106 Tenn. 85 | Tenn. | 1900
This is an action for damages for the breach of a contract made by. the defendants with the county of Sullivan to erect a bridge across the Iiolston river at Bluff City. The Chancellor was of opinion the defendants had substantially complied with the contract and were not liable for damages, and dismissed complainant’s bill.
There was an appeal by the county, and on a hearing before the Court of Chancery Appeals that Court modified the decree of the Chancellor and gave judgment for an item of $172, with interest from the filing of the bill in this cause, this being the cost of having the bridge piers grouted, . which the defendants should have done
It appears that the County Court of Sullivan County appointed a committee, consisting of the Road Commissioner and two others, to have the bridge built, and empowered them to employ an engineer. The committee let the stone work to .Ruth & Co., entering into a written contract with them, with specifications. The contracts were reported to the Court and by it approved. The contract and specifications required the contractors to do and perform the work as specified in it, and in conformity with the instructions which shall be given from time to time by the engineer in charge for the county, the work to be paid for when completed agreeably to the specifications and to the satisfaction of the engineer.
Upon the facts as thus stated the Court of Chancery Appeals was of opinion that the provisions of the Act of 1835, being Sections 1730, 1731, 1732 of Shannon’s Code, fixing the rights and duties of the contractors, and that the Act of 1859-60 (Shannon, § 1738) did not apply exclusively, the latter relating to the repair of bridges, while the former related to the erection of new bridges. The Court ivas of opinion that under Sections 1730, 1732 the engineers and commissioners must have the contract executed strictly according to the specifications, and had no power to waive any of their requirements or deviate from their provisions, and hence the contractors could not be protected in their deviations from the specifications by the directions of the engineer and the acquiesence of the committee. We
It ' is not meant to hold that Section 1738, Shannon’s compilation, is not also applicable, as the repair of bridges may very properly be held to embrace the erection of a new one on the site of an old one which has become defective, but the question remains whether under either Act the committee appointed to have the bridge erected can in any way deviate from the specifications laid down in the contract. It rvill be observed that the contract bound defendants to perform the work in accordance with tire contract, and, also, in accordance with the instructions to be given from time to time by the engineer in charge. Evidently some duty was intended to be imposed on the engineer and committee in the execution of the contract and performance of the work. But we do not find that any discretion is
The Court of Chancery Appeals reports that it is not true that the defective work was the prime, efficient and proximate cause of the destruction of the pier, and fhe destruction of the bridge placed on it, but that by reason of said defective work the pier was less able to withstand the impact of an unusual flood tide in the-river, which bore down on it an unusual quantity of drift, and that if the work had been constructed in accordance with the terms of the contract, it would probably have not been able to resist the violence of the flood and the impact of heavy driftwood, timber, and the trunks of
The bridge AAras finished and accepted February 21, 1897, and Avas washed aAvay and, destroyed March 23, 1897. The freshet which destroyed the pier was • one almost unprecedented, and as we construe the finding of the Court of Chancery Appeals, the bridge would not probably have withstood it, if it had been constructed according to contract, but it Aras not so strong and secure as it would have been if constructed according to contract. We are. of opinion it was beyond the power and authority of the engineer and committee to waive • any requirement of the contract which Avould make the bridge less secure than if built according to specifications, and that their authority only extended to superintending the construction according to contract, and they had no power to alloAv the stability of the structure to be lessened, and this Avas knoAvn to the contractors. It is probable that the Court might have delegated to the engineer and committee the de
The Court declined to charge the defendants with the cost of replacing the superstructure, and limited the recovery to the replacing of the pier which was washed away, and the grouting of those which remained, and this is made the basis of an assignment of error on the part of the county.
This damage the Court of Chancery Appeals treat as consequential, and arising out of two contributing causes, to wit, the weakness of the pier and the violence of the flood. The doctrine of contributing causes may be stated, generally, that where two or more causes concur, and it cannot be determined which contributed most largely, or whether without their concurrence the accident would have happened, a recovery cannot be had. Marble v. Worcester. 4 Gray, 395.
The' wrongful act of the defendant must be the efficient cause of the injury, without which the injury would not have occurred, and the influence of the wrongful act should predominate over all other supervening causes. Brown v. Wabash Railroad, 30 Mo. Appeals, 222 (S. C., 5 L. R. A., 787).
So when an injury has been occasioned by one of two causes for only one of which defendant is responsible, the plaintiff must show that the damage was produced by that cause. Searles v. Manhattan Railroad Co., 101 N. Y., 661 (S. C., 1 L. R. A., 131, note).
Under these rules the defendant should not be liable for the damage to the superstructure. But for the unprecedented flood this misfortune would not have occurred. But the defect in the pier would have existed if the flood had never come, and defendant would have been responsible even if it had not been swept away. Its destruction was simply the revealing of a state of affairs which would have made the defendant liable for the defects, even though no actual consequential injury had occurred.
The defendants, when they undertook the contract, were required to execute a bond for the sum of $4,000 to faithfully comply with it. The Court of Chancery Appeals finds that the bond was never, as a matter of fact and law, executed;, that it was signed by two sureties and placed in the hands of one of the makers, Jenkins, to be-signed by the other surety, Sells, but it was.
The result is that the decree of the Court of Chancery Appeals is affirmed.