Nick and Donna Stom (“Appellants”) appeal from the judgment of the Circuit Court of Camden County finding in their favor on a breach of contract claim against St. Clair Corporation (“Respondent”) but awarding them no damages. We reverse and remand.
Appellants contracted with Respondent to construct a sunroom on their home in Sunrise Beach, Missouri. Respondent completed construction and was paid $9,250. Appellants were dissatisfied with the windows in the sunroom because they had wanted double pane thermal windows instead of the single pane windows that were installed. The contract between Appellants and Respondent, however, had not called for double pane thermal windows. Nonetheless, when Appellants informed Respondent of their complaint, Respondent returned to their home and replaced the windows with double pane thermal windows, using the same frames that were used for the single pane windows.
After the double pane windows were installed, Appellants complained of water leakage in the sunroom when wind blew rain against the windows. Appellant Nick Stom (“Nick”) testified at trial that the windows were not sitting squarely in the frames, causing water leakage. Nick stated that the windows were “cocked” and that Mike McCarroll (“McCarroll”), Respondent’s production supervisor, told him that was because the adjusting screws in the windows were stripped. Appellants notified Respondent- about the leakage problem, but when they received no response, they contracted with Harold Haines, Inc. (“Haines”) to remedy the problem. Haines’s work consisted of replacing the windows and the wall pieces which held the tracking hardware for the window frames, for which Appellants paid a total contract price of $7,895.27. Nick testified that the sunroom was basically the same sunroom after Haines’s work as that which Appellants had ordered from Respondent, but the evidence also indicated that after Haines’s work the sunroom contained more windows than had been installed by Respondent.
Appellants filed suit and were granted a default judgment against Respondent. Respondent filed a motion to set aside the judgment and a request to file responsive pleadings out of time. It appears that the trial court granted this motion, although the record does not contain any responsive pleadings that may have been filed by Respondent. After a bench trial, the trial court entered judgment for the plaintiff stating,
[Tjhe Court finds the issue of liability in favor of [Appellants]. As to the issue of damages the Court finds that [Appellants] have failed to prove damages in that no evidence was introduced re diminished value only cost of repair. Therefore, the Court enters judgment for [Appellants] as to liability. Awards damages of zero. Costs of this action assessed to [Respondent]. Clerk to send copy of this docket sheet to Attorneys of record. [Signed/Bruce E. Col-yer Judge.] Also all exhibits to be returned to attorneys. BEC.
Appellants’ motion for new trial was overruled. This appeal followed.
The evidence indicated that McCarroll oversaw the construction of a standard sunroom at Appellants’ home. He testified that although Respondent only sells
Appellants present one point on appeal, claiming that the trial court erred in finding zero damages for Appellants “because the burden of presenting evidence [that] the cost of repairing or replacing property is disproportionate to the diminution in value of property is on the contractor,” and the trial court placed this burden on Appellants. In support of their contention, Appellants cite
Ken Cucchi Const., Inc. v. O’Keefe,
Respondent agrees that
Ken Cucchi Const, Inc.
is factually similar to the present case and that it presents the general rule for calculating damages in a breach of contract case. Respondent contends, however, that in this case it substantially complied with the contract and that in such instances, the proper measure of damages is an amount that “will reasonably compensate [Appellants] for defects in the building due to unskillful labor or defective materials and for items omitted by [Respondent] in the performance of the agreement.”
Mathis v. Glover,
We will sustain the judgment of the trial court in a court-tried case unless
Neither party requested that the trial court make specific findings of fact and conclusions of law. In such situations, “all issues of fact on which no specific findings were made are considered to have been found in accordance with the judgment.”
Ankrom v. Roberts,
Because the trial court found the issue of liability in favor of Appellants, it must have found that Respondent breached its contract with Appellants. The appropriate measure of damages is the only issue on appeal. As indicated, Respondent asserts this is a case of substantial compliance with the contract, and that the measure of damages should therefore be an amount to compensate for the defects in the building due to unskillful labor or defective materials.
Mathis,
“The general rule in calculating damages for a breach of contract is that the non-breaching party is entitled to the cost of repairing or replacing the defective work.”
Ken Cucchi Const., Inc.,
The trial court, in its judgment, appears to have favored the diminished value rule for determining damages over the general rule of cost of repair or replacement when it said, “As to the issue of
Since both parties presented evidence on the cost of repair or replacement, “[i]t is up to the trier of fact to judge the credibility and weight to be given to the evidence at trial.”
Walker v. Hanke,
