51 So. 874 | Ala. | 1909
Appellee sued appellant on the common counts, for work and labor done, and material furnished in remodeling and improving a residence. The defendant pleaded the general issue, and several special pleas of recoupment and set-off as per the contract under which the work was done and the material furnished. The contract set forth in the special pleas, and conceded to be the one under which the work was done, was as follows :J
“State of Alabama, County of Mobile.
“This instrument made and entered into by and between Peter J. Hamilton, as agent for Georgia K. Gage, of the first part, and Edward G. Fike, of the second part witnesseth: That for mutual consideration said parties do contract together as follows:
“(2) Said Hamilton agrees to pay said Fike for such work the sum of four thousand, nine hundred and thirteen dollars, on proper certificates of the architect, in instalments as follows: On Saturdays up to fifteen per cent of materials delivered and work performed not to exceed one thousand two hundred and fifty dollars in the first thirty days.
“(3) Said work is to be completed and the building turned over to said Hamilton, or his principal, on or before the 20th day of December, 1906. Should said building not be turned over complete, said Hamilton may retain out of the compensation hereinabove provided for the sum of ten dollars a day until the building is so turned over, delays beyond contractor’s control excepted.
“(4) Said work is to be superintended and under the direction of Willis B. Diggers, or such other architect as said Hamilton may designate.
“Witness our hands and seals in duplicate at Mobile, this first day of Sept., 1906.
“(Signed) E. G. Fike, (Seal.)
“P. J. Hamilton, (Seal.)
“Agent for Ga. K. Gage.”
“Signed, sealed, and delivered in the presence of: (Corrections before execution.) A. L. Staats.”
This court, among others, has announced some rules or laws of construction applicable to such stipulations in contracts. In Hooper’s Case, 69 Ala. 343, the court, through Brickell, O. J., said: “In the determination of this question, as in the determination of all other questions touching the construction of contracts, the gov: erning guides are the subject of the contract and-tne intention of the parties. Considering this particular question, said Chief Justice Collier in Watts v. Sheppard, 2 Ala. 434: ‘The first general principle in the construction of all contracts is that they shall be so expounded as to carry into effect the intention of the parties. To this end, the court should, if necessary, look to the subject-matter of the contract, the situation of the parties, the motives that led to it, and the objects intended to be attained by it.’ Among principles well established in determining whether a stipulation or covenant of the character now under consideration is in its nature a penalty or liquidated damages the first is that it is the tendency and preference of the law to
If, from the nature of the contract, the damages for the breach cannot he calculated with any degree of certainty, a stipulated sum will usually be held to be liquidated damages — that is, it will be considered that the parties agreed in advance upon the amount, and it will
It seems that in this particular case the parties agreed that the work should be completed within a particular time, time being to this extent a material part, if not the essence, of the contract, that a gross sum dis
Taking all things into consideration, it seems to us that the manifest intention of the parties to this contract was not to leave the amount of the damages for the delay in the completion of the work to uncertainty or to the estimate of the jury, but that they intended to fix, and did thereby fix, what they considered a reasonable amount for the delay, and fixed it at so much per day, so that the parties could thereby protect themselves by completing as soon as possible or as practicable.
It may be that, for aught we can know, it might have been to the interest of the builder to delay a few days, to pay this finally, rather than to go to the necessary cost and expense of completing it within the time. The losses that the owner may have sustained by reason oí the failure to complete within the time agreed upon are so uncertain, and the advantage that may have accrued
It therefore follows that the trial court erred in refusing the requested charges of the defendant, which authorized a finding in accordance with this construction of the contract and with the issues and the evidence. It clearly appears that the jury did nor allow the damages agreed upon between the parties as ■damages for the delay.
There was no error in declining to allow proof of the matter sought to be proven by the defendant, to wit, that a certain witness saw the house on a certain occasion and that it was not the habitat. If this was relevant for any purpose, it is not made to so appear by the bill of exceptions.
The judgment is reversed, and the cause is remanded.
Reversed and remanded.