Lead Opinion
OPINION
¶ 1 Sunridge Development Corporation (SDC) and Sunridge Enterprises, LLC (SEL) appeal from the trial court’s grant of summary judgment in favor of RB & G Engineering, Inc. (RB & G) on claims of negligence and breach of contract. However,
BACKGROUND
¶ 2 In 1993, SDC contracted with RB & G to perform a geologic study of 10.2 acres that would become the Alpine Brook Development (the Property). The purpose of the 1993 study was to analyze potential faults and other geologic features of the Property that could affect SDC’s ability to develop the Property. In 1995, SDC contracted with RB & G to perform a geotechnical investigation of the Property, whereby RB & G was to determine whether geological hazards existed on the Property and recommend foundation designs for SDC’s development plan. In the 1995 report, RB & G concluded that the small faults on the Property were expected for the area and did not present problems for development. Based on these two RB & G reports, SDC proceeded with its plan to develop eighty-six units on the Property.
¶ 3 In 1996, SDC principal Stephen Stewart formed SEL for liability purposes, and SDC conveyed the Property to SEL. The conveyance included the assignment to SEL of all of SDC’s rights and claims in relation to the various engineering reports, surveys, studies, and zoning approvals.
¶4 SDC and SEL both filed suit against RB & G, alleging negligence and breach of contract. In August and September of 2005, the trial court ruled in favor of RB & G on two separate motions for summary judgment. The first motion was primarily against SEL, arguing alternative rationales for prohibiting SEL from claiming damages against RB & G: the economic loss rule, see generally SME Indus., Inc. v. Thompson, Ventulett, Stainback & Assocs., Inc.,
¶ 5 The only evidence SDC presented in response to the second motion for summary judgement came in the form of sworn affidavits. The trial court denied the admission of SDC’s affidavits because they were offered after the August 1, 2006 deadline for parties to file dispositive motions. “Given this case history,” the trial court wrote, “the August 1, 2006 deadline presupposes an end of the discovery process.” In granting the motion, the trial court specifically found: “[SDC] has failed to marshal admissible evidence as to its claim for damages. A simple statement that one has been damaged is not evidence; it is a legal conclusion.”
¶ 6 On December 18, 2006, the parties then stipulated to the dismissal with prejudice of SDC’s claims against RB & G for breach of contract; Plaintiffs also agreed not to appeal the trial court’s second summary judgment ruling. On January 5, 2007, the' trial court entered the final judgment and order thereon. Plaintiffs now challenge the trial court’s
ISSUE AND STANDARDS OF REVIEW
¶ 7 Plaintiffs challenge the trial court’s grant of summary judgment on SEL’s breach of contract and negligence claims in favor of RB & G.
ANALYSIS
¶8 SEL argues that it should be allowed to pursue its breach of contract claim against RB & G beyond the summary judgment stage because the assignment of the contracts in question allows SEL, as the assignee, to assert the claims against RB & G that SDC would have been able to assert had the assignment never taken place. Under the law of assignments, “[assignees] are entitled to bring against the [obligor] any contractual action the [assignor] could have brought.” Spears v. Warr,
¶ 9 Here, at the time of assignment, RB & G had already completed its geological surveys under its contracts with SDC. In response to the second motion for summary judgment, SDC attempted to submit affidavits into evidence regarding damages. But the trial court refused to admit the affidavits, ruling that they were not timely, and this ruling was included in the second summary judgment. Thereafter, Plaintiffs stipulated not to appeal this second summary judgment ruling. The parties entered into this stipulation on December 18, 2006, and the trial court entered the final judgment and order on January 5, 2007. Plaintiffs had thirty days to appeal the final judgment and order. See Utah R.App. P. 4(a). However, per the stipulation, they did not do so. Since assignment merely allows the assignee to stand in the shoes of the assignor, SEL is precluded from claiming damages against RB & G — an essential element of any claim, see Campbell,
¶ 10 Plaintiffs argue that at the time of assignment, damages were not yet ripe because the errors in RB & G’s geological surveys were not discovered until years later. Nevertheless, even after the errors were discovered, SEL never pursued a damages claim against SDC for conveying SEL a property allegedly worth over a million dollars less than SEL paid. SEL cannot be “permitted to enjoy the benefits of [its] separate corporate structure for some purposes while also claiming [that the trial court] elevate[d] form over substance in an attempt to [attach SEL’s damages against SDC to RB & G].” Sachs v. Lesser,
CONCLUSION
¶ 11 SDC’s assignment to SEL of all rights and claims relating to the contracts for the survey work of RB & G put SEL in the same position as SDC-without admissible evidence of damages against RB & G. Because Plaintiffs agreed not to appeal the trial court’s granting of the second motion for summary judgment, both SDC and SEL are precluded from claiming any damages against RB & G, whether sounding in contract or torts. We therefore affirm the decision of the trial court.
¶ 12 I CONCUR: PAMELA T. GREENWOOD, Presiding Judge.
Notes
. For purposes of summary judgment, the parties centered their arguments on the effect of the assignment and not on the underlying validity thereof.' At trial, however, SEL would have the burden of proving the validity of the assignment by a preponderance of the evidence.
. We do not address Plaintiffs' arguments relating to the trial court's application of the economic loss rule and its rejection of the adoption of the independent duty concept for engineers because our decision — based on RB & G's motion
. Per stipulation, Plaintiffs do not challenge the trial court's grant of summary judgment on SDC's breach of contract claim, nor the refusal of the trial court to admit the affidavits into evidence. We therefore do not address these issues. See State v. Jennings,
. While it is true that "it only takes one sworn statement under oath to dispute the averments on the other side of the controversy and create an issue of fact,” thereby precluding summary judgment, Holbrook Co. v. Adams, 542 P.2d 191, 193 (Utah 1975), if such evidence is untimely it may still properly be excluded, even if the result leads to a grant of summary judgment against the party seeking its introduction. Cf. Gerbich v. Numed Inc.,
Dissenting Opinion
(dissenting):
¶ 13 Procedurally, SEL’s claims were dismissed entirely in September 2005 when the trial court ruled that there was a lack of privity and applied the economic loss rule, thereby foreclosing SEL’s breach of contract and negligence claims respectively. In October 2006, the trial court dismissed SDC’s breach of contract claim for failing to timely produce evidence of damages. Finally, in December 2006, a stipulation was entered into by which SDC, as the only remaining “Plaintiff,” agreed to settle the lone outstanding claim against RB & G and waive its right to appeal the October 2006 summary judgment order. The issues before us on appeal are focused on the summary judgment entered against SEL in September of 2005.
¶ 14 The majority fails to analyze the central issue presented: whether SEL was in privity with RB & G for purposes of asserting a breach of contract claim. The trial court dismissed SEL’s case at the summary judgment stage for a lack of privity. Yet, my colleagues do not even attempt to address whether this determination was in error. Instead, they skip ahead and use the trial court’s later dismissal of SDC’s breach of contract claim, on procedural grounds, as retroactive justification for thwarting SEL’s appeal.
¶ 15 Privity is a paramount consideration in this case. If the trial court was wrong about SEL’s privity with RB & G, which I believe it was, then SDC’s claim should have never gone forward as it did. SEL, as the assignee, is the proper party to litigate the breach of contract claim. The effect of the majority’s opinion is to require an assignee like SEL to rely upon its assignor to litigate the issue of damages against the obligor. This line of reasoning is contrary to the rule that assignees stand in the shoes of their assignors. See 6 Am.Jur.2d Assignments
¶ 16 In affirming, the majority also ignores evidence in the record that should have moved SEL’s claim past summary judgment. In April 2005, more than a year before the trial court’s deadline for submitting evidence of damages, SDC principal Stephen Stewart filed a sworn affidavit with the trial court. The affidavit outlined, in specific dollar amounts, SDC’s. damages resulting from the failure of RB & G to detect the pertinent faults on the Property. This “one sworn statement” is sufficient to create a genuine issue of material fact. Holbrook Co. v. Adams,
¶ 17 Finally, the majority has not addressed SEL’s alternative argument on appeal, namely that the economic loss rule should not bar its claim of negligence. Without explanation, my colleagues conclude that their decision is dispositive and they need not consider SEL’s alternative arguments on appeal. But because they hold that SEL has no contractual claim to pursue, my colleagues must deal with SEL’s alternative argument for negligence.
¶ 18 For the foregoing reasons, I respectfully dissent. In my view, SEL should be allowed to pursue its breach of contract claim against RB & G and prove damages in accordance with the law of assignments. I would therefore reverse the summary judgment and remand for further proceedings on SEL’s claim for breach of contract.
