159 P. 44 | Utah | 1916
The plaintiff commenced this action to recover an alleged balance due him from the defendants upon an oral subcontract, wherein plaintiff agreed to and did perform certain work for the defendants. The plaintiff, as a first cause of action, alleged that on the 26th day of October, 1913, he and the defendants entered into an oral contract—
“whereby this plaintiff agreed to construct that portion of the roadbed of said Salt Lake & Utah Railroad Company lying between stations 277 and 282 in mile 26, according to the engineer’s survey of the Salt Lake and Utah Railroad Company, and to complete and make ready the said grade or roadbed for the laying of track thereon; and said Yosburg and Carlson, in consideration of the work so to be performed and completed by said plaintiff, agreed to pay to plaintiff at the time of the completion of said work, the sum of forty cents ($.40) per cubic yard, for all loose dry material removed in the execution of said work, and, if in the prosecution of said work the plaintiff should encounter wet material, then and in that event he was to prosecute said work to completion upon what is known as a force account, that is to say, the said plaintiff was to be paid at the rate of five dollars ($5) per day for each man and team, plus ten per cent for wear and tear on the tools and equipment and $2.50 for each laborer doing common labor; in other words, the plaintiff was to be paid at the rate
Plaintiff further alleged' that he commenced work on the date aforesaid and completed the work on the 10th day of December, 1913; that in completing said work he removed 10,516.5 cubic yards of dry material, and that, in addition thereto, he removed a certain quantity of wet material; that for the removal of dry material he, under the terms of the contract, was entitled to the sum of $4,206.60, and for the removal of the wet material the further sum of $1,914.00 “plus ten per cent”; that there was a balance due him at the commencement of the action, upon the contract aforesaid, amounting to the sum of $4,698.20. As a second cause of action plaintiff alleged the defendants owed him a balance of $141.30 for the use of his teams, etc. The defendants answered the complaint, and, in answer to the first cause of action, after admitting that they had entered into a contract with the plaintiff to do certain excavation work, they set forth the terms and conditions'of that contract in the following words:
“That the terms, conditions and stipulations of the contracts between the Inter-Urban Construction Company and the Reynolds-Ely Construction Company and the Reynolds-Ely Construction Company and these defendants covering the said work (the said two contracts being identical as to terms except as to price per cubic yard and amount), all of which terms, conditions and stipulations plaintiff knew and understood, were adopted and made a part of the said agreement entered into between these defendants and plaintiff herein, except that these defendants were to pay plaintiff the sum of 40 cents per cubic yard for material removed in the course of said work, and that said work so undertaken by plaintiff was to be completed by November 15, 1913. ’ ’
Defendants denied that plaintiff had removed the amount of dry material claimed by him, and averred that he had removed only 5,140.1 cubic yards of dry material, and further averred that he had removed no wet material at all as defined by the
The defendants were subcontractors under the contractors’ names in their answer and they in turn sublet the work in question here to the plaintiff. A trial to a jury resulted in a •verdict for the plaintiff in the sum of $1,135.78 on the first cause of action, and nothing on the second cause of action. Judgment was entered in accordance with the verdict, and the defendants appeal.
While defendants’ counsel have assigned a large number of errors, yet in their brief they have grouped them all under a few heads. We shall consider only those assignments which are deemed material.
“Now, this offer which is now made 'of certain matters in the document marked for identification as ‘Defendants’ Exhibit 16, ’ in the first place, could not bind the plaintiff in this case, because it could not be considered as an admission. There is an entirely different privy between the parties to this document and the parties in this action, and then the record further discloses that this witness did not read this contract and does not know what it contains. The objection is sustained.”
From what he did say it is quite clear that the ruling is erroneous according to the most elementary principles of law. Quite true plaintiff could not be bound by the terms and conditions of contracts made between others with whom he was not in privity, but the defendants by their offer did not seek to so bind him. All they attempted to do was to establish the terms of plaintiff’s own contract as the defendants claimed them to be, and thus bind him by those terms if the jury should find them to be as contended by the defendants. In order to so bind the plaintiff, the defendants were required to prove at least two things: (1) What the terms, condi
“You needn’t explain to me those conditions. I bid on this work and I understand what they are. ”
That evidence was, however, without effect as long as the defendants were not permitted to show what the terms and conditions of the contracts were to which they had referred in their answer and which, they contended, were adopted by the plaintiff and the defendants. The court, therefore, committed manifest error in excluding the defendants’ proffered evidence by which they sought to prove the terms, conditions, and stipulations of the contracts referred to in the answer.
‘ ‘ The exclusion of this evidence did not. prevent defendants, however, from proving their theory of the contract and of the yardage involved. ’ ’
That is quite true, but defendants had the right to establish those facts by any competent and material evidence at their command. That right was denied them. We cannot say what conclusion the jury might have reached if the excluded evidence had been admitted. We think, therefore, that the trial court was clearly in error in excluding defendants’ proffered evidence, and that the error was prejudicial to the substantial rights of the defendants.
It is next insisted that the court erred in permitting the plaintiff to recover for removing wet material which it is
The next assignment arises as follows: At the trial'the plaintiff claimed that he was entitled to a large sum, to wit, $1,500, for having removed material not contemplated under his original contract entered into with the defendants. In the original contracts made by the railroad company the sides or banks of the cut plaintiff was to excavate under his contract were to be made or left vertical. He, however, insisted that in doing the work the banks “sloughed” to such an extent that it was necessary for him to remove a large amount of material not originally contemplated; that he saw the defendants about it, and that it was agreed between him and the defendants that he should receive pay as though he had in fact constructed the sides of the cut to a “one to one slopé,” which would be at an angle of forty-five degrees; that while he did not in fact make such a slope, yet the cut should be measured as though he had constructed the sides in that way. The defendants denied plaintiff’s contention, and insisted that he was to receive pay only for vertical sides. Ordinarily the question whether plaintiff’s contention should prevail or not would, as a matter of course, be one for the jury. Defendants ’ counsel, however, insist that the court erred in submitting that question to the jury for the reasons: (1) That there was no consideration for the alleged agreement to pay for a one to one slope; and (2) that no such an agreement was pleaded, and hence no issue of that character was presented.
“But wliere the party refusing to complete his contract does so by reason of some unforeseen and substantial difficulties in the performance of the contract, which were not known or anticipated by the parties when the contract was entered into, and which cast upon him an additional burden not contemplated by the parties, and the opposite party promises him extra pay or benefits if he will complete his contract, and he so promises, the promise to pay is supported by a valid consideration. In such a case the natural inference arising from the transaction, if unmodified by any equitable considerations, is rebutted, and the presumption arises that by the voluntary and mutual promises of the parties their respective rights and obligations under the original contract are waived, and those of the new or modified contract substituted for them. Cases of this character form an exception to the general rule that a promise to do that which a party is already legally bound to do is not a sufficient consideration to support a promise by the other party to the contract to give the former an additional compensation or benefit. 1 Whárt. Cont., Section 500.”
What we have said sufficiently covers all other assignments, including those relating to the instructions. All those assignments are covered by the same general principles we have discussed, and of course will not occur again. Moreover, the instructions were erroneous only because they were in harmony with the trial court’s rulings upon the evidence which we have already passed on. All such errors will therefore necessarily be avoided upon a retrial of the case.
For the reasons stated herein, the judgment is reversed, and the case is remanded to the district court of Utah County, with directions to grant a new trial. It is further ordered that the court may make such orders with regard to amendments of the pleadings by either party as he may deem just and proper. Costs to appellants.