80 N.J.L. 549 | N.J. | 1910
The opinion of the court was delivered by
This action was brought under the third section of the Mechanics’ Lien act, to recover money due to the plaintiff from William Mosher. The contract price for the building was $2,500, payable in installments, as follows: $500'when the frame was up; $700 when the sides and roof were on; $500 when the floors were laid, partitions set and rough plumbing in; $400 when the outside work was finished and one coat of paint on, the leaders up and the plumbing fixtures on the premises; and the final payment of $400 when the building was completed and accepted by the owner. The contract contained the usual clause, permitting the owner to provide material and workmen to finish the work and deduct the expense from the amount of the contract in case of default by the contractor. No question is raised as to the validity of the notice by the plaintiff. The contest is over the amount due from Corcoran to Mosher, applicable to the plaintiff’s claim. The state of the case shows that the first payment of $500 was made; that $500 was paid on account of the second payment, leaving $200 thereof unpaid; that shortly after service of the notice Corcoran admitted service of the notice and that there was due Mosher $700; that at that time Mosher had completed sufficient work on the building to entitle him to the $200 due on the second payment and the full amount of the third payment.' • Some time after this Mosher ceased work on the building, and Corcoran completed it at an expense of $1,457. Deducting from the contract price this amount and the $1,000 airead]' paid, the balance left would be only $43. The plaintiff’s claim was $475, and for that amount and interest the District Court gave judgment.
Shortly stated, the question to be decided is whether the cost of completing the building is a first lien upon the unpaid balance of the contract price, or whether it is subject to the amount which the plaintiff sought to impound by his stop no
There is no substance in the contention that the money was not due for the reason that Mosher had never produced an architect’s certificate as required by the contract. The contract was unusual, in that it named A. N. Simpson as architect, but provided for certificates under the hand of Corcoran, the owner; and while the subsequent provision of the contract is that a certificate shall be produced, signed by the architect, it is quite evident that this inconsistency arises from the failure to change a printed blank to accord with the provision requiring a certificate under the hand of Corcoran. Corcoran was himself the owner, and his subsequent admission to the plaintiff that the amount of $700 was due to Mosher, was a waiver on his part of the necessity of producing any written certificate under his own hand, if a waiver had been necessary.
The trial court allowed the plaintiff interest, and it is said that Corcoran is not chargeable with interest. This contention overlooks the real situation. The plaintiff is seeking to recover a debt due from Mosher. On that debt he is entitled to interest. In theory of law Corcoran does not pay the debt out of his own money, but he pays it out of money due to Mosher, and is entitled to credit for it in his settlement with Mosher. There seems to be no reason why the plaintiff should not have interest out of the fund which is more than sufficient to pay the whole amount for which the District Court rendered judgment.
The judgment-is therefore affirmed, with costs, and the plaintiff may enter judgment in this court for the amount.