History
  • No items yet
midpage
Sundmacher v. Lloyd
135 Mo. App. 517
Mo. Ct. App.
1909
Check Treatment
GOODE, J.

This case was considered in the decision reported in 114 Missouri Appeal Reports, 217.. After the remand an amended petition was filed in which the plaintiffs alleged in the first count the making of a contract with defendant, June 21, 1902, to do the excavating and grading for the William McKinley High School in the city of St. Louis, which defendant was to erect under contract Avith the board of education of said city, that plaintiffs agreed to do said excavating and grading according to the plans and specifications prepared for the board of education except the excavation below the grade lines for granitoid walks, and defendant agreed to pay plaintiffs for their Avork $6,000; that plaintiffs«entered on the execution of the contract and performed all of it according to the plans and specifications, except such part as Avas not required to be done, and defendant accepted their work as satisfactory and paid them $5,700, leaving a balance of $300 due, which he had'refused to pay. In the second count *520another contract of date of October 10, 1903, is alleged by wbicb defendant employed plaintiffs to excavate below the grade lines for granitoid walks on the lot where the McKinley High School was to be erected; that plaintiffs entered on the performance of their contract for which defendant had agreed to pay f236.50, but after the work was done defendant refused to pay said sum or any part of it. To this petition defendant filed the same answer he had filed to the original petition, the substance of which is set out in the report of the first appeal, but we need to state it here. The first paragraph of the answer is a general denial of the statements in the first count of the petition. The second paragraph consists, firstly, of a general denial of the averments in the second count of the petition and every allegation and matter therein contained, and secondly, of this averment: “Defendant says he has fully paid and' discharged all sums arising out of the claim made by plaintiffs therein (i. e. in the second count of the petition) for excavating below the grade lines for grani-toid walks around' said Wm. McKinley High School.” The third paragraph is a counterclaim for damages sustained by defendant in consequence of plaintiffs having failed to keep the two contracts declared on in the two counts of the petition. These contracts are admitted in the answer substantially as pleaded by plaintiffs and it is averred plaintiffs entered on the performance and did some work, but abandoned them before completion, and defendant had to complete them at an expense of $572.50, for which judgment was asked. Defendant’s answer was filed out of time and later than it should have been, and the record goes to show this circumstance prevented plaintiffs’ counsel from filing a reply until the day of the trial; -when one was filed denying each and every allegation of the new matter contained in the answer and counterclaim. Defendant moved to strike out the reply and for judgment for plaintiffs on the. two causes of action set up in the petition, and *521an inter]ocntory judgment in favor of defendant and against p]aintiff on the counterclaim. The reason assigned for this motion was failure of the reply to deny specifically or generally the facts and matter set .forth in defendant’s answer and counterclaim. The motion was overruled and an exception saved, and thereupon an application for a continuance was made by defendant. The court continued the cause until October 29th, then overruled defendant’s application for further continuance and a trial occurred. Evidence was introduced by both parties in support of their positions on the merits of the cause, instructions were given and a verdict for plaintiffs returned on the first count for $268.40, and on' the second count for $290.42, and judgment having been rendered accordingly, this appeal was prosecuted.

The principal contention of error is the refusal of' the court below to sustain defendant’s motion to strike out the reply and for judgment on the pleadings. The reply was faulty in form because it denied the allegations of new matter contained in the answer and counterclaim without pointing out what said allegations were. [Betz v. Telephone Co., 121 Mo. App. 473; Young v. Schofield, 132 Mo. 650; Dezell v. Casualty Co., 176 Mo. 253.] Defendant did not stand on his motion, but went to trial on the merits of the cause, and must be held to have waived any error committed in overruling the motion unless the argument of his counsel against this general proposition should prevail, it is contended the second paragraph of the answer contained a plea of payment of the demand asserted in the second count of the petition, and defendant relied at the trial on this plea of payment as having been confessed, the reply being so defective as to constitute no denial of it; that defendant introduced no evidence in support of said plea, and therefore, was entitled to an order for a verdict in his favor on the second count of the petition and is now entitled to judgment non obstante veredicto on *522said count ; citing Dezell v. Casualty Co., supra. Admitting for argument’s sake the so-called plea of payment in the second paragraph is consistent with the sweeping denial of every averment in the second paragraph of the petition, which is coupled with said plea, we ask whether there was, in truth, a plea of payment of plaintiffs’ demand and whether it was relied on by defendant as confesséd by the failure to deny it in a good reply. It will be observed the third paragraph of the answer, instead of counting on payment of the demand contained in the first count of the petition, pleads a counterclaim based on plaintiffs’ alleged breách of both contracts; on the one declared on in the second count of the petition, as well as the one declared on in the first count. Moreover, the evidence of defendant himself refutes the idea that he was relying on his plea of payment of the demand alleged in the second paragraph of the petition; for he did not testify he had paid for the work done under the second contract, but, in effect, that the work was satisfactory and he was willing to pay for it, if plaintiffs would reimburse him for other work he had been compelled to have done in order to finish the 'first contract; work in the basement and grading around the outside of the building. Again, a scrutiny of the supposed plea of payment will reveal that, instead of being an averment defendant had paid plaintiffs their demand on account of their second contract, it merely says defendant had paid and discharged all sums arising out of the claim made by plaintiffs thereon for excavating below the grade lines for grani-toid walks around the McKinley High School. This was no averment he had paid plaintiffs’ demand as asserted in the second paragraph of the petition, but an ambiguous statement which may be interpreted to mean defendant had paid either the whole of plaintiffs’ demand or had paid such sum as plaintiffs had earned. The allegation was not one which confessed judgment on the ground they had been paid. We would disregard the statute *523which commands ns not to reverse a judgment unless error has been committed in prejudice of the appealing party, were we to hold defendant was prejudiced by the form of the reply. By going to trial on the merits he waived that matter. [Nelson v. Wallace, 48 Mo. App. 193; Anderson v. Railroad, 129 Mo. App. 384.]

A witness named Wittier testified for plaintiffs over defendant’s objection, that Lloyd told plaintiffs, or Wittier, who worked for them, to omit compliance with the specifications requiring the top soil to be removed and the placing of two piers at the bottom of the sewer Avhich was to be dug. This was the same evidence held erroneous on the first appeal, and it is insisted its admission at the second trial was contrary to the decision then given. But it will be perceived on reading the opinion of the court on the other appeal, said evidence was received at the first trial to prove it was orally agreed, before the contract between defendant and plaintiffs Avas made, certain terms of the specifications need not be complied with by plaintiffs. Inasmuch as the written contract between plaintiffs and Lloyd required plaintiffs to do the work called for in the contract in accordance with the specifications, we held an anterior oral agreement for the omission of certain specifications was a variation of the later written contract and incompetent. [Tracy v. Iron Works, 104 Mo. 193.] The testimony was received at the second trial, not to prove the contract between plaintiffs .and Lloyd was other than on its face it purported to be, but that in the progress of the work Lloyd notified Wittier not to remove the soil or put in piers at the bottom of the sewer. If defendant chose to relieve plaintiffs of those portions, of the work called for by their contract, and to accept the job as completely performed without them, he might do so. It is averred in the amended petition filed after the cause was remanded, he relieved them from compliance with those items of the specifications; and no doubt the averment *524was inserted in order to declare on the contract as altered by the subsequent command of the defendant, as was right. [Lanitz v. King, 93 Mo. 513.]

For the reasons given on the last point, the court •rightly gave an instruction requested by plaintiffs which authorized a recovery if plaintiffs had performed their contract according to Lloyd’s direction, even if, by said, direction, they omitted part of the specifications.

The judgment is affirmed.

Nortoni, J., concurs; Reynolds, P. J., not sitting.

Case Details

Case Name: Sundmacher v. Lloyd
Court Name: Missouri Court of Appeals
Date Published: Feb 9, 1909
Citation: 135 Mo. App. 517
Court Abbreviation: Mo. Ct. App.
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.