77 So. 2d 697 | Miss. | 1955
This case is before us on appeal by Sam Strangi, complainant, from a decree of the Chancery Court of Jackson County establishing the order of priorities of the
The record shows that during the summer of 1950 Frank Haviland and Eose Mary D. Haviland, his wife, agreed to convey to William C. Wilson the land described as Lots 6 and 17 of the Edgewater Court Subdivision of the City of Ocean Springs, for the sum of $1,150. Wilson was a member of the armed forces of the United States at that time and was stationed at Keesler Field near the City of Biloxi; and after making arrangements for the purchase of the lots Wilson applied through William E. Barber of G-ulfport for a Veterans Administration loan to enable him to purchase the lots and construct the dwelling house. A tentative approval of the loan for the sum of $8,800 was obtained. The value of the lot on which the building was to be located was fixed at $1,000. Wilson was to provide the sum of $1,200 in cash to be applied to the payment of the construction cost of the building which was not to exceed the sum of $9,000. Wilson then entered into a contract or agreement with Gr. A. Marshall, doing business as The Marshall Engineering-Company, for the construction of a dwelling house on Lot 6 for the sum of $9,000.
After work had been started on the building, Joe Walsh, Marshall’s foreman, learned that the Marshall Engineering Company would be unable to obtain a temporary loan for the financing of the project through William E. Barber; and Walsh approached the appellant, Sam Strangi, who operated a lumber yard in the City of Biloxi, for the purpose of having Strangi advance the necessary funds to defray the balance of the construction cost. Strangi agreed to finance the construction cost in an amount not to exceed $7,500 upon the condition that Wilson and his wife execute a note for that amount and a mortgage deed of trust on the lot on which the build
After tbe note and deed of trust bad been executed, Strangi furnished building materials, upon Walsh’s orders, and also money which was used in paying for labor on tbe job, and tbe work on tbe building proceeded without interruption. Strangi’s bills for lumber and other building materials amounted to $3,106.59. The sums advanced by him for labor amounted to $4,487.08, making a total advancement of materials and money in tbe sum of $7,593.67.
Tbe building was completed during tbe month of July, and at that time Strangi learned that there were claims due and owing by Marshall to other materialmen in tbe total amount of $2,916.56.
The $7,500 note signed by Wilson and his wife and payable to Strangi became due ninety days after date, and Strangi being unable to foreclose bis deed of trust, because tbe legal title to tbe lot was still vested in tbe Havilands, filed bis bill in tbe Chancery Court for tbe purpose of having tbe property subjected to tbe payment of the mortgage indebtedness due and owing to him. W. C. Wilson and bis wife, Frank Haviland and his wife, G-. A. Marshall, and William R. Barber, who had been named as trustee in tbe above mentioned mortgage deed of trust, and tbe above mentioned materialmen were named as parties defendant. Tbe complainant in bis bill asked that the deed of trust executed by Wilson and his wife to secure tbe payment of said note be held to constitute a first lien upon said Lot 6 of tbe Edgewater Court Subdivision, together with tbe improvements thereon, except as to the amount due Frank Haviland on tbe purchase price of tbe lot; and tbe complainant asked, that tbe legal title to tbe property be divested out of tbe
The Wilsons in their answer admitted that they had entered into a contract with Marshall for the construction-of a dwelling house on the lot which the Havilands had agreed to convey to them, and that they had executed the note and mortgage deed of trust to Strangi, copies of which were attached to the bill of complaint. But the Wilsons in their answer denied that they were liable for the payment of the $7,500 note for the reason that the note and deed of trust were conditionally delivered upon the premise that the building would be constructed and approved by the Veterans Administration and that a G.I. loan would be made “which contingency was prevented from occurring by the deliberate act of the complainant, Sam Strangi, in filing this suit.”
The Wilsons made their answer a cross bill, and in their cross bill alleged that they had contracted with Marshall for the construction of the dwelling house for the sum of $9,000, that they had paid to Marshall the sum of $1,200, and that the balance which they owed to Marshall was $7,800; that the materialmen named in the original bill as codefendants had dealt directly with Marshall and had not given the required notice of their claims to the cross-complainants and were not entitled to a lien of any kind upon the property. The cross-complainants asked that their total liability to Strangi and the other materialmen be limited to the $7,800, and that the court determine the rights of priority between Strangi and the
The materialmen, who had been named as parties defendant, filed their petitions of intervention under the materialmen’s lien statute. The cause was heard by the chancellor on the pleadings and proof, and at the conclusion of the testimony the chancellor incorporated in his decree his findings of fact and his conclusions of law.
The chancellor found that Marshall had agreed to construct the house fo(r Wilson for the sum of $9,000; and that Wilson had paid to Marshall during the months of January and February, 1951, the sum of $1,200 on the contract price, leaving a balance of $7,800 to be paid. The chancellor found that after Marshall’s foreman had failed in his effort to obtain temporary financing of the project through William R. Barber, Strangi agreed to finance the balance of the construction cost of the building, not to exceed the sum of $7,500, provided Wilson and his wife would execute and deliver to him a note for that amount and a mortgage deed of trust on the property to secure the payment of same; and that Wilson and his wife executed the note and the mortgage deed of trust on February 17,1951. The chancellor found that Strangi thereafter advanced to Marshall money for the payment of labor in the total sum of $4,487.08 (which included the sum of $203, for which check was issued on February 17, 1951), and building materials in the additional sum of $3,106.59, making a total of $7,593.67, and the chancellor found that, but for the financing of the project by Strangi, the house would not have been completed.
The chancellor also found that the other materialmen named in the original bill of complaint had furnished materials and services for which they had not been paid in amounts as follows: Saucier Brothers, $498.28; Rhodes
The chancellor found that Haviland and his wife resided on the land adjacent to the lot on which the dwelling house had been constructed; that they were familiar with the agreement that Wilson had entered into with Marshall for the construction of the dwelling house on Lot 6, and that they knew of the efforts that were being made to finance the construction of the dwelling house and had endeavored to assist Wilson in obtaining a loan; and that they had stated in open court that they intended to convey to Wilson Lots 6 and 17 for the price of $1,150, notwithstanding the agreement dated March 1, 1951, which had been executed long after the construction work on the dwelling house had begun; and the chancellor held that, in view of the above mentioned facts, they should be estopped from doing otherwise, and that they should be compelled to execute a conveyance of said lots to Wilson for the sum of $1,150, and that they should be given a lien on the property to secure the payment of said purchase price.
The chancellor held that the. deed of trust and the note executed by Wilson and his wife to Strangi should be set aside and cancelled, “for the reason the conditions and circumstances under which they were executed were not such as to meet the legal requirements of valid and binding obligations.” The chancellor held that out of the $7,800 due Marshall under the contract Strangi should be paid the sum of $4,284.08 as a reimbursement for the amounts advanced by him after February 17, 1951, for the payment of labor on the job, and that the balance of the $7,800 should be distributed pro rata among Strangi and the other materialmen and subcontractors.
From the above mentioned decree Sam Strangi, the complainant and cross-defendant, has prosecuted this appeal; and Naif Jordan, doing business as Back Bay Lumber and Box Factory, Saucier Brothers, Gr. H. Bhodes, doing business as Bhodes Floor Covering, and the City Lumber & Supply Company, materialmen, have filed cross-assignments of error.
The main points argued by the appellant’s attorneys as ground for reversal on this appeal are that the court erred in holding that the $7,500 note and mortgage deed
The main point argued by the cross-appellants’ attorneys in support of their cross-appeal is that the court erred in holding that the cross-appellee’s claim for the sum of $4,284.08, which represented the amount advanced by the cross-appellee for the payment of labor, was entitled to priority over the claims of the materialmen and subcontractors, and in directing that the said sum of $4,284.08 be paid to the cross-appellee before any payment should be made to the cross-appellants.
In as much as our decision on these points will dispose of most of the other questions involved in this appeal, we shall discuss these points first.
We think that the chancellor erred in holding that the $7,500 note and mortgage deed of trust executed by W. C. Wilson and his wife to Sam Strangi on February 17,1951, should be set aside and cancelled, “for the reason the conditions and circumstances under which they were executed were not such as to meet the legal requirements of valid and binding obligations.” We are unable to determine from the decree itself what the conditions and circumstances were which in the chancellor’s opinion rendered the note and deed of trust invalid; and the record, we think, fails to disclose any
It is true that the deed of trust was not recorded until July 30, 1951; but the delay in recording the deed of trust did not affect its validity or the binding force of the obligation as between the parties to the instrument.
It is also true that Wilson and his wife averred in their answer that there was no consideration for the execution of the note and deed of trust. But there is no merit in this contention. The proof showed conclusively, and the chancellor found, that Strangi refused to advance the $7,500 for the payment of labor and material to enable the contractor to proceed with the construction of the building, unless Wilson and his wife would agree to bind themselves for the repayment of such advancements and secure the same by a mortgage deed of trust on the property. Strangi advanced the above mentioned sum of $4,487.08 in money for the payment of labor, and in addition thereto building materials of the value of $3,106.59. All of the advancements of building materials with the exception of building materials of the value of $378.95 delivered prior to February 17, 1951, were made in reliance upon the note and deed of trust executed by Wilson and his wife, and after receiving the benefit of the transaction the Wilsons are not in a position to assert that they are not bound by the obligation which they assumed to enable Marshall to complete the work on the house.
It is also argued, however, on behalf of some of the materialmen, that the chancellor was justified in holding that the deed of trust was invalid for the reason that the legal title to the lot on which the building was located was still vested in Frank Haviland and his wife, and that the Wilsons had no title to the property and could convey no title to the trustee. But the proof showed, and the chancellor found, as we have already stated,
Haviland and his wife were not only estopped from refusing to carry out their agreement to convey Lots 6 and 17 to Wilson for the sum of $1,150, as the chancellor stated; but they were also estopped from asserting their title against Wilson’s mortgagee.
“Where the owner of land knowingly stands by and permits his property to be mortgaged or sold by another to one who is, to the owner’s knowledge, relying on the apparent ownership of the person executing the conveyance, such conduct, irrespective of who benefits by the transaction, will estop the owner from asserting his title against the mortgagee or grantee. ’ ’ 19 Am. Jur., p. 748, Estoppel, par. 91.
But the Havilands were entitled to a purchase money lien on the lots to secure the payment of the purchase price of $1,150; and the chancellor very properly recognized the superiority of that lien over the lien of Strangi’s deed of trust and expressly provided in his decree that, in the event the property should be sold to satisfy the claims of the creditors, the $1,150 owing by Wilson to them should be paid out of the proceeds of the sale before any of the funds were applied to the payment of the other indebtedness.
So far as the Wilsons are concerned, they are in no position to deny the equitable title conveyed by them to the trustee in the deed of trust executed to secure the payment of the $7,500 note due and owing to Strangi. The Wilsons are estopped by their own deed from denying the title to the lot conveyed by them to the trustee. 19 Am. Jur., p. 606, Estoppel, par. 10; Meyers v. American Oil Co., 192 Miss. 180, 5 So. 2d 218; Perkins v. White, 208 Miss. 157, 43 So. 2d 897;
In the case of Meyers v. American Oil Company, supra, the Court said: “Nothing is better settled in this state than the rule that the grantor and all persons in privity with him shall be estopped from ever afterwards denying that, at the time his deed of conveyance was executed, he was seized of the property which his deed purported to convey, and that mortgages and deeds of trust are within this rule. By statute, Sec. 2125, Code of 1930, the rule is extended even to quitclaim deeds. The effect of this doctrine of estoppel by deed is the same as if in the deed itself, or in the mortgage, there had been inserted with valid force the express provision that it then and there conveyed not only the title then possessed by the grantor in the property therein described, but all that he might thereafter acquire. ’ ’
The deed of trust executed by Wilson and his wife to Strangi to secure the $7,500 note was not void, even though the legal title to the lot had not been conveyed to Wilson at the time of the execution of the deed of trust; and Strangi had a right to invoke the aid of a court of equity to subject the property to the payment of the indebtedness due and owing to him.
We think that the chancellor erred in holding that the note and the mortgage deed of trust given to secure the payment of same should be cancelled, and in refusing to permit the appellant to recover the full amount of the note, with interest and attorney’s fee.
It is true that the chancellor found that Wilson had a contract with Marshall for the construction of the house for $9,000, and that Wilson had paid to Marshall $1,200, leaving a balance due of only $7,800, and that when the interest and attorney’s fee are added to the principal of the $7,500 note the total amount of the mortgage indebtedness due and owing to Strangi will exceed the $7,800. But Strangi’s suit against the Wilsons
We come now to a consideration of the claims of the subcontractors and other materialmen, who were named as codefendants in the original bill of complaint, and who have filed cross-assignments of error on this appeal. The main contention of their attorneys is that their claims should have priority over the claim of the appellant, Strangi, for the reason, first, that the appellant’s deed of trust was not filed for record until after the job was completed and the lien of the appellant’s deed of trust did not become effective as to innocent third parties until the deed of trust was filed for record; and, second, that the appellant, Strangi advanced money to the contractor Marshall and was therefore not entitled to a statutory lien under the rule laid down in Sadler v. Glenn, 190 Miss. 112, 199 So. 305.
Both of these contentions are in our opinion unsound.
When Wilson executed his promissory note for the sum of $7,500 and the mortgage deed of trust on the property to secure the payment of same, for the purpose of having Strangi advance money to the contractor for the payment of labor and materials to be used in the construction of the building in the sum of $7,500 and
In the case of Lake v. Brannin, supra, the Court held that, where the owner had employed a firm of carpenters to make certain improvements on his residence for a stipulated price, and long prior to the time at which written notice was served on him by the appellees of any claim that they had against the contractors, such owner had obligated himself and became indebted to other materialmen for materials furnished by them which it was the duty of the contractors to supply, the amount due the contractors under the contract with the owner, which might be subjected to the payment of the appellees’ claims, was necessarily reduced in amount by whatever sum the materials that had been obtained from such other materialmen amounted to.
In Chancellor et al. v. Melvin et al., supra, the Court said:
“In the absence of a statutory provision to the contrary, the owner may make payment to his principal contractor in any method and at any time they agree upon. Rockel, Mechanics’ Liens (1909), Sec. 67; 57 C. J. S., Mechanics’ Liens, Section 251. There are numerous cases in which the owner was held to have paid his contractor by giving him in good faith a promissory note for the amount due on the contract, even though the note was not paid until after stop notices had been given to the owner. McGranahan Lumber Co. v. Pyramid Asbestos & Roofing Co., Tex. Civ. App. 1929, 18 S. W. (2d) 224; Cramer v. Dallas Lumber Co., Tex. Civ. App. 1926, 283 S. W. 596; George E. Sealy Co. v. Ards Build*143 ing Corp., 1926, 216 App. Div. 313, 214 N. Y. S. 768, affirmed in 1927, 244 N. Y. 505, 155 N. E. 899.”
The claims of the subcontractors and other materialmen were claims against G. A. Marshall, the contractor. None of those parties dealt directly with Wilson, the owner. None of them gave notice in writing to Wilson of their claims against Marshall or took any action under Section 372, Code of 1942, until after this suit was filed. But, if such notices had been given before the house was finished, such notices would have been effective to bind Wilson for no greater amount than the amount due Marshall at the time the notices were given. The record shows that Wilson had paid to Marshall the sum of $1,200, and that Wilson had executed the $7,500 note to Strangi for money and materials to be used by Marshall in the construction of the building. After crediting Wilson with these two amounts, the only amount remaining in the hands of Wilson that could be bound for the payment of the claims of the subcontractors and other materialmen was $300. The $300 had not been paid at the time this suit was filed, and the subcontractors and other materialmen were entitled to have that amount in the hands of Wilson subjected to the payment of their claims.
The rule applied by the Court in Sadler v. Glenn, supra, which is cited in the briefs of the cross-appellants, has no application to the facts in this case. In that case Sadler had no dealings with White, the owner of the property, relative to the advancements of money which he agreed to make to Glenn, the contractor, to enable Glenn to pay for laborers, and White assumed no obligation to reimburse Sadler for the advancements made by Sadler to Glenn. In this case Strangi dealt directly with Wilson, the owner. Strangi declined to make the advancements of money and building materials to Marshall, unless Wilson and his wife obligated themselves directly for the payment of the $7,500.
In the event the property should be sold for the payment of the mortgage indebtedness due and owing to Strangi, the claim of Strangi for the principal sum of $7,500 should be given priority over the claims of the subcontractors and other materialmen for the $300 balance due and owing by Wilson under his contract with Marshall; but after the payment of the $7,500 principal due and owing to Strangi, the claims of the subcontractors and other materialmen for the $300 bal
Reversed and remanded.