Strome v. Lyon

110 Mich. 680 | Mich. | 1896

Grant, J.

Plaintiff sued to recover a balance due upon a written contract by which he agreed to erect a house for the defendant, and also for extra work and material. The balance unpaid on the contract was $93; the extra work and material, $43. The jury found for the plaintiff for the entire amount. The defense was that the contract was not complied with in three particulars: (1) That the work was not finished; (2) that the plastering was not done according to the contract, or in a good and workmanlike manner; and (3) that the woodwork was not finished with two coats of oil, as specified.

*681The principal objection urged is that plaintiff did not perform his part of the contract, and therefore cannot maintain an action upon the common counts. Plaintiff testified that he performed the work; that the building was turned over to, and accepted by, the defendant; that he made no objection; that he expressed himself satisfied, and repeatedly promised to pay. On cross-examination plaintiff admitted that a few square feet around one door were not given the last coat of paint as required by the contract, the cost of finishing which would be 10 or 15 cents. He also explained why this was not done. His testimony also tended to establish the fact that the change of plastering was made at the defendant’s request, after the contract was made, and that the inside woodwork was finished according to the contract. The defendant gave notice of recoupment, and the court instructed the jury that, if they found that the work was not done according to the contract, the defendant was entitled to recover such damages as he had suffered.

The claim of the defendant that plaintiff cannot maintain this form of action because he had not completed the contract cannot be sustained. The jury evidently found that plaintiff had substantially complied with it, and that defendant had accepted it. If defendant accepted the work without objection, and expressed himself satisfied therewith, he is now estopped to deny the full execution of the contract. The charge of the learned circuit judge was full and fair, and left the jury to determine all the questions involved, and the testimony was ample to sustain the verdict.

Several questions were raised upon the admissibility of evidence, which we do not think it important to consider. The rulings of the court in this respect were correct.

Judgment affirmed.

The other Justices concurred.