119 Va. 271 | Va. | 1916
delivered the opinion of the court.
The declaration contains but one count, and plaintiff’s cause of action as set out is that, by reason of the alleged mining out of the coal in, under and upon two certain tracts of land, the surface of which was owned by the plaintiff, to-wit: the J. A. Dotson tract and that part of a tract conveyed to the plaintiff by Hans-ford Gilliam which lies west of a certain road, called the Birchfield road, and the failure of the defendant, in so mining and removing said coal, to leave blocks, stumps or pillars of coal, or some other adequate or sufficient means of support for said overlying surface, the strata of rock overlying the said coal were cracked and broken, and large bodies of it fell and large cracks, fissures, and holes were left in said overlying surface, by reason whereof the surface of said land had been left unsafe and of little value for agricultural or other purposes, and all of the springs, streams and other water supplying the said lands were drained, sunken, diverted and wholly destroyed, etc.
The defendant filed its demurrer to the declaration, which the court overruled, and at the trial of the case upon its merits there was a verdict for the plaintiff, assessing his damages at the sum of $1,000, which the court refused to set aside and entered judgment thereon, to which judgment this writ of error was awarded the defendant.
The first assignment of error is to the action of the
We are of opinion, however, that the demurrer should have been overruled. The best pleading, as this court has repeatedly held, is that which states facts and not conclusions of law, leaving no need for conjecture as to any fact upon which the right of recovery is based. Section 3246 of the Code of 1904 provides that no action shall abate for want of form, where the declaration sets forth sufficient matter of substance for the court to proceed upon the merits of the cause; and section 3272 provides that on a demurrer (unless it be to a plea in abatement)- the court shall not regard any defect or imperfection in the declaration or pleadings, whether it has been deemed mispleading or insufficient pleading or not, unless there be omitted something so essential to the action or defense that judgment, according to law and the very right of the case, cannot be given.
In the instant case the words in the declaration, “of a plea of trespass,” without stating whether it was trespass on the case, or trespass vi et, armis, could not affect the real character of the declaration, which is really, by the facts alleged, a declaration in trespass on the ease, setting forth sufficient matter of substance for the court, to proceed upon the merits of the cause.
The distinction between trespass vi et armis and trespass on the case is very clearly drawn in 4 Min. Inst, p. 436, and the distinction between the two actions appears to be so nice and useless that both the courts
In the more recent cases this rule, stated in somewhat different phraseology, though in substance the same, is declared to be that a declaration is sufficient if it informs the defendant of the nature of the demand made against him, and states such facts as will enable the court to say that if the facts are proved, as alleged, they establish a good cause of action. Va., &c. Wheel Co. v. Harris, 103 Va. 708, 49 S. E., 991, and authorities cited.
By successive conveyances the plaintiff, prior to the grievances for which he sues in this action became the owner of the surface of two tracts of land-—-the J. A. Dotson tract and the Hansford Gilliam tract—formerly constituting one tract, • and the several conveyances which form the chain of title in the plaintiff to the surface of each tract, recognized and preserved in and as belonging to O. M. Vicars the benefits of the following reservation and exception contained-in a deed from said O. M. Vicars and wife to Milburn Gilliam, dated the 16th day of May, 1901, to-wit: “But there is excepted and reserved from the operation of this conveyance all the coal in, under and upon said tract of land, and the right and privileges of the said parties of the first part, their heirs and assigns to enter upon said tract of land and excavate and mine, prepare for market and remove said coal with all the usual mining privileges
At the same term of the court—January, 1913— the defendant filed in writing its several grounds of defense to the action, which, besides the defenses under the plea of the general issue and the three and five years statutes of limitations, were that the defendant, in mining the coal under the said J. A. Dotson tract of land, did not exceed its rights under the grant or reservation of the coal under which said mining was done; that the alleged loss of the spring on the J. A. Dotson tract of land did not occur by reason of any mining done by the defendant at any time of the coal in and under the said land; and that in any mining done by the defendant of the coal under the said J. A. Dotson tract, the defendant never interfered with any water upon the same, unless it be subterranean waters, or mere percolating veins thereof, oozing or percolating through the soil and sub-strata of the land or natural cracks in the stone or earth over said coal, or other causes incident to the mining of said coal, for which the defendant was not liable.
During the progress of the trial many exceptions were taken by the defendant to the rulings of the court in the admission and rejection of evidence, giving, refusing or modifying instructions, and to its refusal to set aside the verdict because contrary to the law and the evidence. These exceptions, twenty-four in number, are made the basis of twenty-three of the
It appears that the defendant, as the lessee of O. M. Vicars and one J. J. Kelly, Jr., for many years prior to June, 1910, had been mining coal under the Hansford Gilliam and J. A. Dotson tracts of land, and also under several adjoining tracts, and the mining was continued on the Gilliam and Dotson tracts after June 30, 1910, in fact until into the year 1913. The spring on the Gilliam tract, it appears, went dry not later than in the spring of 1906, the coal under which and for 250 feet from it was not taken out till much later; and the spring on the Dotson tract went dry about the first of June, 1910, at which time, as defendant claims, there had been left three pillars of coal in the vicinity thereof and under the same, one 50 feet long by 20 feet wide, another (directly under the spring) 30 by 30, another 30 by 70 and still another 50 by 200 feet.
It is to be observed from his declaration and the bill of particulars filed therewith, that the plaintiff rests his claim to damages, in this action upon the failure of the defendant, in mining and removing the coal in question, to leave, adequate or sufficient means of support for the overlying surface thereof, and that by reason of such failure or neglect, the stratum of rock, etc., overlying the coal was cracked and holes were left in said overlying surface, causing it to be un
There is no evidence in the record tending to prove that the cracks, gaps and fissures in the surface overlying the coal, alleged to have been caused by the mining out of the coal, had extended through to the top or face of this surface, so that the drying up of the spring on the Dotson tract and the resultant injuries to plaintiff’s, lands, the Dotson and Gilliam tracts, by reason of the loss of the water theretofore supplied by the spring on the Dotson tract were the only damages that the evidence tended to prove. Of course the plaintiff contended that the drying up of the spring on the Dotson tract and the resultant injuries to that tract and the Gilliam tract were caused by the defendant mining out the underlying coal in disregard of his right to subjacent support of the overlying surface. Whether the evidence and the inferences to be drawn therefrom sustained this contention involved questions of fact for determination by the jury under proper instructions from the court as to the law applicable to the case.
This brings us, though rather in inverse order of the assignments of error, to assignments 19 to 23 inclusive, relating to the rulings of the trial court in giving, refusing and modifying instructions.
The defendant, plaintiff in error here, does not, as its contention is understood by us, controvert the doctrine of subjacent support as established by the courts of both England and America, and sustained by practically all of the text-writers in both countries, resting the doctrine upon the ground that there were the same reasons for it that there were to maintain the right to
It is further urged by the learned counsel for the defendant that the terms used in the conveyance in this case, wherein the coal was granted, reserved or excepted, together with the “usual mining privileges,” the right to enter upon the lands “above described and excavate, mine, prepare for market, and remove said coal; together with all the usual mining privileges,” and the rights “to pass to and under said land for the purpose of mining and removing any other coal of the party of the second part, his heirs, assigns or vendees, which he now owns or may hereafter acquire, on or under any other land,” are the same terms employed in the deed under consideration in the case of Griffin v. Fairmont Coal Co., 59 W. Va. p. 480, 2 L. R. A. 1115, 53 S. E. 24, where, by a divided court, it was held: “The vendor of land may sell and convey his coal, and grant to the vendee the right to enter upon and under said land, and to mine, excavate, and remove all the coal purchased and paid for by him; and, if the removal of the coal necessarily causes the surface to subside or break, the grantor cannot be heard to complain thereof.
“Where a deed conveys the coal under a tract of land, together with the right to enter upon and under said land, and to mine, excavate, and remove all of it,
The opinion in that ease by Cox, J., in which the majority of the court concurred, adopts in part an opinion written by Judge Mason who decided the case in the circuit court,- but expressly states that while the court agrees with the conclusion of Judge Mason and with much of his reasoning, they disagreed with him in two important particulars, namely: (1) “We do not agree that the additional grant contained in the deed of the right to enter upon and under said land and to mine, excavate and remove all the coal, adds nothing to the legal effect of the déed.” (2) “We in no sense question the doctrine or right of subjacent support in a case where the surface and subjacent estate are owned by different persons, and the right of support has in. no way been parted with or waived by the surface owner.” This comment was doubtless deemed necessary by reason of the fact that in the opinion by Judge Mason he took the view that the word “all” in the clause which gave the defendant the right to enter upon the land and remove “all” the coal was superfluous and added nothing to the force of the conveyance, for the reason that the right of subjacent support can arise only by express agreement in the instrument creating the severance, and does not exist as a natural right. The opinion of the appellate court, therefore, recognizes the right of the surface owner to subjacent support until he parts with or waives it, and concedes that the plaintiff in that case would have been entitled to support of his surface land, but for the language of the granting clause in the conveyance under which he claimed being sufficient
1. “I cannot see how, against every rule of construction, where a deed has been made by the owner of the fee granting in express terms all the subjacent strata or estate, that the right of subjacent support may be based upon the ground that there is a presumption or implied reservation by such deed, in which there is no express limitation, reservation or exception, and in derogation of the express terms of the grant of so much of the subjacent strata or. estate, to the extent of all, if necessary, to support the overlying surface.”
2. “The plaintiff granted all the coal, and the ownership of the surface and of the underlying coal was severed, creating a separate estate in each. If the deed said nothing more the Owner of each would be bound by the rule sic utere, etc. If the deed said nothing more, I would, without hesitation, hold that the owner of the surface would be entitled to support, and that the owner of the coal could not so use it, by removing all of it, as to injure the surface. The deed does not stop with the grant of all the coal. It contains the express additional grant on the part of the plaintiff to the grantee of the right to enter upon and under said land, and to mine, excavate and remove all of said coal.”
The opinion further says: “I think there is a vast difference between a grant of all the coal simply and a grant of all the coal with the right’ to enter upon and under the land and remove all of it. Without the right to remove all, the owner of the coal may not do so, if to do so would injure the surface.”
The argument followed in the opinion throughout- is
Unquestionably the ground upon which the court’s decision in the case rested was that the word “all” in the grant of the coal, together with the right to enter, etc., and “remove all of it,” gave the conveyance under consideration additional force, for the opinion by Cox, J., which is made the court’s opinion, says: “I have no quarrel with the doctrine of subjacent support, when it has not been parted with, applicable where the surface and subjacent estate in the same land are owned by different persons. I do not condemn or question what I deem the best cases and text-books expounding the doctrine.”
Even if it could be conceded in the instant case that the terms employed in the conveyance under consideration are the same as those employed in the conveyance construed in the case we. have just cited and quoted from, we could not follow either the reasoning or the ruling in that ease, for which ruling the court did not cite a single well considered case as sustaining it. On the other hand the decided cases to which we have adverted, both English and American, and the text-books written by the most eminent law writers, concur in holding that the right of subjacent support is not waived by the sale of all the coal with the right to mine and remove it, or the sale of the surface reserving the coal with the right to mine and remove it. Not only so, but the decision of the court in Griffin v. Fairmont Coal Co., supra, based as the opinion indi
In the last named case the court says: “And it is well settled that the grant of the surface with a reservation of the minerals and the right to extract the same does not permit the destruction of the surface, unless the right to do so has been expressed in terms so plain as to admit of no doubt.”
In 2 Devlin on Real Estate, sec. 979, the author, after stating that a reservation to create an estate must use apt words, and that it is to be construed most strongly against the grantor, says: “A reservation of all minerals or of the right of mining must always respect the surface rights of support. The surface is not to be destroyed without some additional authority.”
The rule is stated in 1 Ruling Case Law, at p. 396 thus: “While the presumption is in favor of the right to support, no particular words are necessary to show its surrender.
“But an absolute right to surface support is not to be taken away by mere implication from language which does not necessarily import' such a result. Therefore a grant of minerals by the owner of the soil
“And likewise, when the owner grants the surface of the land, reserving to himself the right to the minerals, he cannot in excavating for the minerals, let down the surface of the soil, unless the reservation is so framed as to clearly give the grantor the right to let down the soil.”
In 27 Cyc. pp. 789-90, citing a large number of au-. thorities to support the text, it is said, that where one grants the minerals under the surface with the privilege of mining such minerals, the support of the surface is a part of the estate reserved in the grantor; while on the other hand if one sells the surface reserving the minerals, the grantor in removing the minerals reserved, must leave or provide sufficient support for the surface to prevent its subsidence, unless, in either case, there is some additional statutory or unequivocal contract authority therefor. See also Williams v. Hay, 120 Pa. 485, 6 Am. St. 379; Collins v. Gleason, 140 Iowa, 114, 115 N. W. 497, 118 N. W. 36, 18 L. R. A. (N. S.) 736; Blanchard & Weeks’ Notes to Jones v. Wagner, Leading Cases on Mines, p. 617; Barringer & Adams on Law on Mines, p. 676; 18 Am. & Eng. Enc. L. 557; Cooley on Torts, p. 707; Youghiogheny R. Coal Co. v. Alleghany Natl. Bank, 211 Pa. 319, 60 Atl. 924, 69 L. R. A. 637.
In the last named case the direct question was presented in the determination of the rights of the parties under the following provision in their contract: “The said parties of the first part reserve all of the non-worked six-foot vein of stone coal, also the right and privilege for themselves, their heirs and assigns of digging, mining and carrying away said stone coal.”
In Horner v. Watson, 79 Pa. 242, 21 Am. St. Rep. 55, the court construed a deed similar in its provisions to the one here under consideration and held that the surface owner had the right of support, the opinion saying: “When A grants B a tract of land reserving the minerals under it, the legal presumption is that B shall have and enjoy the exclusive and uninterrupted use of the surface, but if A may, notwithstanding, under the plea of the general custom, dig out the foundations of the land and let down the surface, or render it so dangerous that it cannot be used, it is clear that he may thus destroy his own grant and invalidate the rights with which the law clothes his own vendee.” See also Coleman v. Chadwick, 80 Pa. 81, 21 Am. Rep. 93.
We have been cited to no case that approves of the decision in Griffin v. Fairmont Coal Co., supra, but have been cited to a number of more recent decision, which disapprove of that decision, all of which are in line with the dissenting opinion in the case by Poffenbarger, J.,
A conveyance or the reservation of “all the coal” with the right to mine it, is, as was said, in the dissenting opinion in Griffin v. Fairmont Coal Co., supra, one and the same thing. “No talismanie influence is to be attributed to the word ‘all.’ The coal under a tract of land is precisely the same as ‘all the coal,’ and to attribute to the word ‘all’ any intensive force is a mere verbal criticism without effect, weight or influence. It is the sticking in the bark which always misses the marrow.” °
The reasoning running through all the authorities to which we have referred and to which very many more could be added is that when a grantor, as in this case, sells the surface of the land, he knows that the use of it for farming and other purposes is contemplated and assents thereto. He also is presumed to know that when all the coal is removed the overlying surface will sink unless supported, and if he desires to reserve rights inconsistent with the full enjoyment of the surface, it is his duty to reserve those rights by dear and unequivocal language. It is hardly to be supposed that either the grantor or the grantee in the conveyance we have under consideration for a moment contemplated the reservation of a right which would enable the grantor to totally destroy the subject matter of the conveyance, or at least render it largely useless.
Unquestionably, the dominant intent of the deed, and the purpose for which it was executed is that the grantee shall have the surface, with the right to its use and enjoyment modo et forma, while the grantor still owned the coal, with the right to mine and market it, but in the enjoyment of their respective rights each
It is to be observed that there was a diversion in the chain of title to the surface of the Dotson and the Gilliam tracts as a whole, which had reunited in the plaintiff before the sinking or drying up of the spring on the Dotson tract, and the claim plaintiff is making in this action is to damages which resulted not only to the Dotson land, but for damages resulting to the Gilliam land from the loss of the spring on the Dotson land.
There was evidence tending to prove damage to the Dotson land by reason of the drying up of the spring thereon, and counsel for the plaintiff do not contend that he is entitled to damages that resulted from defendant’s operating its mine, driving the regular entries, rooms and other usual excavations that it had a right to make, but seeks reparation for the unlawful, wrongful and injurious act of the defendant in withdrawing the surface supports to which the plaintiff was entitled, which it had no right to do; so that the crucial question of fact submitted to the jury for determination under the instructions of the court was whether or not the sinking or drying up of the spring on the Dotson land was caused by the failure of the defendant in mining
Plaintiff’s instruction No. 1, to which the defendant excepted, is as follows:
“The court instructs the jury that under the conveyances introduced in evidence' in this case, it was the duty of the defendant in mining and removing the coal under the tract of land known as the J. A. Dotson tract, to leave sufficient pillars, props or other means of support to prevent the strata overlying the coal from breaking and falling; and if they believe from the preponderance of the evidence that the defendant mined the coal in and under the plaintiff’s tract of land known as the Dotson tract, without leaving sufficient pillars, props or other means of support to prevent the strata overlying said coal from breaking and falling, and that as a result thereof the said strata was broken and the spring on the J. A. Dotson tract thereby drained and destroyed, they should find for the plaintiff such damages as he has sustained by reason of the draining of said spring.”
We have already disposed of the contention of the defendant that the doctrine announced in the case of Griffin v. Fairmont C. Co. supra, applies and controls this case. The further objection urged against instruction No. 1 is that it erroneously holds that the surface of a tract of land, which must be protected at all hazards, extends down to the very top of the underlying coal, including all strata over it, even slate and rock, that must be pulled down if accident to life and limb is to be avoided, whereas “surface” means that portion of the land which is or may be used for agricultural purposes. In other words, this contention, as we
Authorities are cited which say that the word “surface” when specifically used as a subject of conveyance means that portion of the land which is or may be used for agricultural purposes, but its meaning in any particular case must necessarily depend upon the intention of the parties as gathered from the language of the deed and the purpose of the conveyance, and according to the authorities the word “surface” may mean either the mere superficial or geometrical surface, the part of the soil used for agricultural purposes, or all of the strata except the minerals.
In Yandes v. Wright, 66 Ind. 319, 32 Am. Rep. 109, where the word “surface” was used in a conveyance creating a severance, the opinion of the court says: “It should be noticed through the cases above cited that the word surface, as used in the books, means not merely the geometrical superficies without thickness, but includes whatever earth, soil or land is above and superincumbent upon the mine.” See also Kansas
The authorities recognize that mining must interfere more or less with those subterranean streams and percolations of water which appear upon the surface as springs, and that to hold the owner of the substrata accountable for damages for their disturbance would be in effect to say that he could have no use of his minerals, for without interfering to some extent with such waters mining would be impossible; but they also recognize that there is a difference between water courses on the surface and those which run underground, and hold that the distinction does not authorize neighboring proprietors to disregard the necessities of each other’s condition in respect to the latter.' “It is manifest that valuable rights may exist in both; and it is indisputable that whenever they do exist they must be protected by law.” Wheatley v. Baugh, 25 Pa. 528, 64 Am. Lec. 721. Horner v. Watson, 79 Penn. St. 242, 21 Am. Rep. 55.
In the last named ease the court, citing a number of autorities, held that the surface owner having the right to subjacent support, the defendant had no right to withdraw the pillars in its mine and drain the waters above, and if it did so, it would be liable for the wrongful act, regardless 'of custom or negligence.
In Gumbert v. Kilgore, 6 Cent. Rep. 406, it was pointedly held: “The owner of the coal is liable to the surface owner if a spring is ruined through failure to support the surface properly, but not where the injury
To the same effect is section 939, 3 Farnham on Waters, where, after stating that “the owner of the minerals has the right to use all waters found percolating therein, although the effect is to cut off the supply of water to the surface springs,” it is said: “But where the surface and the mine belong to different owners, the owner of the mine has no right to carry on his operations in. such a way as to remove the surface support, so that, if he does so, and a spring is destroyed as a result of his wrongful act, he is liable.” See also 1 Barringer & Adams on L. of Mines, supra, p. 678; Hart v. Jamaica, &c. Corporation, 133 Mass. 489.
As observed, the plaintiff in this ease is not claiming any damages that resulted from defendant driving the regular entries, rooms and other usual excavations that it had a right to make in removing its coal underlying the plaintiff’s surface land, but is seeking reparation of an injury alleged to have been sustained by the unlawful and wrongful act of the defendant in withdrawing the surface support to which plaintiff was entitled; and plaintiff’s instruction No. 1, we think, fairly submitted to the jury the question whether or not, upon a preponderance of the evidence, the defendant in mining the coal in and under plaintiff’s Dotson tract of land failed to leave sufficient pillars, props or other means of support to prevent the strata overlying said coal from breaking and falling, and as a result the. said strata were so broken and caused the spring on the Dotson tract to be drained and destroyed.
Plaintiff’s instruction No. 2, to which defendant also excepted, told the jury that if they believed from the evidence that the plaintiff was entitled to recover,
That part of the instruction relating to damages resulting to the Gilliam tract was erroneous and should not have been given, since the drying up of the spring-on the Dotson tract was the -only damage that the evidence tended to prove. The same error was repeated in plaintiff’s instruction No. 3, and the. further error committed in instructing the jury that in estimating damages they might consider, not only damage, if any, resulting from the drying up of the spring on the' Dotson land, but the decrease, if any, in the value of the plaintiff’s' land for residence and other purposes. The latter part of the instruction, which is erroneous, is predicated upon testimony erroneously admitted by the court over the objection of the defendant, that plaintiff’s land was close enough to the town of Wise to be divided into lots and tracts and sold for homes. Clearly, such damage was too remote and speculative to be proper for the consideration of the jury upon any issue in the case.
Plaintiff’s instructions Nos. 4 and 5, which appear in the official report of the case, were,, for the reasons stated in considering plaintiff’s instruction No. 1, properly given to the jury.
The court having given to the jury plaintiff’s instructions Nos. 1, 4 and 5, it did not err in refusing an instruction asked by the defendant which sought to have the jury told “that even though they should believe from the evidence that the spring of the plaintiff on the J. A. Dotson tract of land was sunk or caused to go dry by reason of the mining of the coal thereunder,
The defendant, however, asked for the same instruction, omitting the latter part of it, namely, the words “and this is true even though the jury shall believe that the defendant did not in mining out the coal under the J. A. Dotson tract, leave sufficient pillars or props to uphold and keep intact the strata overlying the vein of coal so mined,” which the court refused, and this ruling, we think, was error, for the reasons already sufficiently stated in this opinion.
The defendant asked another and a very lengthy instruction, relating to its rights in mining out the coal under the lands adjacent to and binding on the J. A. Dotson tract of land, which instruction the. court gave in a modified form, and this ruling is assigned as error. With respect to this instruction and its modification by the court, we deem it only necessary to say that the instruction as offered was well calculated to confuse the minds of the jurors and to mislead them, to the prejudice of the defendant, in their consideration and determination of the facts which the relevant testimony in the case tended to prove, and, therefore, the' instruction, even as modified, should not have been given.
Assignments of error four to thirteen, inclusive, relate to the rulings of the court permitting certain witnesses for the plaintiff to testify, over defendant’s objection, with respect to damage to the Gilliam tract by reason of the spring on the Dotson tract going dry. As observed, the spring on the Gilliam tract was dry at the time plaintiff bought it, and as the defendant contends, he had no right of action for this. 4 Min. Inst., Pt. 1, p. 452; Com’th ex rel, &c. v. Wampler, 104 Va. 337, 51 S. E. 737, 1 L. R. A. (N. S.) 149, 113 Ann. St. Rep. 1039, 7 Ann. Cas. 422. But the plaintiff having become the owner of the surface of a contiguous boundary embracing both the Dotson and Gilliam tracts, and before the diversion of the spring on the Dotson tract, he undoubtedly had the right to the use of the water from that spring on any part of his land, and if the defendant unlawfully and wrongfully destroyed the said spring, evidence of resulting damages, if any, to the Gilliam land was competent and relevant evidence for the consideration of the jury in ascertaining the damages, if any, that plaintiff should recover. •Upon examination of the testimony given by the wit
Assignments 15, 16 and 17 relate to the action of the court in permitting certain questions to be propounded to plaintiff’s witness, Malcolm Smith, and requiring him to answer the same. These questions sought the witness’ opinion as an expert, and all we deem it necessary to say with respect to the questions is that the hypothesis assumed in them was not supported by any evidence in the case, and, therefore, the answers of the witness to the questions, which were rather vague and indefinite, were well calculated to confuse and mislead the jury to the prejudice of the defendant.
Assignment of error 18 relates to the refusal of the court to allow defendant’s witness, Cheney, to testify that if the defendant had been compelled to leave enough coal in said mines to support the roof and all overlying strata, defendant would have been compelled to leave all the coal in place, as it would not have been safe to take out any of the coal, and the same would be the effect upon all the coal mines in that region. The court properly permitted this witness and others to testify that a coal operator could not tell beforehand
•Assignment of error 19, relating to the action of the court in overruling defendant’s motion that the jury be allowed a view of the premises, is without merit, since there is nothing in the record to take the case out of the control of the general rule that such motions are addressed to the sound discretion of the trial court, and the ruling of the trial court thereon will not be reversed by the appellate court, unless it appears from the record that a view was necessary to a just decision. B. & O. R. Co. v. Polly Woods, 14 Gratt. (55 Va.) 447.
The remaining assignment of error relates to the refusal of the court to set aside the verdict of the jury
Reversed.