Stromberg Metal Works, Inc., and Comfort Control, Inc. v. Press Mechanical, Inc.Stromberg Metal Works, Inc., and Comfort Control, Inc. v. Press Mechanical, Inc.
Bechtel Power Corporation is the owner’s contracting agent for the Calvert Cliffs nuclear power station under construction in Lusby, Maryland. Bechtel hired Press Mechanical to work on the heating, ventilation, and air conditioning system of the power station’s diesel generator building. The contract between Bechtel and Press calls for the application of Maryland law and requires Press to “bind every subcontractor to ... the terms of the construction documents as far as applicable to the work performed by the subcontractor”. Press engaged Stromberg Metal Works and Comfort Control to do some of the HVAC work required by the Bechtel-Press contract. Press issued purchase orders, which provide on the front that the work is to be done “in strict accordance with the plans, specifications and other contract documents listed below” — which include
The contract between Press and Bechtel provides that Bechtel will pay Press for work done by a subcontractor only if Press certifies that the subcontractor has been paid, or that a bond secures payment. The project’s owner needs clean title, which means that Bechtel or the owner may have to pay the subcontractor directly if necessary to clear a mechanic’s or materialman’s lien. No one wants to pay twice for the same work. Hence the requirement that Press pay the subcontractor before Bechtel will pay Press. According to the complaint, whose allegations we must accept, Press represented to Bechtel that it had paid more than $425,000 to Stromberg, and more than $27,000 to Comfort Control, for their work under the subcontracts. Bechtel then reimbursed Press. But the representation was false; Press had paid only $18,000 to Stromberg and nothing to Comfort Control. Press is insolvent and has made an assignment for the benefit of its creditors. Apparently Stromberg and Comfort Control do not have liens on their work (the reason for this is not clear, but we need not pursue the question). Having paid Press, Bechtel is unwilling to pay the subcontractors directly, and Press cannot. Stromberg and Comfort Control filed this action under the diversity jurisdiction seeking to collect from Lester H. Goldwyn, John P. Goldwyn, and George E. Zielinski, who it believes controlled Press and were responsible for the false certification to Bechtel and the non-payment of the debts on the subcontracts. They invoke the Maryland Construction Trust Fund Statute. One clause of this law, Md. Real Property Code § 9-201(b)(l), provides that funds received by a contractor “for work done or materials furnished ... for or about a building by any subcontractor” are held in trust for the subcontractor, and § 9-202 adds:
Any officer, director, or managing agent of any. contractor or subcontractor, who knowingly retains or uses the moneys held in trust under § 9-201 of this subtitle, or any part thereof, for any purpose other than to pay those subcontractors for whom the moneys are held in trust, shall be personally liable to any person damaged by the action.
Illinois law lacks any comparable provision, so plaintiffs’ case depends on the application of Maryland law. Zielinski and the Goldwyns believe that they have defenses even if Maryland law applies, but we need not decide whether that is so. Similarly, we sidestep the question whether the current version of the Maryland law (which we have quoted) differs materially from the version in force when Press failed to pay Stromberg and Comfort Control.
I
Stromberg’s claim exceeds $50,000, but Comfort Control’s claim does not, so the immediate question is: does the supplemental jurisdiction permit a court to hear a claim by a party whose loss does not meet the jurisdictional minimum? In
Clark v. Paul Gray, Inc.,
Although the final sentence of
The Goldwyns ask us to distinguish
Abbott Laboratories
on the ground that it, like
Zahn,
involved a class action.
Zahn held
that every member of a class must satisfy the jurisdictional minimum, and
Abbott Laboratories
concluded that under
over claims by plaintiffs against persons made parties under Rule 14, 19, 20, or 24 of the Federal Rules of Civil Procedure, or over claims by persons proposed to be joined as plaintiffs under Rule 19 of suchrules, or seeking to intervene as plaintiffs under Rule 24 of such rules, when exercising supplemental jurisdiction over such claims would be inconsistent with the jurisdictional requirements of section 1332.
Thus plaintiffs joined under
“Closely related” is a vital qualification.
II
Stromberg lost on the merits in the district court because the judge thought that Stromberg had assented to the application of Illinois law. Press is an Illinois corporation with its principal place of business in Illinois; Stromberg and Comfort Control are Maryland corporations; Stromberg’s place of business is Washington, D.C., and Comfort Control’s is in Maryland. The subcontracts had enough of a link to Illinois that an Illinois court would permit the parties to select Illinois law. See
Hofeld v. Nationwide Life Insurance Co.,
All questions of contract to one side, Illinois law is presumptively applicable because plaintiffs want to hold corporate officers liable for corporate acts. Efforts to “pierce the corporate veil” are governed by the law of the state of incorporation, see
Kern v. Chicago & Eastern Illinois R.R.,
One way to establish that Maryland law applies would be to show that subcontractors are third-party beneficiaries of the rules Bechtel established for the project-rules that appear in the Bechtel-Press contract. See E. Allan Farnsworth, 3
Famsivorth on Contracts
§ 10.4 (1990). Owners and their agents have powerful reasons to want all work on a project done according to one set of laws. For example, the owner must decide whether to require contractors to post bonds securing payment of subcontractors. The decision whether to require such a bond could be influenced by the existence of a law such as Maryland’s Construction Trust Fund Statute. When corporate managers have more incentive to pay their subcontractors (as they do under Maryland law, to avoid personal liability), there is less need for bonds. Then, too, the price of the Bechtel-Press contract may well have depended on assumptions about liability for defects (which depends on state law), on the likelihood that the contractor could excuse noncompliance with the contract (state law,
Negotiated language on the front of each purchase order reads:
Seller shall furnish and install all duct work, hangers, HVAC, equipment and appurtenances and install all owner-furnished equipment in strict accordance with the plans, specifications and other contract documents listed below, as well as Bechtel procurement specification DG-80491, Bechtel design specification SP-782 and all shop drawings prepared by buyer. All work to be performed under the direct supervision and control of buyer’s project manager, project superintendent (or their designee) and shall adhere to all project requirements, including, but not limited to, Buyer’s Quality Assurance Safety and Fitness for Duty programs.
Plaintiffs emphasize the words “other contract documents” and “all project requirements”, but the context in which these words appear establishes that they refer to the technical requirements of the work. Strom-berg and Comfort Control agreed to do exactly what Press had promised Bechtel it would do. A more backhanded way of selecting Maryland law would be difficult to imagine. True, the Bechtel documents include that provision, but they are crammed with other requirements that are not plausible candidates for imputing to the subcontract. Reading the language typed on the purchase orders as limited to the nature of the work the subcontractors agreed to do makes so much more sense than reading it as incorporating the whole Bechtel-Press contract that the judge was entitled to dismiss the complaint under
The judgment with respect to Stromberg is affirmed. The judgment dismissing Comfort Control as a plaintiff is vacated, and the case is remanded with instructions to enter judgment on the merits.