SUNRAY MID-CONTINENT OIL CO. v. FEDERAL POWER COMMISSION
No. 335
Supreme Court of the United States
Argued April 26-27, 1960. - Decided June 27, 1960.
364 U.S. 137
Howard E. Wahrenbrock argued the cause for respondent. With him on the brief were Solicitor General Rankin, Assistant Attorney General Doub, Alan S. Rosenthal, Willard W. Gatchell, Robert L. Russell and Peter H. Schiff.
MR. JUSTICE BRENNAN delivered the opinion of the Court.
This case presents an important question under the
Petitioner, Sunray Mid-Continent Oil Company, an independent producer of natural gas, entered into a contract with United Gas Pipeline Company, an interstate transmission company. The contract covered considerable acreage owned by, or under mineral lease to, petitioner in Vermilion and Lafayette Parishes, Louisiana, in and about what is called the Ridge field. Under it, United agreed to take an annual amount of gas from petitioner equivalent to 4.5625 per cent of petitioner‘s gas reserves in the area covered by the agreement;3 and United had the right, in addition, to call for any amount up to 150 per cent of the amount it had annually agreed to take. The term of the agreement was 20 years. The initial price provided was 20.5 cents per thousand cubic feet (Mcf.); and the price was to increase one cent per Mcf. every five years.4
Section 7 (c) of the
Petitioner‘s application for the certificate contained the request that the certificate sought “provide for its own expiration on the expiration of the . . . contract term so as to authorize Applicant to cease the delivеry and sale of gas thereunder at that time.” The Commission, upholding its examiner‘s recommendations, rejected the contentions of petitioner that there should be issued to cover the contract only a certificate limited to the term of the contract itself, and tendered it a certificate without time limitation.6 19 F. P. C. 618. Petitioner applied for a rehearing of the Commission‘s order. Basic to this application was the contention that “The Commission is without authority to issue a certificate to an applicant authorizing more than the whole or some part of the sale covered by the application for certificate of public convenience and necessity . . . .” The Commission denied the rehearing application. 19 F. P. C. 1107.
The practical reasons behind petitioner‘s superficially self-abnegating desire to have a limited rather than an unlimited authorization from the Commission are obvious from a study of the
I.
Section 7 (b) of the
If petitioner‘s contentions, as to the want of authority in the Commission to grant a permanent certificate where one of limited duration has been sought for, were to be sustained, the way would be clear for every independent producer of natural gas to seek certification only for the limited period of its initial contract with the transmission company, and thus automatically be free at a future date, untrammeled by Commission regulation, to reassess whether it desired to continue serving the interstate market. And contracts—as did the 1947 contract in the companion case to the one at bar, Sun Oil Co. v. Federal Power Comm‘n, post, p. 170—might provide for termination in the event of a rate reduction by the Commission. Petitioner‘s theory, by tying the term of the certificate to the contract, would mean that such a reduction of rates would under those circumstances enable the producer to cease supplying gas, without obligation to justify its cessa-
The consequences оf petitioner‘s argument do not stop there. The identical provisions of the
And there are practical consequences, related to rate control, which are even more concrete. The companion case, Sun Oil Co. v. Federal Power Comm‘n, post, p. 170, illustrates them. If petitioner‘s certificate of public convenience must expire with its first contract with United, service after then—under a new contract or otherwise—will require a new certificate. And under that certificate, petitioner may file, pursuant to
subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.”
Clearly, the rate change provisions of
Thus it is apparent that petitioner‘s position would enable it to make what in practical effect would be rate
accurate accounts in detail of all amounts received by reason of such increase, specifying by whom and in whose behalf such amounts were paid, and, upon completion of the hearing and decision, to order such natural-gas company to refund, with interest, the portion of such increased rates or charges by its decision found not justified. At any hearing involving a rate or charge sought to be increased, the burden of proof to show that the increased rate or charge is just and reasonable shall be upon the natural-gas company, and the Commission shall give to the hearing and decision of such questions preference over other questions pending before it and decide the same as speedily as possible.”
This Court declared as early as the Hope Natural Gas case that the primary aim of the Natural Gas Act was “to protect consumers against exploitation at the hands of natural gas companies.” 320 U. S. 591, 610. We reiterated that declaration last Term in Catco, and observed that “The Act was so framed as to afford consumers a complete, permanent and effective bond of protection from excessive rates and charges.” 360 U. S., at 388. Against the backdrop of the practical consequences of the petitioner‘s claim and the purposes of the Act, we look to the details of its argument that the Commission is limited, in granting its certificate of public convenience and necessity, to a term certificate of the duration petitioner has proposed.
First. Petitioner‘s argument is based primarily on its construction of
The argument seems to us unpersuasive even on the face of the statutory language. It depends in the first instance upon freighting the phrase “the whole or any part,” obviously intended to give the Commission power to grant less than the whole of an application, with a
Furthermore, within
in subsection (e) of this section and such certificate shall be issued or denied accordingly: Provided, however, That the Commission may issue a temporary certificate in cases of emergency, to assure maintenance of adequate service or to serve particular customers, without notice or hearing, pending the determination of an application for a certificate, and may by regulation exempt from the requirements of this section temporary acts or operations for which the issuance of a certificate will not be required in the public interest.” Added by the
Second. Once we pass beyond parsing the Act to a consideration of its purpose, and of the practice under it, the construction we have given it becomes inescapable. We have outlined the serious consequences for the regulatory scheme that acceptance of the petitioner‘s argument would entail. These consequences cannot readily be averted by other means suggested by the Act.
It is urged that if it is in the public interest to award only an unlimited certificate, the Commission might attain this end by refusing all applications for a limited one, intimating that an unlimited application would be favorably regarded. But the action of the Commission in refusing the certificate as originally applied for would
The Commission‘s practice supports its authority here in the terms of
Further, the Power Commission has from an early date taken the view that there is a continuing obligation to perform “service” imposed by the Act which outlasts the term of a seller‘s original contract of sale. As early as 1942 it held that an abandonment of service after the expiry of such a contract had to have Commission approval under
Third. But against these considerations, it is urged that United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332, establishes dominant factors which impel one to the construction petitioner would put on the Act. Petitioner claims that Mobile establishes a principle that the Act (unlike many other regulatory sсhemes)21 in general preserves the integrity of private contracts, and that the judgment below is in conflict with that principle.
The petitioner states accurately enough the principle that Mobile establishes. See 350 U. S., at 338, 344. But the conclusion petitioner asserts does not follow. In Mobile, this Court held that where a seller of gas had entered into a contract for the sale, it could not, by virtue of the provision in
It is apparent that the Commission‘s order in no way violates the integrity of petitioner‘s contract with United. During its term, both parties are bound by it to the same extent as any members of this regulated industry. When it expires, petitioner, to be sure, will be under an obligation to continue to deliver gas to United on the latter‘s request unless it can justify an abandonment before the Commission; but we do not see how this in any way disturbs the integrity of the contract during its term. The obligation that petitioner will be under after the contract term will not be one imposed by contract but by the Act. It will be free then, as it was not free during the contract term under the contract here in question, to make rate changеs under
The short of the matter is that Mobile recognized that there were two sources of price and supply stability inherent in the regulatory system established by the Natural Gas Act—the provisions of private contracts and the public regulatory power. See 350 U. S., at 344. Petitioner now urges an application of that decision that could
II.
Once the power of the Commission to issue the certificate without time limitation is established, the other objections of the petitioner fall readily. It is contended that the Commission‘s order, by requiring the petitioner to supply gas beyond the term of its contract, may, by requiring petitioner to produce more gas than it has contemplated, offend the provision of
Other objections seem primarily directed to the point that the Commission imposed the burden of proof on the petitioner to show that the certificate should be limited, in the public interest, rather than itself taking on the burden of supporting its issuance of an unlimited certificate. There is no contention that the Commission was again indulging in the erroneous notion that it had no power to issue a limited certificate. Cf. Sunray Mid-Continent Oil Co. v. Federal Power Comm‘n, 239 F. 2d 97, reversed on other grounds, 353 U. S. 944. This procedural formulation seems to us well within the Commission‘s discretion as an implementation of the Act‘s protective provisions which we have discussed. And, though much urged by petitioner, the fact that the Commission has certificated pipеline operations despite their showing of gas resources of a shorter duration than petitioner‘s contract term is not inconsistent with the Commission‘s
Finally it is suggested that for various reasons which petitioner claims to be related to the public interest, it would be more advantageous if gas producers were given a free hand, after the completion of each contract, to determine for themselves whether they should continue to serve the interstate market. These considerations were not urged before the Commission, and hence we are not called upon to decide whether they would compel a different approach by the Commission to the question of time limitations in certificates, or even whether, in the light of the Act‘s provisions—particularly the policy expressed in
Affirmed.
In joining MR. JUSTICE HARLAN‘S opinion I should like to add a word by way of emphasis.
Once analysis of the problem of these two cases, relating as they do exclusively to independent producers of natural gas, is stripped of darkening details and reduced to its statutory determinants, as spelled out in my Brother HARLAN‘S dissent, the answer becomes clear and uncomplicated. If a licensing agency has power to grant a particular kind of license, an applicant has the right to apply for such a license. It may be withheld without ado only if the agency has arbitrary—judicially unreviewable—power to withhold such a license. Concededly the Commission has power to grant a time-limited certificate, and its denial of such a certificate is not free from judicial review. Therefore it must give a reason for denying a proper application, with due regard, of course, to its wide discretionary power for determining what satisfies “рublic convenience and necessity.” The Commission cannot rest denial on its ipse dixit. Nor can the Commission rest on the general spirit or the ultimate purposes of the Natural Gas Act, for to do so amounts to saying that the Act forbids time certificates, when in fact it does not.
MR. JUSTICE HARLAN, whom MR. JUSTICE FRANKFURTER, MR. JUSTICE WHITTAKER, and MR. JUSTICE STEWART join, dissenting.*
The basic issue presented by these two cases is essentially this: When an independent producer of natural gas enters into a contract for the sale of his gas in interstate commerce for resale, and seeks a certificate from the Federal Power Commission to carry out that contract,
*[These opinions apply also to No. 321, Sun Oil Co. v. Federal Power Comm‘n, post, p. 170.]
I.
In my view the Court‘s conclusions are аttributable at bottom to its failure to take into account the basic distinction between an interstate pipeline and an independent producer of natural gas. A pipeline performs a service akin to those traditionally performed by public utilities: The independent producer, on the other hand, is unique among the objects of public-utility regulation because it is not engaged in rendering a service to the public in the conventional sense of that concept, but rather simply in selling a commodity which it owns. The Court‘s basic error, it seems to me, is its notion that the petitioners are rendering a continuing service to the public in the same sense as a pipeline or other conventional utility, to which the usual modes of utility regulation are equally applicable.
I think that the Natural Gas Act, particularly as construed by the Court in Phillips Petroleum Co. v. Wisconsin, 347 U. S. 672, recognizes this important distinction. The basic jurisdictional framework of the Natural Gas Act is found in
“The provisions of this chapter shall apply to the transportation of natural gas in interstate commerce,
to the sale in interstate commerce of natural gas for resale . . . and to natural-gas companies engaged in such transportation or sale, but shall not apply to . . . the production or gathering of natural gas.” (Emphasis added.)
In Phillips the application of this provision to independent producers, such as the petitioners in these cases, was considered. Phillips there contended that it was not subject to the Act because it did not engage in the interstate transmission of gas and was not affiliated with any interstate pipeline company, and that to regulate its prices would be to control the “production or gathering” of natural gas, which is specifically exempted by
The operative provisions of the Act consistently reflect their more limited reach as regards independent producers
“engage in the transportation or sale of natural gas, subject to the jurisdiction of the Commission, or undertake the construction or extension of any facilities therefor, or acquire or operate any such facilities or extensions thereof . . . .”
Thus three distinct categories of jurisdictional acts are subject to certification: (1) transportation, (2) sale, and (3) maintenance of jurisdictional facilities. A pipeline must necessarily secure authorization for both transportation and maintenance of jurisdictional facilities, acts which by their nature are continuing services. But I do not understand the Court to contend that petitioners, as independent producers, have engaged in any jurisdictional аct other than a sale.
The word “sale,” in its ordinary sense, signifies a transaction limited in duration and amount.
The Court, however, purports to find support in the statute for its notion that a sale is really a perpetual service. It relies primarily on
“a certificate shall be issued to any qualified applicant therefor, authorizing the whole or any part of the operation, sale, service, construction, extension, or acquisition covered by the application, if it is found that the applicant is able and willing properly to do the acts and to perform the service proposed, . . . and that the proposed service, sale, operation, construction, extension, or acquisition . . . will be required by the public convenience and necessity . . . .” (Emphasis added.)
It would appear plain from the face of the very language quoted that, while the word “service” is used, it is used disjunctively with “sale” and several other words, so that a sale and a service are simply two different, and not
The Court further says that the provisions of
Finally, the Court points to the requirement of
I must conclude that there is nothing in the statute which makes “sale” the equivalent of “service.” On the contrary, the terms are always used disjunctively. A sale, as a jurisdictional ground distinct from either transportation or the maintenance of jurisdictional facilities (
II.
The Court asserts that a construction of the statute contrary to the one it reaches will result in intolerable consequences, primarily in two respects. First, it says, producers and pipelines would be able to abandon their undertakings at the end of the contract term without a showing that the public convenience and necessity justify such abandonment, thus defeating the policy of
As to abandonment, the Court‘s view again rests on the erroneous notion that the Commission is charged with assuring continuity of “service” on the part of independent producers. However,
There is a more basic reason, however, why the evils which the Court imagines do not exist. The Commission is required to issue a certificate only if the applicant‘s proposal is required by the public convenience and necessity. The vast majority of sales are, of economic necessity, bona fide transactions of substantial duration (see United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332, at 344) and will, of course, be approved in ordinary course. But surely, if a proposal contains such disingenuous provisions as the Court suggests, its certification would not be in the public interest. The Court‘s fear that denial of the certificate under such circumstances would be overturned on review is the sheerest speculation, especially in an area where the Commission is entrusted with such wide discretion.
Furthermore, the Commission can tender a perpetual certificate under its
I would hold that where, as in No. 335, an independent producer applies for authority simply to engage in a sale transaction specifically limited in duration, the Commission has no authority to tender an unlimited certificate without bearing the burden of showing that such a departure from the proposal is required by the public convenience and necessity.
III.
The question remains whether petitioner in No. 321 proposed a sale transaction which was limited in duration and whether the Commission certificаted no more than that sale. The term of the contract filed with the Commission was clearly limited to 10 years. Petitioner‘s application incorporated that contract by reference, and declared that “[t]his application is hereby made only for a certificate of public convenience and necessity authorizing the sale of natural gas in the circumstances above described.” The Commission ordered that a certificate be “hereby issued . . . authorizing the sale by Applicant of natural gas . . . as more fully described in the application and exhibits in this proceeding. . . . The certificate . . . shall be effective only so long as Applicant
The Commission, however, contends that since, at the time petitioner‘s certificate was issued, it had taken the position in Sunray Oil Corp., 14 F. P. C. 877, that it had no power to issue a certificate specifically limited in duration, this certificate must be taken as one unlimited in duration. That position, however, was later reversed on appeal, Sunray Mid-Continent Oil Co. v. Federal Power Comm‘n, 239 F. 2d 97, and the Commission acquiesced therein. But the Commission was more fundamentally wrong in believing that a certificate authorizing a sale is unlimited unless specifically otherwise conditioned. Therefore, when it tendered to petitioner a certificate without any limiting language, its erroneous belief that it was issuing a perpetual certificate could not bind petitioner. The Commission was authorized to issue only a certificate limited to the duration of the sale unless a condition were expressly imposed to the contrary, and what it issued purported to be no more than that. Petitioner cannot be taken to have acquiesced in a certificate authorizing something other than it requested, where the certificate gave no notice of that fact, simply because the Commission may have believed its effect to be otherwise.
I fear this is another instance where the Court has taken impermissible liberties with statutory language in order to remedy what it considers an undesirable deficiency in the way Congress has written the statute. Cf. United States v. Republic Steel Corp., 362 U. S. 482, 493 (dissenting opinion).
I would reverse the judgments in both cases.
Notes
“In all other cases the Commission shall set the matter for hearing and shall give such reasonable notice of the hearing thereon to all interested persons as in its judgment may be necessary under rules and regulations to be prescribed by the Commission; and the application shall be decided in accordance with the procedure provided
