waterfront work, and directing that all carpenters employed by plaintiff on such work be paid at a rate higher than that stated in the specifications, that plaintiff paid the $1.42 1/2 per hour demanded by the union.
In view of the fact that the contract itself, upon giving effect to the clause with reference to
At this point the defendant makes the argument that the contract under which plaintiff‘s claim arises was entered into by the Government in its capacity as a con
We think this principle is inapplicable to the facts of this case. It may be granted, as defendant contends, that the Government in its sovereign capacity and acting for the public good set up a general program to control inflationary tendencies and minimize work interruptions which might interfere with the effective prosecution of the war, and that
The underlying basis for the doctrine of nonliability of the Government for its general and public acts as a sovereign is well expressed in Jones v. United States, supra, where the court said: In this court the United States appear simply as contractors; and they are to be held liable only within the same limits that any other defendant would be in any other court. Though their sovereign acts performed for the general good may work injury to some private contractors, such parties gain nothing by having the United States as their defendants.
We know of no reason why the Government may not by the terms of its contract bind itself for the consequences of some act on its behalf which, but for the contract, would be nonactionable as an act of the sovereign. As shown in Bostwick v. United States, 94 U.S. 53, 69, 24 L.Ed. 65, the liability of the Government in such circumstances rests upon the contract and not upon the act of the Government in its sovereign capacity. It was there held that while the Government was not answerable for that portion of the destruction of trees and fences and the removal of stone and gravel from the plaintiff‘s property which occurred during the wartime occupancy of said property by Federal troops prior to a lease of the premises to the Government, it was answerable in the Court of Claims for that destruction and loss which the troops occasioned during the Government‘s occupancy of the premises under lease, as voluntary waste within the prohibition of the implied agreement in such lease. The court stated, 94 U.S. at page 69, 24 L.Ed. 65: If there had been in this lease an express agreement to repair, certainly it could not
It appears in the finding that during the occupancy under the lease ornamental trees were destroyed; fences and walls torn down, and the materials used for sidewalks and the erection of other buildings, or carried away; and that stone was quarried and gravel dug from a stone-quarry and gravel-pit on the premises, and taken away. This was voluntary waste, and within the prohibition of the implied agreement in the lease. For this the Court of Claims can award compensation in this action.
We may concede, for the purpose of this case, that if the War Labor Board, or the Wage Adjustment Board as its agent, had had under consideration and had decided pursuant to
Having concluded that the cause of the increased wages is attributable to defendant as a contracting party, it remains to determine whether under the provisions of the contract this burden should be borne by plaintiff or defendant. Defendant‘s contention on this point is that the contract provides no basis for requiring defendant to reimburse plaintiff for such increased cost of performance; that plaintiff was not justified in figuring its bid on the basis that no increase in the specified wage scale would be made without an adjustment in the amount payable to it, particularly where, as here, the contract discloses the possibility of wage increases and makes no express provision for reimbursement of the contractor in such event. In such circumstances, defendant says, it was incumbent upon the contractor when making its bid to provide for the contingency that a wage increase might be ordered pursuant to the provisions of
It was not usual to find in Government contracts containing such provisions prior to the Stabilization Act of 1942, 56 Stat. 765,
The Stabilization Act of 1942 and
The contractor and the Government as contracting parties were no longer in a position to evidence, by means of such provisions as those to which we have referred above, their intent respecting the burden of wages paid in excess of the rate specified in the schedule.
In these circumstances we find the printed form of Government contract and the Government specifications, upon which plaintiff made its bid, expressly stating that the wages specified in the schedule shall be the maximum wages to be paid, subject to
In view of our conclusions hereinbefore stated, we are of the opinion that the contracting officer not only had the authority but it was his duty under Article 3 of the contract, as plaintiff requested in writing, to carry out the decision made by the Wage Adjustment Board and compensate plaintiff for the extra wages paid by a change order and an equitable adjustment. He declined to do this and plaintiff is entitled to recover.
Plaintiff claims increased wages, insurance and taxes in the amount of $11,492.93, but as stated in findings 16 and 17, the amount payable under the decision and order of the Wage Adjustment Board was $11,222.91. Plaintiff also claims 15 percent for overhead and supervision amounting to $1,723.94 and 10 percent for profit amounting to $1,321.69, but the proof is not sufficient to justify the allowance of either of those items. No extra work or extra employees were required and when plaintiff has been reimbursed for the extra wages paid it will be fully compensated and will be in the same position in which it would have been had the decision and the order referred to not been made and issued.
Judgment will be entered in favor of plaintiff for $11,222.91. It is so ordered.
JONES, Chief Justice, and HOWELL and MADDEN, Judges, concur.
WHITAKER, Judge (concurring).
The specifications in this case stated that $1.25 was the prevailing rate for carpenters. The Wage Adjustment Board found that the prevailing rate for carpenters doing “water front work” was $1.42 1/2, and not $1.25, and that most of the carpenters on plaintiff‘s job were doing “water front work.” As a result plaintiff was required to pay this higher rate.
There was, therefore, a misrepresentation in the specifications as to the prevailing rate for the carpenters on plaintiff‘s job. Since plaintiff was compelled to pay the higher rate, I think it is entitled to recover for the misrepresentation, inasmuch as its bid had been made upon the basis of the $1.25 rate. This is so, I think, independent of whether or not the action of the Wage Adjustment Board was a sovereign act.
For this reason I concur.
I am authorized to say that Judge MADDEN agrees with this opinion.
