Case Information
*4 Before KELLY, MCWILLIAMS, and HENRY, Circuit Judges.
_________________________________
KELLY, Circuit Judge.
_________________________________
For the third time in as many years, we are faced with the task of further defining
and clarifying the relationship between §§ 107 and 113 of the Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C.
§§ 9607 and 9313. See United States v. Colorado & Eastern R.R.,
Background
The operative facts are not in dispute. An abandoned limestone quarry on the south bank of the Arkansas River in Tulsa County, Oklahoma was operated as a landfill from 1972 to 1976. During this time, hazardous materials were brought to the site, and eventually began to seep into the soil, surface water, and ground water near the site. In September 1984, the EPA placed the site on the National Priority List. 40 C.F.R. Part 300, App. B. Three years later the EPA issued a Record of Decision, which selected a remediation for the site consistent with the National Contingency Plan. 42 U.S.C. § 9605.
The EPA identified Plaintiffs, as well as several other parties, as Potentially Responsible Parties (PRPs) who had contributed to the waste at the site. After attempts to negotiate a consent decree were unsuccessful, the EPA issued a Unilateral Administrative Order, pursuant to § 106 of CERCLA, compelling Plaintiffs to pay the costs of remediation for the site. 42 U.S.C. § 9606. Plaintiffs agreed to perform the remediation in compliance with the administrative order and the Record of Decision. Remediation activities began in January 1990, and were completed on or by August 29, 1991. Plaintiffs incurred $6.2 million in cleanup costs.
Plaintiffs were able to identify other parties which they believed had also
contributed hazardous wastes to the site, and brought this action against them on August
29, 1994, asserting a cost recovery action under CERCLA § 107 and a contribution action
under CERCLA § 113. The district court granted Defendants’ motion for summary
judgment on the § 107 action, holding that PRP’s such as Plaintiffs were not allowed to
bring a cost recovery action under § 107. Citing Colorado & Eastern,
The limitations period for a contribution claim under § 113(g)(3) is three years. At issue is when the limitations period begins to run. Section 113(g)(3) provides as follows:
No action for contribution for any response costs or damages may be commenced more than three years after—
(A) the date of judgment in any action under this chapter for recovery of such costs or damages, or
(B) the date of an administrative order under section 9622(g) of this title (relating to de minimis settlements) or 9622(h) of this title (relating to cost recovery settlements) or entry of a judicially approved settlement with respect to such costs or damages.
42 U.S.C. § 9613(g)(3). Plaintiffs incurred cleanup costs in response to an EPA unilateral administrative order under § 106, which is not one of the triggering events above.
The district court held that the fact that Plaintiffs’ action was not governed by one of these triggering events did not guarantee them an unlimited time in which to bring their suit. Rather, according to the district court, this anomaly was the result of an inadvertent *7 omission on the part of Congress. Thus, the court turned to another area of federal contribution law, and held that Plaintiffs’ cause of action accrued (and the limitations period began) when they had paid more than their equitable share of the cleanup costs. With this as the accrual date, the bulk of Plaintiffs’ claims for contribution were time- barred. The district court ruled that each payment should be treated separately, however, so to the extent Plaintiffs could show they made payments within three years of their filing of the instant action, they would still be entitled to seek contribution.
The district court also noted the uncertainty as to possible future costs, as the EPA’s remediation order provides for thirty years of maintenance and review of the Site. Thus, it declined to rule on Plaintiffs’ declaratory action regarding apportionment of such future costs, and requested further briefing on the issue. Such briefing has been abated pending the outcome of this appeal.
Discussion
We review the grant of a motion for summary judgment de novo, applying the
same standard as the district court pursuant to Fed. R. Civ. P. 56(c). Watts v. Atlantic
Richfield Co.,
I.
In Colorado & Eastern, we attempted to clarify the relationship between cost
recovery actions under § 107 and contribution actions under § 113, specifically
addressing who can recover under each provision.
Congress codified this implicit right to contribution with the enactment of the
Superfund Amendments and Reauthorization Act of 1986 (SARA), which added
§§ 113(f) (contribution) and (g) (limitations periods) to CERCLA’s scheme. We held that
under this combined statutory scheme, any action by a PRP who was a defendant in a cost
recovery action was a claim “by and between jointly and severally liable parties for an
appropriate division of the payment one of them has been compelled to make,” and was
“the quintessential claim for contribution.” Id. at 1536. We reaffirmed this holding in
Bancamerica Commercial,
Plaintiffs argue that Colorado & Eastern is distinguishable. They claim that the Colorado & Eastern rule is limited to those situations when the plaintiff PRP has incurred cleanup costs pursuant to a civil action under §§ 106 or 107, whereas Plaintiffs in this case incurred cleanup costs without any such action. Thus, they argue, they are not limited to a § 113 contribution claim, but may also assert a cost recovery claim under § 107. We are not persuaded.
The fact that Plaintiffs incurred cleanup costs by complying with a unilateral
administrative order, without forcing the government to take them to court, does not
change their status as jointly and severally liable parties. They concede that they
generated wastes containing hazardous substances that were transported to the Site. Thus,
Plaintiffs’ claim is still by and between jointly and severally liable parties, seeking the
equitable apportionment of a payment which Plaintiffs have been compelled to make, and
is still a claim for contribution. Bancamerica Commercial,
II.
Plaintiffs’ attempted distinction of Colorado & Eastern is not, however, without
some merit. PRPs who have contributed waste to a site are jointly and severally liable for
cleanup costs, and are limited to seeking contribution from other PRPs.
[1]
If those PRPs
have never been defendants in a civil action under §§ 106 or 107, however, it appears that
there is no statute of limitations governing their contribution claims. Section 113(g)(3)
establishes a three year limitations period for contribution actions, but none of the
[1]
We express no opinion on whether PRPs who assert their innocence with regard
to any waste at a site may be able to recover all of their costs from other PRPs in an action
under § 107. See Redwing Carriers, Inc. v. Saraland Apts.,
As we made clear in Bancamerica Commercial, § 113(f) did not create a new cause
of action, nor did it create any new liabilities.
[2]
It is thus clear that “because §113(f) incorporates the liability provisions of § 107,
. . . a § 113(f) action for contribution is an action under § 107.” Bancamerica
Commercial,
The contours of all CERCLA claims by and between PRPs who contributed waste to a site are thus governed by the equitable contribution principles of § 113(f), and seek to *13 recover costs referred to in § 107. A close reading of § 113(g) makes it clear, however, that not all contribution claims have the same statute of limitations.
PRPs against whom the government has brought a civil action under §§ 106 or 107 and who incur cleanup costs will do so in one of two ways: either the suit will proceed to judgment or the parties will enter into a settlement. PRPs in either situation are expressly covered by the language of § 113(f): “A person may seek contribution . . . during or following any civil action under [§§ 106 or 107] of this title.” In addition, whether by judgment or settlement, the three year limitations period of § 113(g)(3) will be triggered. If the suit proceeds to conclusion, the limitations period begins running on the date of judgment. 42 U.S.C. § 9613(g)(3)(A). If the parties settle, the limitations period begins running on the date of the administrative order embodying the settlement (for § 9622(g) de minimis settlements or § 9622(h) cost recovery settlements), or on the date of entry of a judicially approved settlement. 42 U.S.C. § 9613(g)(3)(B). A judgment has its own procedural safeguards, and CERCLA settlements are subject to publication in the Federal Register and a 30-day notice and comment period. 42 U.S.C. § 9622(i).
PRPs who have incurred cleanup costs in some other way are also covered by the language of § 113(f): “Nothing in this subsection shall diminish the right of any person to bring an action for contribution in the absence of a civil action under [§§ 106 or 107] of this title.” Such PRPs, however, will not trigger the running of the limitations period in *14 § 113(g)(3), nor will their liability be fixed with the procedural safeguards attendant to a civil action.
Contrary to the district court’s ruling, however, this does not create a gap in the statute of limitations, because § 113(g)(2) covers PRPs in this situation. It provides:
An initial action for recovery of the costs referred to in section 9607 of this title must be commenced—
. . . .
(B) for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action . . . .
42 U.S.C. § 9613(g)(2). As we previously noted, “a § 113(f) action for contribution is an
action under § 107.” Bancamerica Commercial,
Defendants argue that § 113(g)(2) covers only the traditional “cost recovery” action under § 107—which imposes strict, joint and several liability on other PRPs and which, as we have already held, is not available to Plaintiffs. We disagree because the language in question contains no such limitation. By its own terms, § 113(g)(2) covers *15 the “initial action” for the recovery of “costs referred to” in § 107. There is no question that this language covers a traditional § 107 cost recovery action brought by the government or any other person who is not a waste-contributing PRP. Nothing in that language, however, excludes a contribution action, which also seeks to recover an equitable portion of “costs referred to” in § 107, provided that particular contribution action is the “initial action” to recover such costs.
Defendants also argue that the language of § 113(g)(3) makes it clear that Congress expressly chose a three-year limitations period for all contribution claims. Thus, they argue, the six-year limitations period in § 113(g)(2) cannot apply. [3] It is true that § 113(g)(3) is subtitled “Contribution,” and provides that “[n]o action for contribution for any response costs or damages may be commenced more than 3 years after—[the four enumerated triggering events].” Contrary to Defendants’ arguments, however, our construction of the statute is not inconsistent with this language. A contribution claim which is the “initial action,” and thus governed by the six-year limitations period of § 113(g)(2), will not be commenced more than three years after any of the four enumerated triggering events, because none of those triggering events will ever occur.
*16
By contrast, if a contribution action is not the initial action, then by definition a
previous action will have been filed, and one of the four triggering events in § 113(g)(3)
will occur. In this way, Congress has provided an express statute of limitations to cover
all CERCLA contribution actions, regardless of how the PRPs in question incurred their
cleanup costs. In effect, there are two different types of contribution actions under
CERCLA, each governed by the same equitable rules of § 113(f) and each seeking to
equitably apportion costs referred to in § 107, but governed by different statutes of
limitations. See Key Tronic Corp. v. United States,
This construction of CERCLA is internally consistent in its application of the
language of the statute, and follows our precedents and the increasing body of law from
other circuits. Together, §§ 107 and 113 allow “any person” who has incurred cleanup
costs consistent with the National Contingency Plan to recover some or all of those costs
from PRPs who were responsible for the waste. A government entity (Federal, State or
Indian) or a party who did not contribute to the waste may recover all of its expenditures
in a traditional § 107(a) “cost recovery” action against any PRP. Liability will be strict,
joint and several. A PRP who contributed to the waste may recover from other PRPs a
portion of the costs it expended in cleaning up the site in a contribution action under
§ 113(f). Colorado & Eastern ,
This construction of §§ 107 and 113 also gives effect to each section of the statute.
See Colorado & Eastern,
III
PRPs who have contributed to the waste at a site may recover from other PRPs that
portion of their cleanup costs which exceeds their pro rata share. Such an action is “the
quintessential claim for contribution,” Colorado & Eastern,
Notes
[2] Section 113(f) of CERCLA governs contribution claims and provides: Any person may seek contribution from any other person who is liable or potentially liable under section 9607(a) of this title, during or following any civil action under section 9606 of this title or under section 9607(a) of this title. Such claims shall be brought in accordance with this section and the Federal Rules of Civil Procedure, and shall be governed by Federal law. In resolving contribution claims, the court may allocate response costs among liable parties using such equitable factors as the court determines are appropriate. Nothing in this subsection shall diminish the right of any person to bring an action for contribution in the absence of a civil action under section 9606 of this title or section 9607 of this title. 42 U.S.C. § 9613(f)(1).
[3] This rationale also was expressed in Ekotek Site PRP Committee v. Self, 881 F.
Supp. 1516, 1522 n.2 (D. Utah 1995), but we do not find exclusive reliance upon
§ 113(g)(3), see Ekotek,
[4] “Orphan shares” are those shares of the waste responsibility which are
attributable to PRPs who either are insolvent or cannot be located or identified. Pinal
Creek,
