Sun Beach Real Estate Development Corp. v. AndersonSun Beach Real Estate Development Corp. v. Anderson
OPINION OF THE COURT
Under the Town Law, a planning board which fails to act on a preliminary subdivision plat application within 45 days is deemed to have approved the preliminary plat (Town Law, § 276, subd 3). What we now decide is how that rigorous mandate for prompt action interacts with the State Environmental Quality Review Act (SEQRA) (ECL 8-0101 et seq.) requirement that an application for a permit
Having been found in violation of the Town Law time restriction in processing petitioner’s 777-acre subdivision plat, East Hampton’s Planning Board argues that the 45-day time limit did not even begin to run until the board accepted petitioner’s DEIS and that 45 days was too short a time for the board to meet its SEQRA obligations. Victorious at Special Term, the petitioner disagrees, contending that the 45-day time limit is an absolute one and that it is unaffected by any provision of SEQRA. We believe that preliminary plat approval determines important design features of a subdivision and therefore SEQRA’s mandate for early meaningful consideration of the environmental consequences of a project requires environmental review to be undertaken when a preliminary plat application is filed. Once the East Hampton Planning Board determined that a DEIS was necessary, the preliminary plat application was not complete until the DEIS was accepted by the board. As a consequence, the time requirements of the Town Law did not commence running until after that acceptance.
On July 29, 1982, Sun Beach Real Estate Development Corp., the owner of a 777-acre tract in the. Town of East Hampton, applied to the planning board for preliminary approval of a subdivision plat which showed a proposed development of 188 one-family residences and 143 condominium units. Attached to the application was an environmental assessment form (EAF) intended to assist the planning board in determining the environmental significance of the application (see 6 NYCRR 617.2 [/]). By letter dated September 7, 1982, the planning board informed Sun Beach that its application would be processed when it was complete, i.e., when the board issued a determination that the preliminary approval was of no environmental significance or when it accepted a DEIS if it decided there was environmental significance. Relying on subdivision 3 of section 276 of the Town Law, on October 15, 1982, Sun Beach demanded a certificate from the town clerk granting preliminary plat approval because the planning board had
There can be no doubt that absent SEQRA’s requirements, Sun Beach would have been entitled to the approval certificate because default statutes such as section 276 of the Town Law and similar provisions governing city and village planning authorities (see General City Law, § 32; Village Law, § 7-728) have been uniformly construed to require automatic approval upon the failure to act within the prescribed time limits (see, e.g., Matter of Pekar v Town of Veteran Planning Bd.,
It is a familiar canon of statutory construction that apparently conflicting statutory provisions should be harmonized in a manner that preserves the essential purposes of both (Matter of Burger King v State Tax Comm.,
SEQRA’s procedures are intended to minimize to the greatest degree possible the adverse environmental consequences of any project that is approved. In Glen Head-Glenwood Landing Civic Council v Town of Oyster Bay (
It is undisputed that development of petitioner’s 777-acre tract will have environmental reverberations and that the instant subdivision process constitutes an “action”
While the imprecision of the statutory language renders it difficult to identify the precise point when a DEIS must be prepared during an “action” (see Matter of Tri-County Taxpayers Assn. v Town Bd.,
It is thus apparent that the DEIS must be prepared at a point “ ‘where genuine flexibility remains before bureaucratic momentum strips [it] of any real influence on decision-making’ ” (see Mount Sutro Defense Comm. v Regents of Univ. of Cal., 77 Cal App 3d 20, 34).
With these considerations in mind, we return to the parties’ debate as to when it is during the subdivision approval process that the DEIS must be filed. We view preliminary plat approval as so significant a determination during the process that an environmental impact statement must be deemed a prerequisite to the approval. The two-stage subdivision approval procedure — preliminary approval and final approval — adopted in this State in 1966 (Town Law, § 276, subds 3, 4, as amd by L 1966, ch 695) was intended to fix the broad outlines of the proposed development so that the developer could know where it stood before incurring additional expenses associated with the preparation of the detailed plans involved in final approval (see Matter of Mahopac Isle v Agar,
Preliminary plat approval has greater weight than a mere informal reaction to a preliminary plat (see 4 Anderson, American Law of Zoning [2d ed], § 23.13) and it has been held that a planning board may not modify a preliminary plat and then disapprove of the layout of a final plat that conforms to the modifications prescribed by the board (see, e.g., Matter of Walton v Town of Brookhaven,
In determining the temporal position of the DEIS in the subdivision process, the holdings of our sister States are entitled to respect in view of the essential uniformity of environmental legislation (see Robinson, SEQRA’s Siblings: Precedents from Little NEPA’s in the Sister States, 46 Albany L Rev 1155, 1157). Interpreting Washington’s State Environmental Policy Act of 1971 (Wash Rev Code Ann, ch 43.21C; SEPA), a statute similar to our own, the Supreme Court of Washington held that preliminary approval of a subdivision requires the preparation of an
Our conclusion, then, is that when the planning agency has determined that development of the subdivision might significantly affect the environment, the application for preliminary approval is not complete until a DEIS has been filed and has been accepted by the agency as satisfactory in scope and content (see ECL 8-0109, subd 5; 6 NYCRR 617.3 [e]). The DEIS should be available when it is still practicable to modify the project so as to mitigate potentially adverse economic effects or to choose a less environmentally damaging alternative (see ECL 8-0109, subds 2, 8) and before it is too late to influence the basic design of a project already fixed at the preliminary stage (see ECL 8-0103, subd 7; Glen Head-Glenwood Landing Civic Council v Town of Oyster Bay,
Once the application is complete, the planning board must co-ordinate its subdivision approval procedures with SEQRA (ECL 8-0109, subd 5; 8-0103, subd 6). The 30-day period of comment on the DEIS for involved agencies and the public (6 NYCRR 617.8 [c]) easily fits within the 45-day period for holding a preliminary plat hearing under subdivision 3 of section 276 of the Town Law and it is preferable that a joint hearing be held (6 NYCRR 617.8 [d]). The final environmental impact statement need not be prepared until after the final plat has been submitted since SEQRA requires only one DEIS and one final environmental impact statement to be prepared for a given action (6 NYCRR 617.2 [b]); preparation of a final environmental
Where a DEIS is a requisite to preliminary approval, the 45-day deadline imposed by the Town Law seems too short for planning boards to fulfill their SEQRA requirements. While an agency may vary SEQRA’s time limits for “preparation, review and public hearings to coordinate the environmental review process with other procedures relating to review and approval of an action” (ECL 8-0109, subd 5), provided the periods as varied are “no less protective of environmental values” (6 NYCRR 617.4 [b]), the agency cannot take any further steps until the submission of a DEIS (see ECL 8-0109, subd 4). If the application does not contain the DEIS, the 45-day period for Town Law action may elapse before the statement has been filed, leaving the agency with the option of granting approval without the DEIS and running the risk of legal challenge to its decision or of denying approval on the ground of inadequate environmental review (Sahm, Project Approval Under the California Environmental Quality Act: It Always Takes Longer Than You Think, 19 Santa Clara L Rev 579). Neither alternative is acceptable.
It is apparent that SEQRA’s drafters did not take into account some of the idiosyncracies of subdivision procedures (see Marsh, Commentary — Unresolved Issues, 46 Albany L Rev 1298, 1304) and it has been left to the judiciary to attempt to co-ordinate the statutes. Resolution of the instant case depends on which statute has preeminence — the 45-day requirement enacted in 1966 to limit the depredations of dilatory planning boards (see Matter of Mahopac Isle v Agar,
In reaching our conclusion, we are quite aware that SEQRA and its regulations have set no time limits within which a planning board must accept a proposed DEIS (see Matter of East Clinton Developers v Town of Clinton,
Whatever the future may hold in this respect, however, the instant judgment should be reversed, without costs or disbursements, and proceeding dismissed.
Damiani, J. P., Thompson and Gulotta, JJ., concur.
Judgment of the Supreme Court, Suffolk County, dated March 14, 1983, reversed, on the law, without costs or disbursements, and proceeding dismissed on the merits.