Sturgeon v. Borough of Oakdale

77 Pa. Super. 448 | Pa. Super. Ct. | 1921

Opinion by

Linn, J.,

This appeal is from a decree dismissing plaintiff’s bill in equity. The important averments were that in October, 1916, he became the owner of twenty-one acres of farm land by the devise of his brother Samuel H. Sturgeon ; that with the devisor’s assent, the defendant borough had constructed a twenty-inch sewer across the land in 1914; that the sewer was supported over a natural watercourse by a concrete structure or bridge which was so constructed “as to leave only twelve inches of vertical space between the said bridge and the bed of said watercourse, and during any rainfall of ordinary quantity, the watercourse becomes clogged up at said bridge, so that the surface waters cannot pass through ......” thereby flooding his farm consisting not only of the twenty-one acres but also of other adjacent land be*450longing to him. He prayed (a) for “such reconstruction of said sewer line that said watercourses shall he as open to passage of surface waters as before same was constructed”; (b) reconstruction so “that the top thereof shall be level with or beneath the natural surface of the land”; (c) for damages sustained since October, 1916; (d) that the borough “remedy said conditions within 30 days.”

The answer contained averments generally denying any nuisance alleged; stated that in October, 1914, Samuel H. Sturgeon, the owner, orally agreed that the sewer should be constructed across the land in consideration that the borough should not, as contemplated, place its sewerage disposal plant on this tract but upon a tract further away; that the sewer and the system were accordingly constructed in December, 1914, and were in service.

There was a trial on the issues so made. Among the findings of fact, fully supported by evidence, and unexcepted to, were the following:

“In the year 1914 one Samuel H. Sturgeon was the owner of a tract of land containing twenty-one acres, located near the Borough of Oakdale in Allegheny County. The borough in that year passed ordinances for the construction of a sanitary sewer system, and proposed to put its disposal plant and filter-beds on this land. The owner, being desirous that the disposal plant should not be put upon his property, agreed with the borough that they might lay their sewer line through his property, provided they would put the disposal plant on another piece of ground farther from the borough. The borough thereupon placed its disposal plant as agreed upon and laid its sewer across the land in question near the bank of Eobinsons Eun, where the sewer crossed a small stream running into Eobinsons Eun, provision being made for the water of the stream by placing two large sewer pipes in the bed of the stream under the sewer:”

*451The chancellor affirmed the following requests presented by plaintiff:

“That where said sewer-line crosses the said watercourse, a concrete bridge was constructed, about ten feet long, two feet wide, and in depth between four or five feet, extending down into the Y-shaped ravine through which said surface waters run. That under said concrete bridge there was a space of about three feet ■to the bottom of said ravine, and in said space the borough laid two 24-inch sewer pipes,- with the evident intention that said two pipes would act as sluice-ways through which the surface waters would run.”

To the request to find that “The two 24-inch sewer pipes failed to carry away the surface waters frequently dammed up at said sewer line where it crosses the watercourse, and spread back over the plaintiff’s farm; in 1918 the same condition was present; and in 1919 the conditions became worse,” the chancellor answered “affirmed as to the sewer line when not cleaned out.” He refused to find the following: “Owing to the fact that the borough did not leave sufficient space under its sewer line where it crosses said watercourse, the waters dammed back during even ordinary rainfalls and the silt and stones were deposited until the space under the concrete bridge completely closed up and the two 24-inch sewer pipes were completely submerged.”

The only exceptions filed below were to two conclusions of law but one of which we need quote: “The prayer of the plaintiff’s bill is that the Borough of Oak-dale be required to reconstruct and replace its sewer so that the top of it shall be level with, or below the natural surface of the land, and so that the watercourse in question shall be as open as it was before the sewer was constructed. As the sewer was constructed under an agreement with the former owner of the land, and so far as appears, in the manner agreed upon between the defendant and that owner, the defendant has a right to *452maintain its sewer as it is. It cannot therefore he required to remove the sewer, or to change its location.”

. The decree was founded upon that conclusion and both are now assigned for error. The conclusion is inevitable from the facts. There was evidence that the borough took the necessary preliminary steps to exercise an undoubted power to construct a sewerage system. Instead of condemning the required property owned by Samuel H. Sturgeon, the borough and he agreed (as the statute contemplates they may) that the sewer should be constructed across the farm. The effect of that agreement was to compensate the owner for all damages sustainable by him in consequence of the lawful construction, operation and maintenance of the sewer: Railway Co. v. Swank, 105 Pa. 555, 561; Pettit v. R. R. Co., 222 Pa. 490, 499; of course it did not compensate for insufficiently culverting a watercourse; Ry. Co. v. Gilleland, 56 Pa. 445, 449; Berninger v. Ry. Co., 203 Pa. 516, a condition not raised by this record. After the construction and. use of the sewer, and until his death nearly two years later, Samuel H. Sturgeon had the farm, physically encumbered with the sewer crossing the watercourse as stated in the findings quoted, and, as has been stated, he had received his compensation for any diminution so resulting in the value of his land. At his death, his devisee, the appellant, took the farm with the sewer lawfully there. There is nothing in the record permitting the court to grant the relief prayed for.

The decree is affirmed; costs to be paid by appellant.

midpage